阅读说明:本技术 一种铝土矿原位溶浸开采方法 (Bauxite in-situ leaching mining method ) 是由 李志忠 罗腾跃 张毅 于 2021-08-17 设计创作,主要内容包括:本发明涉及铝土矿产开采技术领域,尤其涉及一种铝土矿原位溶浸开采方法。一种铝土矿原位溶浸开采方法,包括如下步骤:(1)钻井工程;(2)矿层改造;(3)溶浸作业;(4)地面作业。本发明利用原位溶浸采矿技术优势,通过建立注采井网,压裂改造,配合地面处理,形成一套用于铝土矿原位溶浸开采模式,区别于传统的铝土矿露天开挖和巷洞掘进开采方式,既能实现铝土矿经济高效开采,又能节土、节水,保护矿山环境,有效解决了铝土矿开采对环境破坏的难题。(The invention relates to the technical field of bauxite exploitation, in particular to an in-situ leaching exploitation method of bauxite. An in-situ leaching mining method for bauxite comprises the following steps: (1) drilling engineering; (2) modifying the ore bed; (3) leaching operation; (4) and (5) performing ground operation. The invention utilizes the technical advantages of in-situ leaching mining, forms a set of in-situ leaching mining mode for bauxite by establishing an injection-mining well pattern, fracturing and reforming and matching with ground treatment, is different from the traditional open-pit excavation and roadway excavation mining modes of bauxite, can realize economical and efficient mining of bauxite, save soil and water, protect the mine environment and effectively solve the problem of environmental damage caused by bauxite mining.)

1. An in-situ leaching exploitation method of bauxite is characterized in that: the method comprises the following steps:

(1) drilling engineering:

a slave well is adopted; the ground well site (1) adopts a linear well arrangement, and the distance between well heads is more than 5 m; distributing injection and production well patterns by an inverse nine-point method, an inverse seven-point method or an inverse five-point method; well spacing is 50-100 m; the system comprises a liquid injection well (5) and a drainage and production well (3), wherein the liquid injection well (5) is positioned in the middle position, and the drainage and production well (3) is positioned in the peripheral position; wherein, the liquid injection well (5) is a vertical well, the drainage and production well (3) is a directional well, the maximum inclination angle of the track (4) of the directional well is not more than 35 degrees, the inclination is reduced after entering the bauxite layer (7), and the inclination angle is less than 10 degrees; drilling 20m after drilling through an upper strata (6) of bauxite, a bauxite layer (7) to a bottom bedrock (8) of the bauxite, and completing the well by adopting a sleeve (10);

(2) modifying the ore bed:

the liquid injection well (5) is provided with a perforation section (11) at the top of the bauxite layer (7), and the drainage and mining well (3) is provided with a perforation section (11) at the bottom of the bauxite layer (7);

drilling a first horizontal drilling hole (23) at a position which is 0.5m away from a top plate of the ore layer of the bauxite at the top of the bauxite layer (7) by taking the liquid injection well (5) as an initial end and the drainage and mining well (3) as a termination end, wherein the first horizontal drilling hole (23) horizontally extends from the liquid injection well (5) to the drainage and mining well (3) in parallel with the top plate of the ore layer of the bauxite, and the first horizontal drilling hole (23) is not communicated with the drainage and mining well (3);

drilling a second horizontal drilling hole (12) at a position 0.5m away from the bottom plate of the bauxite layer at the bottom of the bauxite layer (7) by taking the drainage and mining well (3) as an initial end and the liquid injection well (5) as a termination end; the second horizontal drilling hole (12) inclines upwards from the drainage and production well (3) to the injection well (5) at an inclination angle not exceeding 5 degrees, and the second horizontal drilling hole (12) is not communicated with the injection well (5);

hydraulic fracturing or blasting permeation enhancement is carried out on the injection well (5), a fracturing crack (13) is formed in the bauxite layer (7), and a seepage channel is established;

(3) leaching operation:

injecting a leaching solution from a liquid injection well (5), entering a bauxite layer (7) through a perforation section (11) of the liquid injection well (5) and a first horizontal drilling hole (23), and infiltrating and eroding bauxite downwards through a fracturing crack (13); then the second horizontal drilling hole (12) and the seepage of the perforation section (11) of the discharging and extracting well (3) flow to the bottom of the discharging and extracting well (3), and then the leaching solution containing bauxite is extracted to the ground;

(4) ground operation:

after the leaching solution containing bauxite is settled, the leaching solution containing bauxite is separated, extracted and purified in sequence to realize recycling.

2. The in-situ leaching mining method of bauxite according to claim 1, wherein: in the process of modifying the ore bed: if the clay mineral content in the bauxite exceeds 40 percent, blasting is adopted to increase the permeability; if the clay mineral content in the bauxite is lower than 40%, hydraulic fracturing is adopted.

3. The in-situ leaching mining method of bauxite according to claim 2, wherein: the leaching solution comprises an acid leaching solution and an alkaline leaching solution; if the silicon dioxide content of the bauxite is higher than 20%, selecting an acidic leaching solution, otherwise selecting an alkaline leaching solution.

4. The in-situ leaching mining method of bauxite according to claim 3, wherein: when the leaching solution is an acid leaching solution, the sleeve (10) is made of an acid-resistant material sleeve (10), otherwise, the leaching solution is an alkaline leaching solution, and the sleeve (10) is made of an alkali-resistant material sleeve (10).

5. The in-situ leaching mining method of bauxite according to claim 4, wherein: when the leaching solution is injected, the concentrated pressurization is adopted, and the leaching solution containing bauxite is extracted to the ground through concentrated negative pressure extraction or underground liquid drainage.

6. The in-situ leaching mining method of bauxite according to claim 5, wherein: the ground operation comprises an injection and production area and a leaching solution treatment area (21), wherein the injection and production area comprises a production area and an injection area; the leaching solution containing bauxite is firstly settled in a production area and then is conveyed to a leaching solution treatment area (21) to be sequentially separated, extracted, purified and prepared to form new leaching solution, and the new leaching solution is injected into an injection well (5) through an injection area to realize cyclic utilization.

7. The in-situ leaching mining method of bauxite according to claim 6, wherein: the extraction area comprises a settling tank (14), the leaching solution treatment area (21) comprises a separation device (16), an extraction device (22), a purification treatment device (17) and a leaching solution preparation device (18) which are sequentially connected, and the injection area comprises a leaching solution tank (19); wherein, one end of the settling tank (14) is connected to a wellhead device (24) of the drainage and production well, and the other end is connected with the separation device (16); one end of the leaching solution tank (19) is connected with the leaching solution preparation device (18), and the other end is connected with a wellhead device (9) of the liquid injection well.

8. The in-situ leaching mining method of bauxite according to claim 7, wherein: and pressurizing devices are arranged between the settling tank (14) and a wellhead device (24) of the drainage and production well, between the leaching solution tank (19) and the wellhead device (9) of the liquid injection well.

9. The in-situ leaching mining method of bauxite according to claim 8, wherein: the pressurizing device is a pump room (15).

10. The in-situ leaching mining method of bauxite according to claim 9, wherein: the drilling of the first horizontal drilling hole (23) and the second horizontal drilling hole (23) is realized by a high-pressure jet drill bit.

Technical Field

The invention relates to the technical field of bauxite exploitation, in particular to an in-situ leaching exploitation method of bauxite.

Background

Currently, bauxite mining worldwide mainly adopts two types of open-pit excavation and roadway excavation mining, and aims at exposed ore surfaces or ore deposits buried shallowly. The method is characterized in that the method enters a mining stage after the mineral reserve is ascertained, a large amount of capital needs to be invested in the period for stripping a ground surface covering layer or building a roadway hole, and the method has the advantages of large engineering quantity, long construction period, high cost of manpower and material resources invested in the mining process and high safety risk. In addition, open pit mines and hole mining can cause huge environmental damage to the ore body and the periphery, including surface stripping to form pits, damage to vegetation, water and soil loss, tailing pollution and the like, and cause that the mine area is often black water crossflow, surface full-mesh bruise, and sky loess.

The in-situ mining technology has experimental records at the beginning of the twentieth century, and is widely used for mining uranium ores and rare earth ores at home and abroad at present, namely, a specific leaching solution is injected into a target ore body by using a liquid injection well, useful metals are leached through a series of physical and chemical reactions, the leaching solution is extracted out of the earth surface by using a liquid extraction well, and the process of extracting the useful metals is realized in earth surface factories. Bauxite is essentially a residual rock formed under the action of near-surface strong weathering, belongs to sedimentary rock, and is found through research: the bauxite has certain permeability and has geological conditions of in-situ leaching exploitation, so the invention provides the in-situ leaching exploitation technology suitable for the bauxite in deep and shallow layers.

Disclosure of Invention

The invention aims to solve the problems and provides a green, environment-friendly, soil-saving, efficient and safe bauxite mining method, which can realize the mining of deep and shallow bauxite and the effective recovery of leaching solution.

The technical scheme of the invention is as follows:

an in-situ leaching mining method for bauxite comprises the following steps:

(1) drilling engineering:

a slave well is adopted; the ground well site adopts a linear well arrangement, and the distance between well heads is more than 5 m; distributing injection and production well patterns by an inverse nine-point method, an inverse seven-point method or an inverse five-point method; well spacing is 50-100 m; the system comprises a liquid injection well and a drainage and production well, wherein the liquid injection well is positioned in the middle, and the drainage and production well is positioned at the peripheral position; wherein, the liquid injection well is a vertical well, the drainage and extraction well is a directional well, the maximum well inclination angle of the track of the directional well is not more than 35 degrees, the slope is reduced after entering a bauxite layer, and the well inclination angle is less than 10 degrees; drilling a well 20m after the well penetrates through the upper strata of the bauxite, the bauxite layer to the bottom bedrock of the bauxite, and completing the well by adopting a casing;

(2) modifying the ore bed:

the liquid injection well is provided with a perforation section at the top of the bauxite layer, and the drainage and mining well is provided with a perforation section at the bottom of the bauxite layer;

drilling a first horizontal drilling hole at a position which is 0.5m away from a top plate of the ore layer of the bauxite at the top of the bauxite layer by taking the liquid injection well as an initial end and the drainage and mining well as a final end, wherein the first horizontal drilling hole horizontally extends from the liquid injection well to the drainage and mining well in parallel with the top plate of the ore layer of the bauxite, and the first horizontal drilling hole is not communicated with the drainage and mining well;

drilling a second horizontal drilling hole at the position 0.5m away from the bottom plate of the ore bed of the bauxite at the bottom of the bauxite bed by taking the drainage and mining well as the starting end and the liquid injection well as the stopping end; the second horizontal drilling hole inclines upwards from the drainage and production well to the liquid injection well at an inclination angle not more than 5 degrees, and the second horizontal drilling hole is not communicated with the liquid injection well;

hydraulic fracturing or blasting permeation enhancement is carried out on the injection well, a fracturing crack is formed in the bauxite layer, and a seepage channel is established;

(3) leaching operation:

injecting a leaching solution from the injection well, entering the bauxite layer through the perforation section and the first horizontal drilling hole of the injection well, and leaching and corroding the bauxite downwards through a fracturing crack; then, the second horizontal drilling and the seepage of the perforation section of the discharge and production well flow to the bottom of the discharge and production well, and then the leaching solution containing bauxite is extracted to the ground;

(4) ground operation:

after the leaching solution containing bauxite is settled, the leaching solution containing bauxite is separated, extracted and purified in sequence to realize recycling.

Preferably, in the process of modifying the ore bed: if the clay mineral content in the bauxite exceeds 40 percent, blasting is adopted to increase the permeability; if the clay mineral content in the bauxite is lower than 40%, hydraulic fracturing is adopted.

Or preferably, the leaching solution comprises an acidic leaching solution and an alkaline leaching solution; if the silicon dioxide content of the bauxite is higher than 20%, selecting an acidic leaching solution, otherwise selecting an alkaline leaching solution.

More preferably, when the leaching solution is an acidic leaching solution, the sleeve is made of an acid-resistant material, otherwise, the leaching solution is an alkaline leaching solution, and the sleeve is made of an alkali-resistant material.

Preferably, the leaching solution is injected by centralized pressurization, and the leaching solution containing bauxite is extracted to the ground by centralized negative pressure extraction or downhole liquid drainage.

Or preferably, the ground operation comprises an injection and production area and a leaching solution treatment area, wherein the injection and production area comprises a production area and an injection area; the leaching solution containing bauxite is firstly settled in a production area and then is conveyed to a leaching solution treatment area to be sequentially separated, extracted, purified and prepared to form new leaching solution, and the new leaching solution is injected into a liquid injection well through an injection area to realize cyclic utilization.

More preferably, the extraction area comprises a settling tank, the leaching solution treatment area comprises a separation device, an extraction device, a purification treatment device and a leaching solution preparation device which are sequentially connected, and the injection area comprises a leaching solution tank; one end of the settling tank is connected to a wellhead device of the drainage and production well, and the other end of the settling tank is connected with the separation device; one end of the leaching solution tank is connected with the leaching solution preparation device, and the other end of the leaching solution tank is connected to a wellhead device of the liquid injection well.

More preferably, a pressurizing device is arranged between the settling tank and a wellhead device of the drainage and production well, and between the leaching solution tank and a wellhead device of the liquid injection well.

More preferably, the pressurizing device is a pump room.

Or preferably, the drilling of the first horizontal drilling hole and the second horizontal drilling hole is realized by a high-pressure jet drill bit.

The invention has the technical effects that:

the invention utilizes the technical advantages of in-situ leaching mining, forms a set of in-situ leaching mining mode for bauxite by establishing an injection-mining well pattern, fracturing and reforming and matching with ground treatment, is different from the traditional open-pit excavation and roadway excavation mining modes of bauxite, can realize economical and efficient mining of bauxite, save soil and water, protect the mine environment and effectively solve the problem of environmental damage caused by bauxite mining.

Drawings

FIG. 1 is a schematic diagram of the in-situ leaching mining technology for bauxite according to the present invention.

FIG. 2 is a plan well plan of the process of in situ leaching mining of bauxite provided by the practice of the present invention.

FIG. 3 is a schematic cross-sectional view of the bauxite mining process in situ leaching mining.

Reference numerals: 1. a ground well site; 2. a ground wellhead; 3. discharging and extracting wells; 4. orienting a well trajectory; 5. a liquid injection well; 6. an overlying formation; 7. a layer of bauxite; 8. a bauxite bottom bedrock; 9. a wellhead assembly of the fluid injection well; 10. a sleeve; 11. a perforation section; 12. a second horizontal bore; 13. fracturing the crack; 14. a settling tank; 15. a pump house; 16. a separation device; 17. a purification treatment device; 18. a leaching solution preparation device; 19. a leaching solution tank; 20. injecting and producing areas; 21. a leaching solution treatment zone; 22. an extraction device; 23. a first horizontal bore; 24. and a wellhead device for the drainage and production well.

Detailed Description

In order to make the technical problems, technical solutions and advantageous effects to be solved by the present invention more clearly apparent, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.

An in-situ leaching mining method for bauxite comprises the following steps:

(1) drilling engineering:

a slave well is adopted; the ground well site 1 adopts a linear well arrangement, and the well mouth spacing is more than 5 m; distributing injection and production well patterns by an inverse nine-point method, an inverse seven-point method or an inverse five-point method; well spacing is 50-100 m; the system comprises a liquid injection well 5 and a drainage and production well 3, wherein the liquid injection well 5 is positioned in the middle, and the drainage and production well 3 is positioned at the peripheral position; wherein, the liquid injection well 5 is a vertical well, the drainage and production well 3 is a directional well, the track 4 of the directional well needs to be noticed to prevent collision and obstacle detouring, the maximum well inclination angle is not more than 35 degrees, the well inclination angle is reduced after entering the bauxite layer 7, and the well inclination angle is less than 10 degrees; drilling a well to penetrate through an upper strata 6 and a bauxite layer 7 of the bauxite to 20m behind a bottom bedrock 8 of the bauxite, and completing the well by adopting a sleeve 10;

(2) modifying the ore bed:

the liquid injection well 5 is provided with a perforation section 11 at the top of the bauxite layer 7, and the drainage and mining well 3 is provided with a perforation section 11 at the bottom of the bauxite layer 7;

drilling a first horizontal drilling hole 23 at a position which is 0.5m away from the top of the bauxite layer 7 from the top plate of the bauxite layer by taking the liquid injection well 5 as an initial end and the drainage and mining well 3 as a termination end, wherein the first horizontal drilling hole 23 extends horizontally from the liquid injection well 5 to the drainage and mining well 3 in parallel to the top plate of the bauxite layer, and the first horizontal drilling hole 23 is not communicated with the drainage and mining well 3;

drilling a second horizontal drilling hole 12 at a position 0.5m away from the bottom plate of the ore layer of the bauxite at the bottom of the bauxite layer 7 by taking the drainage and mining well 3 as an initial end and the injection well 5 as a termination end; the second horizontal drilling hole 12 inclines upwards from the drainage and production well 3 to the injection well 5 at an inclination angle not exceeding 5 degrees, and the second horizontal drilling hole 12 is not communicated with the injection well 5;

forming a fracturing crack 13 in the bauxite layer 7 by hydraulic fracturing or blasting permeation enhancement on the liquid injection well 5, and establishing a seepage channel;

(3) leaching operation:

injecting a leaching solution from the injection well 5, entering the bauxite layer 7 through the perforation section 11 of the injection well 5 and the first horizontal drilling hole 23, and leaching and corroding the bauxite downwards through the fracturing crack 13; then the second horizontal drilling hole 12 and the seepage of the perforation section 11 of the discharging and extracting well 3 flow to the bottom of the discharging and extracting well 3, and then the leaching solution containing bauxite is extracted to the ground;

(4) ground operation:

after the leaching solution containing bauxite is settled, the leaching solution containing bauxite is separated, extracted and purified in sequence to realize recycling.

Example 2

An in-situ leaching mining method for bauxite comprises the following steps:

(1) drilling engineering:

a slave well is adopted; the ground well site 1 adopts the in-line well arrangement, a drilling machine slides to the last notch from the first notch one by one, and the minimum well mouth distance is set to be 5m in order to meet the anti-collision requirement; arranging injection and production well patterns by an inverse nine-point method, an inverse seven-point method or an inverse five-point method, wherein the well spacing is 50-100 m; the system comprises 1 liquid injection well 5 and 8 drainage and production wells 3, wherein the liquid injection well 5 is positioned in the middle, and the drainage and production wells 3 are positioned at the peripheral positions; the liquid injection well 5 is a vertical well, the drainage and production well 3 is a directional well, the track 4 of the directional well needs to be noticed to prevent collision and obstacle avoidance, the maximum well inclination angle is not more than 35 degrees, the well inclination angle is reduced after entering a bauxite layer 7, the well inclination angle is less than 10 degrees, the risk of later-stage horizontal drilling and fracturing construction is reduced, and the drainage construction operation of the later-stage drainage and production well 3 is facilitated; the liquid injection well 5 and the drainage and mining well 3 are drilled through the upper strata 6 of the bauxite, the bauxite layer 7 to the bottom bedrock 8 of the bauxite 20m later and are completed by a sleeve 10; wherein, if the silicon dioxide content of the bauxite is higher than 20%, the leaching solution is an acidic leaching solution, the sleeve 10 made of an acid-resistant material is selected corresponding to the sleeve 10, otherwise, the leaching solution is an alkaline leaching solution, and the sleeve 10 is an alkali-resistant sleeve 10;

(2) modifying the ore bed:

the liquid injection well 5 is provided with a perforation section 11 at the top of the bauxite layer 7, and the drainage and mining well 3 is provided with a perforation section 11 at the bottom of the bauxite layer 7;

drilling a first horizontal drilling hole 23 at a position which is 0.5m away from the top of the bauxite layer 7 from the top plate of the bauxite layer by taking the liquid injection well 5 as an initial end and the drainage and mining well 3 as a termination end, wherein the first horizontal drilling hole 23 extends horizontally from the liquid injection well 5 to the drainage and mining well 3 in parallel to the top plate of the bauxite layer, and the first horizontal drilling hole 23 is not communicated with the drainage and mining well 3;

drilling a second horizontal drilling hole 12 at a position 0.5m away from the bottom plate of the ore layer of the bauxite at the bottom of the bauxite layer 7 by taking the drainage and mining well 3 as an initial end and the injection well 5 as a termination end; the second horizontal drilling hole 12 inclines upwards from the drainage and production well 3 to the injection well 5 at an inclination angle not exceeding 5 degrees, and the second horizontal drilling hole 12 is not communicated with the injection well 5;

the number of the second horizontal drilling holes 12 between the liquid injection well 5 and the drainage and production well 3 can be one or more;

forming a fracturing crack 13 in the bauxite layer 7 by hydraulic fracturing or blasting permeation enhancement on the liquid injection well 5, and establishing a seepage channel;

wherein, if the clay mineral content in the bauxite exceeds 40 percent, blasting is adopted to increase the permeability; if the clay mineral content in the bauxite is lower than 40%, hydraulic fracturing is adopted;

two-way parallel horizontal drilling holes (a first horizontal drilling hole 23 and a second horizontal drilling hole 12) are arranged between the injection well 5 and the drainage and production well 3, leaching liquid enters the bauxite layer 7 through the first horizontal drilling hole 23 of the injection well 5, seeps along the fracturing crack 13, leaches the bauxite, and flows into the second horizontal drilling hole 12 of the drainage and production well 3, and the leaching liquid containing the bauxite is convenient to recover because the second horizontal drilling hole 12 of the drainage and production well 3 has an inclination angle of 5 degrees;

the arrangement of the bidirectional parallel horizontal drilling holes is beneficial to the reconstruction of the bauxite layer 7, so that effective cracks can be formed at the near well section and the far well section, a seepage passage with a larger range is established, the full contact between leaching solution and bauxite is facilitated, and the leaching rate is improved; the second horizontal drilling hole 12 is positioned at the bottom of the bauxite layer 7, so that the recovery of bauxite leaching solution is mainly facilitated, the leaching solution leakage is prevented, the leaching solution recovery rate is improved, and better economic benefits are realized, therefore, the second horizontal drilling hole 12 between the injection well 5 and the discharge and extraction well 3 is not limited to one, and a plurality of second horizontal drilling holes can be designed;

(3) leaching operation:

injecting leaching solution from the injection well 5 through centralized pressurization, entering the bauxite layer 7 through the perforation section 11 of the injection well 5 and the first horizontal drilling hole 23, and leaching and corroding bauxite downwards through the fracturing crack 13; then the second horizontal drilling hole 12 and the seepage of the perforation section 11 of the drainage and production well 3 flow to the bottom of the drainage and production well 3, and the leaching solution containing bauxite is extracted to the ground by means of centralized negative pressure extraction or down-hole drainage process;

(4) ground operation:

the ground operation comprises an injection production area 20 and a leaching solution treatment area 21, wherein the injection production area 20 comprises a production area and an injection area; the extraction area comprises a settling tank 14, the leaching solution treatment area 21 comprises a separation device 16, an extraction device 22, a purification treatment device 17 and a leaching solution preparation device 18 which are connected in sequence, and the injection area comprises a leaching solution tank 19; wherein, one end of the settling tank 14 is connected to a wellhead device 24 of the drainage and production well, and the other end is connected with the separation device 16; one end of the leaching solution tank 19 is connected with the leaching solution preparation device 18, and the other end is connected with the wellhead device 9 of the liquid injection well. And pressurizing devices are arranged between the settling tank 14 and a wellhead device 24 of the drainage and production well, and between the leaching solution tank 19 and the wellhead device 9 of the injection well. The pressurizing device is a pump room 15. The leaching solution containing bauxite is firstly settled in the extraction area and then is conveyed to the leaching solution treatment area 21 to be sequentially separated, extracted, purified and prepared to form new leaching solution, and the new leaching solution is injected into the injection well 5 through the injection area to realize cyclic utilization.