Pile bottom grouting cavity, using method thereof, cast-in-place pile body and construction method of cast-in-place pile body

文档序号:1436425 发布日期:2020-03-20 浏览:29次 中文

阅读说明:本技术 桩底注浆腔及使用方法以及灌注桩体和灌注桩体的施工方法 (Pile bottom grouting cavity, using method thereof, cast-in-place pile body and construction method of cast-in-place pile body ) 是由 高永光 高云飞 于 2019-06-28 设计创作,主要内容包括:本发明公开了一种桩底注浆腔及使用方法以及灌注桩体和灌注桩体的施工方法,桩底注浆腔,包括:注浆胶囊,具有内部填充有浆液以承载桩体的膨胀状态,以及内部中空的收缩状态;注浆管,与所述注浆胶囊的内腔相连通,向所述注浆胶囊内注浆;单向阀,所述单向阀设置在所述注浆管与所述注浆胶囊的连通位置,以阻挡所述注浆胶囊内的堵塞物进入所述注浆管。从而避免现有技术中进入注浆胶囊内的泥沙、沉渣等混合物进入注浆管,从而堵塞注浆管的问题。(The invention discloses a pile bottom grouting cavity, a using method thereof, a cast-in-place pile body and a construction method of the cast-in-place pile body, wherein the pile bottom grouting cavity comprises: a grouting capsule having an expanded state in which grout is filled inside to bear the pile body, and a contracted state in which the interior is hollow; the grouting pipe is communicated with the inner cavity of the grouting capsule and used for grouting into the grouting capsule; the one-way valve is arranged at the communication position of the grouting pipe and the grouting capsule so as to prevent the blockage in the grouting capsule from entering the grouting pipe. Thereby avoiding the mixture such as silt, sediment and the like entering the grouting capsule from entering the grouting pipe in the prior art and further avoiding the problem of blocking the grouting pipe.)

1. A pile bottom grouting cavity, comprising:

a grouting capsule (1) having an expanded state in which the interior is filled with grout to support the pile body, and a contracted state in which the interior is hollow;

the grouting pipe (2) is communicated with the inner cavity of the grouting capsule (1) and used for grouting into the grouting capsule (1);

it is characterized by also comprising:

the one-way valve is arranged at the communication position of the grouting pipe (2) and the grouting capsule (1) so as to prevent the blockage in the grouting capsule (1) from entering the grouting pipe (2).

2. The pile bottom grouting cavity according to claim 1, characterized in that the grouting pipe (2) is provided with a grouting hole (3) for the grouting liquid to enter into the grouting capsule (1), and the one-way valve comprises: with grout hole (3) on slip casting pipe (2) set up relatively, in order to seal elastic component (4) of slip casting hole (3), elastic component (4) have with slip casting pipe (2) closely laminate in order to block the plug passes through the encapsulated situation that slip casting hole (3) got into slip casting pipe (2), and receive slip casting pipe (2) internal pressure effect orientation is kept away from slip casting pipe (2) direction removes so that the thick liquid passes through slip casting hole (3) gets into the open mode of slip casting capsule (1).

3. Pile bottom grouting cavity according to claim 2, characterised in that the grouting pipe (2) has a grouting part (5) extending into the inner cavity of the grouting capsule (1), the grouting holes (3) being arranged at the surface of the grouting part (5).

4. Pile bottom grouting cavity according to claim 3, characterised in that the elastic element (4) has a fixing part connected to the grouting part (5).

5. Pile bottom grouting cavity according to claim 3 or 4, characterised in that there are at least two grouting pipes (2), the grouting pipes (2) are connected together through the grouting part (5), and a valve for closing the grouting passage is arranged on the grouting pipe (2).

6. Pile bottom grouting cavity according to claim 5, characterised in that the grouting part (5) is of a tubular structure, and both ends of the grouting part (5) are respectively communicated with one grouting pipe (2).

7. Pile bottom grouting cavity according to claim 5 or 6, characterised in that the elastic element (4) is an annular sleeve placed over the grouting part (5) of the tubular structure.

8. Pile bottom grouting cavity according to any of claims 2-7, characterised in that the grouting holes (3) are multiple and arranged on the surface of the grouting part (5).

9. The pile bottom grouting cavity according to any one of claims 1 to 8, further comprising a fixing plate (6), wherein the grouting capsule (1) is arranged on the fixing plate (6), and the grouting capsule (1) and the fixing plate (6) enclose a containing cavity for containing grout.

10. Pile bottom grouting cavity according to claim 9, characterised in that the grouting capsule (1) is provided with a capsule detection port (11) for filling medium into the interior thereof.

11. Pile bottom grouting chamber according to claim 10, characterised in that the capsule detection port (11) is provided on the fixing plate (6).

12. The pile bottom grouting cavity of claim 10, wherein the medium is air.

13. A method of using the pile bottom grouting cavity of any one of claims 1-12, comprising:

cleaning the grouting pipe (2);

and grouting into the grouting capsule (1).

14. The method for using a pile bottom grouting cavity according to claim 13, characterized in that the cleaning of the grouting pipe (2) comprises: s1, opening at least two grouting pipes (2) connected together through a grouting part (5); s2, introducing cleaning liquid into at least one grouting pipe (2) of the at least two grouting pipes (2) in the opened state, discharging the cleaning liquid from the other grouting pipe (2) which is in the opened state and is not injected with the cleaning liquid, and enabling the pressure in the grouting pipe (2) to be smaller than the pressure for opening the one-way valve.

15. The method for using the pile bottom grouting cavity according to claim 13, wherein the grouting into the grouting capsule (1) specifically comprises: and (2) introducing grout into the grouting pipe (2) in an open state, wherein the pressure in the grouting part (5) is greater than the biasing force of the elastic part (4), and the grout overflows through a gap between the elastic part (4) and the grouting part (5) and enters the grouting capsule (1).

16. A cast-in-place pile body, comprising:

the pile bottom grouting cavity of any one of claims 1 to 12;

and the reinforcement cage (7) is connected with the pile bottom grouting cavity, and the grouting pipe (2) is fixedly connected with the reinforcement cage (7).

17. A bored pile body according to claim 16, further comprising a pile-side grouting pipe (10) fixed to said reinforcement cage (7), said pile-side grouting pipe (10) having its grouting hole provided near said grouting capsule (1) for grouting toward the pile-side ground.

18. A method for constructing a bored concrete pile according to claim 16 or 17, characterized by comprising the steps of:

s1, drilling a hole by adopting a full casing pipe hole forming method to form a hole (9) for accommodating a full casing pipe (8);

s2, sinking the reinforcement cage (7) with the lower end provided with the pile bottom grouting cavity to the bottom of the hole (9);

s3, pulling out the full sleeve (8), and pouring concrete into the hole (9) at the same time, so that the reinforcement cage (7) is fixed with the inner cavity wall of the hole (9);

and S4, grouting into the grouting capsule (1) to form the pile bottom enlarged head.

19. The method of constructing a bored concrete pile according to claim 18, further comprising: and step S5, grouting towards the stratum at the side part of the pile body.

20. A method for constructing a bored concrete pile according to claim 16 or 17, characterized by comprising the steps of:

s1, forming holes by using an artificial retaining wall hole forming method to form holes (9) with artificial retaining walls;

s2, sinking the reinforcement cage (7) with the lower end provided with the pile bottom grouting cavity to the bottom of the hole (9);

s3, pouring concrete into the hole (9) to fix the reinforcement cage (7) and the inner cavity wall of the hole (9) together;

and S4, grouting into the grouting capsule (1) to form the pile bottom enlarged head.

Technical Field

The invention relates to the technical field of foundation foundations, in particular to a pile bottom grouting cavity, a using method of the pile bottom grouting cavity, a cast-in-place pile body and a construction method of the cast-in-place pile body.

Background

At present, in the field of foundation foundations, open grouting is generally adopted in post-grouting of cast-in-place piles. However, open grouting has the problems of low controllability of a grouting area, small forming effect on a pile end expanding head and a surrounding stratum, and small improvement range of the bearing capacity of the pile end.

In order to solve the problem of open grouting. In the prior art, a grouting device for a cast-in-place pile with a grouting capsule is disclosed, which comprises a grouting pipe, a steel bottom plate, a grouting interface and a grouting capsule, wherein the grouting interface extends out of the upper part and the lower part of the steel bottom plate; and the upper part of the grouting pipe is connected with a grouting pump. However, if the grouting capsule is damaged and materials such as silt and sediment enter the grouting pipe or grouting stops due to mechanical failure in the grouting process, the grouting pipe is blocked, and the quality problem that grouting cannot be completed satisfactorily is caused. Especially when the capsule takes place to damage, break before the slip casting, can lead to mixture such as a large amount of soil and silt to get into the slip casting capsule, and at this moment, the outside pressure of slip casting pipe can be greater than the inside pressure of slip casting pipe, can lead to mixture such as soil and silt to get into the slip casting pipe to block up the slip casting pipe, so that the stake end slip casting chamber can't use.

Disclosure of Invention

Therefore, the invention aims to provide a pile bottom grouting cavity, a using method thereof, a cast-in-place pile body and a construction method of the cast-in-place pile body, so as to solve the problem that in the prior art, a mixture of soil, silt, stone and the like enters a grouting pipe from the pile bottom grouting cavity to cause blockage of the grouting pipe. Therefore, the invention provides a pile bottom grouting cavity, which comprises:

a grouting capsule having an expanded state in which grout is filled inside to bear the pile body, and a contracted state in which the interior is hollow;

the grouting pipe is communicated with the inner cavity of the grouting capsule, and grout is injected into the grouting capsule and is mortar, chemical grout or cement slurry;

further comprising:

the one-way valve is arranged at the communication position of the grouting pipe and the grouting capsule so as to prevent the blockage in the grouting capsule from entering the grouting pipe.

Be provided with on the slip casting pipe and supply the thick liquids to get into the slip casting hole in the slip casting capsule, the check valve includes: the elastic piece is arranged opposite to the grouting hole in the grouting pipe to seal the grouting hole, and the elastic piece is tightly attached to the grouting pipe to block the blockage from entering the grouting pipe through the grouting hole and moves towards the direction far away from the grouting pipe under the action of the pressure in the grouting pipe to enable the grout to enter the grouting capsule through the grouting hole in the opening state.

The grouting pipe is provided with a grouting part extending into the inner cavity of the grouting capsule, and the grouting hole is arranged on the surface of the grouting part.

The elastic piece is provided with a fixing part connected with the grouting part.

The grouting pipe is at least two, the grouting pipes are communicated together through the grouting part, and a valve used for closing the grouting channel is arranged on each grouting pipe.

The grouting part is of a tubular structure, and two ends of the grouting part are respectively communicated with one grouting pipe.

The elastic part is an annular sleeve sleeved on the grouting part of the tubular structure.

The grouting holes are multiple and are arranged on the surface of the grouting part.

The pile bottom grouting cavity further comprises a fixing plate, the grouting capsule is arranged on the fixing plate, and the grouting capsule and the fixing plate enclose a containing cavity for containing grout.

And the grouting capsule is provided with a capsule detection port for filling media into the grouting capsule so as to verify whether the grouting capsule leaks or not.

The capsule detection port is arranged on the fixing plate.

The medium is air.

The use method of the pile bottom grouting cavity comprises the following steps:

cleaning the grouting pipe;

and grouting into the grouting capsule.

The use method of the pile bottom grouting cavity comprises the following steps: s1, opening at least two grouting pipes connected together through a grouting part; and S2, introducing a cleaning liquid into at least one grouting pipe of the at least two grouting pipes in the open state, discharging the cleaning liquid from the other grouting pipe which is in the open state and is not injected with the cleaning liquid, wherein the pressure in the grouting pipe is less than the pressure for opening the one-way valve.

The step of injecting the slurry into the slurry injection capsule specifically comprises the following steps: and introducing grout into the grouting pipe in an open state, wherein the pressure in the grouting part is greater than the biasing force of the elastic part, and the grout overflows through a gap between the elastic part and the grouting part and enters the grouting capsule.

A cast-in-place pile body, comprising:

a pile bottom grouting cavity;

and the reinforcement cage is connected with the pile bottom grouting cavity, and the grouting pipe is fixedly connected with the reinforcement cage.

The construction method of the cast-in-place pile body comprises the following steps:

s1, drilling a hole by adopting a full casing pipe hole forming method to form a hole for accommodating a full casing pipe;

s2, sinking the reinforcement cage with the lower end provided with the pile bottom grouting cavity to the bottom of the hole;

s3, pulling out the whole sleeve, and pouring concrete into the hole at the same time to fix the reinforcement cage and the inner cavity wall of the hole together;

and S4, grouting into the grouting capsule to form the pile bottom expanded head.

The construction method of the cast-in-place pile body comprises the following steps:

s1, forming holes by using an artificial retaining wall hole forming method to form holes with artificial retaining walls;

s2, sinking the reinforcement cage with the lower end provided with the pile bottom grouting cavity to the bottom of the hole;

s3, pouring concrete into the hole to fix the reinforcement cage and the inner cavity wall of the hole together;

and S4, grouting into the grouting capsule to form the pile bottom expanded head.

The technical scheme of the invention has the following advantages:

1. the invention provides a pile bottom grouting cavity, which comprises: a grouting capsule having an expanded state in which grout is filled inside to bear the pile body, and a contracted state in which the interior is hollow; the grouting pipe is communicated with the inner cavity of the grouting capsule and used for grouting into the grouting capsule; the one-way valve is arranged at the communication position of the grouting pipe and the grouting capsule so as to prevent the blockage in the grouting capsule from entering the grouting pipe. Through above-mentioned check valve can prevent effectively that when the circumstances such as the slip casting capsule takes place to break, when the outside pressure of slip casting pipe is greater than the inside pressure of slip casting pipe, mixture such as silt, sediment that get into in the slip casting capsule get into the slip casting pipe, or cause the slip casting to break because of mechanical failure to cause the problem of slip casting pipe jam, with the unable problem that uses in the slip casting chamber at the bottom of the pile. Moreover, sediment mixture can be effectively prevented from entering the grouting pipe through the one-way valve, and then under the condition that a grouting capsule is damaged before grouting and sediment and other mixtures enter, the grouting can be continuously performed towards the direction of the grouting capsule through the grouting pipe, or under the condition that grouting is interrupted due to mechanical faults, the grouting pipe is flushed in time to ensure that a pipeline is smooth, repeated grouting can be realized for many times, the formation of a pile end expanding head and the compaction effect on surrounding strata are ensured, and the bearing capacity of the pile end is improved.

2. The pile bottom grouting cavity provided by the invention is characterized in that the grouting pipe is provided with a grouting hole for allowing a grouting liquid to enter the grouting capsule, and the one-way valve comprises: the elastic piece is arranged opposite to the grouting hole in the grouting pipe to seal the grouting hole, and the elastic piece is in a sealing state of being tightly attached to the grouting pipe to block the blocking object from entering the grouting pipe through the grouting hole and is moved towards the direction far away from the grouting part under the action of the pressure in the grouting pipe to enable the grout to enter the grouting capsule through the grouting hole. Above-mentioned elastic component sets up the position that its and slip casting capsule are linked together at the slip casting pipe, and when the outside pressure of slip casting pipe was greater than the inside pressure of slip casting pipe, the elastic component can laminate mutually with the slip casting pipe under its self biasing force effect with the shutoff slip casting hole to avoid effectively that the plug passes through the slip casting hole and gets into the slip casting pipe in order to block up the slip casting pipe, cause the unable problem to the slip casting of stake end slip casting chamber. On the other hand, when the pressure inside the grouting pipe is larger than the pressure outside the grouting pipe, the elastic part can be deformed under the action of the pressure of liquid inside the grouting pipe, so that the elastic part is far away from the grouting hole, and the grout is discharged from the grouting pipe into the grouting capsule or enters the stratum through the damaged grouting capsule to reinforce the stratum around the pile bottom. Can take place the one-way mud discharging of slip casting pipe through the above-mentioned elastic component that deforms can simply guarantee effectively to guarantee that the unable slip casting pipe that gets into of mixture in the slip casting intracavity at the bottom of the pile, and the slip casting still can play a role at the bottom of the pile when slip casting capsule breaks, consolidates the stratum around the bottom of the pile.

3. The pile bottom grouting cavity provided by the invention is characterized in that the grouting pipe is provided with a grouting part extending into the inner cavity of the grouting capsule, and the grouting hole is arranged on the surface of the grouting part. Above-mentioned slip casting pipe has the slip casting portion that extends to in the slip casting capsule inner chamber, through arranging the slip casting hole on slip casting portion, can be fast effectively with in the slip casting capsule of thick liquid injection pile bottom, guarantee the mud discharging ability.

4. According to the pile bottom grouting cavity provided by the invention, the elastic piece is provided with the fixing part connected with the grouting part. The elastic component is fixedly connected with the grouting part, so that when grouting is carried out towards the inner cavity of the grouting capsule through the grouting hole, the elastic component deviates from a preset position under the action of grouting pressure, and the elastic component loses the sealing capacity of the grouting hole.

5. According to the pile bottom grouting cavity provided by the invention, at least two grouting pipes are arranged, the grouting pipes are communicated together through the grouting part, and a valve for closing a grouting channel is arranged on each grouting pipe. The plurality of grouting pipes are arranged, so that the plurality of grouting pipes can be opened and the slurry can be introduced into the grouting part, the elastic part can be effectively opened by the internal pressure value of the grouting part, the sufficient pressure of the grouting part is ensured, and the grouting efficiency of the grouting pipes is ensured; or opening a plurality of grouting pipes and closing other grouting pipes, and injecting grout into the opened grouting pipes to ensure that the grouting part has enough pressure and the grouting efficiency of the grouting pipes.

6. According to the pile bottom grouting cavity provided by the invention, the grouting part is of a tubular structure, and two ends of the grouting part are respectively communicated with one grouting pipe. The two end openings of the grouting part of the tubular structure are respectively communicated with one grouting pipe. When the grouting pipes are cleaned, two grouting pipes are opened simultaneously, cleaning fluid is injected into one grouting pipe, the cleaning fluid is water or other liquid, the cleaning fluid flows in through one grouting pipe and flows out through the other grouting pipe, and therefore the cleaning work of the grouting pipes can be effectively achieved; when slurry is injected into the grouting capsule, one of the two grouting pipes is opened, the other grouting pipe is closed, or the two grouting pipes are simultaneously opened to ensure that the grouting part has enough pressure to perform grouting towards the grouting capsule, and two ends of the grouting part are respectively communicated with one grouting pipe.

7. According to the pile bottom grouting cavity provided by the invention, the elastic part is an annular sleeve sleeved on the grouting part of the tubular structure. The elastic piece of the annular sleeve structure can effectively wrap the grouting part of the tubular structure, so that the elastic piece can effectively seal the grouting hole when the pressure in the grouting part is smaller than that outside the pipe, and mixtures such as sediment and sediment at the bottom of the hole can be prevented from entering the grouting pipe from all angles.

8. The pile bottom grouting cavity provided by the invention further comprises a fixing plate, the grouting capsule is arranged on the fixing plate, and the grouting capsule and the fixing plate enclose a containing cavity for containing grout. The fixing plate can be effectively connected with a reinforcement cage, and the pile bottom grouting cavity is installed and used.

9. According to the pile bottom grouting cavity provided by the invention, the grouting capsule is provided with the capsule detection port for filling media into the grouting capsule so as to verify whether the grouting capsule leaks or not. Air, water or other media are filled into the grouting capsule through the capsule detection port, so that the problems of damage, leakage and the like of the grouting capsule can be effectively verified.

10. According to the pile bottom grouting cavity provided by the invention, the capsule detection port is arranged on the fixing plate, so that the operation of a construction party can be facilitated, and the operation difficulty of a user is reduced.

11. The invention provides a using method of a pile bottom grouting cavity, which comprises the following steps: the washing slip casting pipe specifically includes: s1, opening at least two grouting pipes connected together through a grouting part; and S2, introducing a cleaning liquid into at least one grouting pipe of the at least two grouting pipes in the open state, discharging the cleaning liquid from the other grouting pipe which is in the open state and is not injected with the cleaning liquid, wherein the pressure in the grouting pipe is less than the pressure for opening the one-way valve. Through setting up above-mentioned mode can guarantee that the check valve does not open to make the washing liquid not get into the slip casting capsule, the washing liquid can be cleared up the slip casting pipe effectively.

12. The use method of the pile bottom grouting cavity provided by the invention specifically comprises the following steps of: and introducing grout into the grouting pipe in an open state, wherein the pressure in the grouting part is greater than the biasing force of the elastic part, and the grout overflows through a gap between the elastic part and the grouting part and enters the grouting capsule. When a plurality of grouting pipes can not form a liquid loop, the liquid pressure value in the grouting pipes can be effectively increased, so that the pressure in the grouting pipes is enough to open the one-way valve, grout is injected into the grouting capsule, and the normal use of the grouting cavity at the bottom of the pile is ensured.

13. The construction method of the cast-in-place pile body provided by the invention comprises the following steps: s1, drilling a hole by adopting a full casing pipe hole forming method to form a hole for accommodating a full casing pipe; s2, sinking the reinforcement cage with the lower end provided with the pile bottom grouting cavity to the bottom of the hole; s3, pulling out the whole sleeve, and pouring concrete into the hole at the same time to fix the reinforcement cage and the inner cavity wall of the hole together; and S4, grouting into the grouting capsule to form the pile bottom expanded head. Through the full sleeve pipe cooperation pore-forming, can prevent following problem effectively: when a cast-in-place pile body is formed by adopting a slurry protection wall, in the process of descending the reinforcement cage to the bottom of a hole, the reinforcement cage with the fixing plate acts like a piston in a drilling hole and is easy to form vortex in slurry water, so that slurry water current revolving between the edge of the fixing plate and the wall of the drilling hole scours and disturbs the wall of the drilling hole, the fixing plate is easy to scrape the wall of the drilling hole, the factors easily cause the wall of the drilling hole to collapse, the sediment of the drilling hole after hole cleaning exceeds the standard after the drilling hole reaches the bottom of the cast-in-place container, and simultaneously, silt collapsed from the wall of the drilling hole is easily accumulated on the fixing plate, thereby affecting the quality of the cast-in-place pile and further causing pile breakage if the diameter of the fixing plate is smaller, or other reasons such as hole collapse and over-pouring and the like can also cause the problem that a. In order to solve the problems, the hole forming of the full sleeve pipe matched cast-in-place pile body is realized, the full sleeve pipe is hard and reliable in texture, the hole wall can be effectively protected, the hole wall cannot be influenced by slurry water flow to collapse and deform, the hole wall protected by the full sleeve pipe cannot be scratched and damaged by a fixing plate, and the hole wall of a drilled hole cannot collapse.

14. The construction method of the cast-in-place pile body further comprises the step S5 after the step S4, and the step S5 comprises grouting towards the pile side stratum through the pile side grouting pipe. Through towards stake side stratum slip casting, make the stratum around the pile body compacter, intensity is higher, makes inseparabler that bored concrete pile and stratum combine

15. The construction method of the cast-in-place pile body provided by the invention comprises the following steps: s1, forming holes by using an artificial retaining wall hole forming method to form holes with artificial retaining walls; s2, sinking the reinforcement cage with the lower end provided with the pile bottom grouting cavity to the bottom of the hole; s3, pouring concrete into the hole to fix the reinforcement cage and the inner cavity wall of the hole together; and S4, grouting into the grouting capsule to form the pile bottom expanded head. Through artifical dado cooperation bored concrete pile body pore-forming, can prevent following problem effectively: when a cast-in-place pile body is formed by adopting a slurry protection wall, in the process of descending the reinforcement cage to the bottom of a hole, the reinforcement cage with the fixing plate acts like a piston in a drilling hole and is easy to form vortex in slurry water, so that slurry water current revolving between the edge of the fixing plate and the wall of the drilling hole scours and disturbs the wall of the drilling hole, the fixing plate is easy to scrape the wall of the drilling hole, the factors easily cause the wall of the drilling hole to collapse, the sediment of the drilling hole after hole cleaning exceeds the standard after the drilling hole reaches the bottom of the cast-in-place container, and simultaneously, silt collapsed from the wall of the drilling hole is easily accumulated on the fixing plate, thereby affecting the quality of the cast-in-place pile and further causing pile breakage if the diameter of the fixing plate is smaller, or other reasons such as hole collapse and over-pouring and the like can also cause the problem that a. In order to solve the problems, the hole is formed by matching the artificial retaining wall with the cast-in-place pile body, because the artificial retaining wall is hard and reliable compared with the slurry retaining wall, the hole wall can be effectively protected, the hole wall cannot be influenced by slurry water flow to collapse and deform, the hole wall protected by the artificial retaining wall cannot be scratched and damaged by a fixing plate, and the hole wall of a drilled hole cannot collapse.

Drawings

In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and other drawings can be obtained by those skilled in the art without creative efforts.

Fig. 1 is a schematic view of an internal structure of a pile bottom grouting cavity provided by the invention;

FIG. 2 is a schematic diagram of a full casing hole forming provided by the present invention;

FIG. 3 is a schematic view of a steel reinforcement cage with a pile bottom grouting cavity sunk to the bottom of a hole provided by the invention;

FIG. 4 is a schematic illustration of the present invention providing a hoisting sleeve while simultaneously cementing concrete into the borehole;

FIG. 5 is a schematic view of the present invention providing grouting into a grouting capsule;

FIG. 6 is a schematic structural diagram of a bored concrete pile body with a pile-side grouting pipe according to the present invention;

FIG. 7 is a schematic structural view of an annular grouting portion inside a pile bottom grouting cavity provided by the invention;

fig. 8 is a schematic structural view of a pile bottom grouting cavity with a capsule detection port provided by the invention.

Description of reference numerals:

1-grouting capsules; 2-grouting pipe; 3-grouting holes; 4-an elastic member; 5-grouting part; 6, fixing a plate; 7-a reinforcement cage; 8-full sleeve; 9-hole; 10-pile side grouting pipe; 11-capsule detection port.

Detailed Description

The technical solutions of the present invention will be described clearly and completely with reference to the accompanying drawings, and it should be understood that the described embodiments are some, but not all embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.

In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.

In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.

In addition, the technical features involved in the different embodiments of the present invention described below may be combined with each other as long as they do not conflict with each other.

17页详细技术资料下载
上一篇:一种医用注射器针头装配设备
下一篇:桩底注浆腔及使用方法与灌注桩体及其施工方法

网友询问留言

已有0条留言

还没有人留言评论。精彩留言会获得点赞!

精彩留言,会给你点赞!

技术分类