阅读说明:本技术 建筑平台的安装方法 (Method for mounting building platform ) 是由 钟松杏 张阳川 林宇鹏 吴泽琛 于 2021-07-28 设计创作,主要内容包括:本发明提供了一种建筑平台的安装方法,包括:在墙体的外表面安装有多个附墙支架,多个所述附墙支架沿着所述墙体的延伸方向间隔布置;将顶升模组安装于相邻的两所述附墙支架;所述顶升模组依次沿着所述附墙支架向上移动;在所述顶升模组的顶部安装有平台,并基于所述平台构建各个工作区域。(The invention provides a method for installing a building platform, which comprises the following steps: the wall-attached support structure comprises a wall body, a plurality of wall-attached supports and a plurality of supporting pieces, wherein the wall-attached supports are arranged on the outer surface of the wall body at intervals along the extending direction of the wall body; installing a jacking module on two adjacent wall-attached supports; the jacking module sequentially moves upwards along the wall-attached support; and a platform is arranged at the top of the jacking module, and each working area is constructed based on the platform.)

1. A method of installing a building platform, comprising:

the wall-attached support structure comprises a wall body, a plurality of wall-attached supports and a plurality of supporting pieces, wherein the wall-attached supports are arranged on the outer surface of the wall body at intervals along the extending direction of the wall body;

installing a jacking module on two adjacent wall-attached supports; the jacking module sequentially moves upwards along the wall-attached support;

and a platform is arranged at the top of the jacking module, and each working area is constructed based on the platform.

2. The method for installing a building platform according to claim 1, wherein the step of installing a plurality of wall-attached brackets on the outer surface of the wall body, the plurality of wall-attached brackets being arranged at intervals along the extending direction of the wall body, comprises the steps of:

embedding a steel frame into the wall body, wherein the outer surface of the steel frame supports the wall body;

the steel frame is formed by a plurality of first supports in a surrounding manner, and a containing cavity is formed by the plurality of first supports in the surrounding manner;

a plurality of support frames which are arranged in a staggered mode are installed on the basis of the accommodating cavity, and the support frames are stacked in the vertical upward direction and are arranged in a staggered mode;

the wall-attached supports penetrate through the wall body and are sequentially hung on the steel frame;

the wall-attached brackets are arranged at intervals along the extending direction of the wall body;

the wall-attached support is provided with a supporting part protruding outwards, and the supporting part is abutted to the outer surface of the wall body and used for installing the jacking module.

3. The method of installing a building platform as claimed in claim 2, further comprising: the wall body is provided with a clamping groove which penetrates through the wall body along the vertical direction; and the wall-attached support is clamped with the clamping grooves and is sequentially arranged on the wall body along the extending direction of the clamping grooves.

4. The method of installing a building platform as claimed in claim 1, wherein the jacking module is installed to two adjacent wall-attached brackets; jacking module is in proper order along attach wall support rebound, include:

sequentially mounting the fixed end of the jacking module on two adjacent wall-attached supports, wherein the jacking module comprises a jacking oil cylinder and a supporting column connected with the jacking oil cylinder;

the supporting column is driven by the jacking oil cylinder to protrude upwards;

the supporting columns sequentially pass through the wall-attached support and are fixedly connected with the wall-attached support;

the installation of the jacking oil cylinder is changed along with the jacking of the jacking oil cylinder, and the jacking module moves upwards along the wall-attached support in sequence.

5. The method for installing a building platform according to claim 4, wherein the step of installing a platform on top of the jacking module and constructing each work area based on the platform comprises:

mounting the platform on top of the support post;

the supporting column is provided with a plurality of inclined columns outwards protruding along the peripheral side of the supporting column, and the top of each inclined column and the top of the supporting column are arranged in a staggered mode in the height direction;

the platform is clamped at the tops of the supporting columns and the tops of the inclined columns and is limited by the tops of the inclined columns in the horizontal direction by taking the tops of the supporting columns as centers.

6. A method of installing a building platform according to claim 5 wherein a plurality of different work areas are provided above the platform, and a flow path is provided between adjacent work areas: the platform arranges each of the working areas along the flow path.

7. A method of installing a building platform according to claim 6, wherein the platform comprises a sub-truss, a main truss and a perimeter truss;

the secondary truss is clamped at the top of the jacking module and extends according to the arrangement of the jacking module;

the main truss is lapped on the secondary truss and extends along four sides of the secondary truss so as to enclose a rectangular supporting area; the main truss is inserted into the secondary truss in a penetrating way and is level with the secondary truss;

the peripheral trusses enclose the outer contour of the rectangular supporting area and are sequentially connected with the secondary trusses and the main trusses.

8. The method of installing a construction platform of claim 7, further comprising:

after the construction of the building platform is completed, sequentially decomposing the building platform;

and are sequentially decomposed along the reverse direction of the installation sequence and are gradually decomposed along the up-down direction.

9. The method of installing a construction platform according to claim 8, wherein the steps of sequentially disassembling in the reverse direction of the installation sequence and gradually disassembling in the up-down direction comprise:

disassembling the platform and removing each working area;

sequentially removing the peripheral truss and the main truss and reserving the secondary truss;

removing the jacking module and releasing the connection relation between the jacking module and the wall-attached support;

and removing the wall-attached bracket, and outwards detaching and recovering.

Technical Field

The invention relates to the technical field of building platforms, in particular to a mounting method of a building platform.

Background

In the building industry, the installation of a platform requires the integral suspension of a suspension machine, and a suspension arm of the suspension machine lifts the platform upwards from the ground and moves in the air, wherein the platform is easy to shift in the suspension process, resulting in lower flatness of the platform in the horizontal direction.

Disclosure of Invention

The invention aims to provide an installation method of a building platform.

In order to solve the technical problems, the invention adopts the following technical scheme:

according to one aspect of the present invention, there is provided a method of installing a construction platform, comprising:

the wall-attached support structure comprises a wall body, a plurality of wall-attached supports and a plurality of supporting pieces, wherein the wall-attached supports are arranged on the outer surface of the wall body at intervals along the extending direction of the wall body;

installing a jacking module on two adjacent wall-attached supports; the jacking module sequentially moves upwards along the wall-attached support;

and a platform is arranged at the top of the jacking module, and each working area is constructed based on the platform.

Optionally, the outer surface of the wall body is provided with a plurality of wall-attached brackets, and the plurality of wall-attached brackets are arranged at intervals along the extending direction of the wall body, and include:

embedding a steel frame into the wall body, wherein the outer surface of the steel frame supports the wall body;

the steel frame is formed by a plurality of first supports in a surrounding manner, and a containing cavity is formed by the plurality of first supports in the surrounding manner;

a plurality of support frames which are arranged in a staggered mode are installed on the basis of the accommodating cavity, and the support frames are stacked in the vertical upward direction and are arranged in a staggered mode;

the wall-attached supports penetrate through the wall body and are sequentially hung on the steel frame;

the wall-attached brackets are arranged at intervals along the extending direction of the wall body;

the wall-attached support is provided with a supporting part protruding outwards, and the supporting part is abutted to the outer surface of the wall body and used for installing the jacking module.

Optionally, the method further includes: the wall body is provided with a clamping groove which penetrates through the wall body along the vertical direction; and the wall-attached support is clamped with the clamping grooves and is sequentially arranged on the wall body along the extending direction of the clamping grooves.

Optionally, the jacking module is mounted on two adjacent wall-attached supports; jacking module is in proper order along attach wall support rebound, include:

sequentially mounting the fixed end of the jacking module on two adjacent wall-attached supports, wherein the jacking module comprises a jacking oil cylinder and a supporting column connected with the jacking oil cylinder;

the supporting column is driven by the jacking oil cylinder to protrude upwards;

the supporting columns sequentially pass through the wall-attached support and are fixedly connected with the wall-attached support;

the installation of the jacking oil cylinder is changed along with the jacking of the jacking oil cylinder, and the jacking module moves upwards along the wall-attached support in sequence.

Optionally, the top of jacking module is installed the platform, and based on each work area is built to the platform, include:

mounting the platform on top of the support post;

the supporting column is provided with a plurality of inclined columns outwards protruding along the peripheral side of the supporting column, and the top of each inclined column and the top of the supporting column are arranged in a staggered mode in the height direction;

the platform is clamped at the tops of the supporting columns and the tops of the inclined columns and is limited by the tops of the inclined columns in the horizontal direction by taking the tops of the supporting columns as centers.

Optionally, a plurality of different working areas are arranged above the platform, and a flow channel is arranged between the adjacent working areas: the platform arranges each of the working areas along the flow path.

Optionally, the platform comprises a secondary truss, a primary truss and a peripheral truss;

the secondary truss is clamped at the top of the jacking module and extends according to the arrangement of the jacking module;

the main truss is lapped on the secondary truss and extends along four sides of the secondary truss so as to enclose a rectangular supporting area; the main truss is inserted into the secondary truss in a penetrating way and is level with the secondary truss;

the peripheral trusses enclose the outer contour of the rectangular supporting area and are sequentially connected with the secondary trusses and the main trusses.

Optionally, the installation method of the building platform further includes:

after the construction of the building platform is completed, sequentially decomposing the building platform;

and are sequentially decomposed along the reverse direction of the installation sequence and are gradually decomposed along the up-down direction.

Optionally, the assembly is sequentially disassembled along the reverse direction of the installation sequence, and is gradually disassembled along the up-down direction, including:

disassembling the platform and removing each working area;

sequentially removing the peripheral truss and the main truss and reserving the secondary truss;

removing the jacking module and releasing the connection relation between the jacking module and the wall-attached support;

and removing the wall-attached bracket, and outwards detaching and recovering.

According to the technical scheme, the embodiment of the invention at least has the following advantages and positive effects:

according to the installation method of the building platform, a plurality of wall attaching supports are installed on the outer surface of a wall body, and the wall attaching supports are arranged at intervals along the extending direction of the wall body; installing a jacking module on two adjacent wall-attached supports; the jacking module sequentially moves upwards along the wall-attached support; the platform is installed at the top of jacking module, and based on each work area is found to the platform, thereby based on the establishment of jacking realization platform of jacking module, and the jacking module is in follow the wall body and creep in proper order under the assistance of attaching the wall support, and then improve the roughness of platform in the horizontal direction avoids the platform to squint and remove in the air.

Drawings

Fig. 1 is an installation flowchart of an installation method of a construction platform according to an embodiment of the present application.

The reference numbers are as follows:

1. a first bracket; 11. a second engaging portion; 12. a first leg; 2. a jacking assembly; 21. a telescopic arm; 22. a cylinder body; 3. a wall body; 31. a first engaging part

Detailed Description

Exemplary embodiments that embody features and advantages of the invention are described in detail below in the specification. It is to be understood that the invention is capable of other embodiments and that various changes in form and details may be made therein without departing from the scope of the invention and the description and drawings are to be regarded as illustrative in nature and not as restrictive.

In the building industry, the installation of a platform requires the integral suspension of a suspension machine, and a suspension arm of the suspension machine lifts the platform upwards from the ground and moves in the air, wherein the platform is easy to shift in the suspension process, resulting in lower flatness of the platform in the horizontal direction.

According to an embodiment of the present disclosure, there is provided a method for controlling an integral jacking platform, as shown in fig. 1, the method for controlling the integral jacking platform includes:

step S110, mounting a plurality of wall attaching supports on the outer surface of a wall body, wherein the wall attaching supports are arranged at intervals along the extending direction of the wall body;

step S120, installing a jacking module on two adjacent wall-attached supports; the jacking module sequentially moves upwards along the wall-attached support;

and S130, mounting a platform on the top of the jacking module, and constructing each working area based on the platform.

In some embodiments of the present invention, a plurality of wall-attached brackets are mounted on an outer surface of a wall body, and the plurality of wall-attached brackets are arranged at intervals along an extending direction of the wall body; installing a jacking module on two adjacent wall-attached supports; the jacking module sequentially moves upwards along the wall-attached support; the platform is installed at the top of jacking module, and based on each work area is found to the platform, thereby based on the establishment of jacking realization platform of jacking module, and the jacking module is in follow the wall body and creep in proper order under the assistance of attaching the wall support, and then improve the roughness of platform in the horizontal direction avoids the platform to squint and remove in the air.

These steps are described in detail below.

In step S110, a plurality of wall-attached brackets are mounted on an outer surface of the wall body, and the wall-attached brackets are arranged at intervals along an extending direction of the wall body;

the method comprises the following specific steps: embedding a steel frame into the wall body, wherein the outer surface of the steel frame supports the wall body; the steel frame is formed by a plurality of first supports in a surrounding manner, and a containing cavity is formed by the plurality of first supports in the surrounding manner; a plurality of support frames which are arranged in a staggered mode are installed on the basis of the accommodating cavity, and the support frames are stacked in the vertical upward direction and are arranged in a staggered mode; the wall-attached supports penetrate through the wall body and are sequentially hung on the steel frame; the wall-attached brackets are arranged at intervals along the extending direction of the wall body; the wall-attached support is provided with a supporting part protruding outwards, and the supporting part is abutted to the outer surface of the wall body and used for installing the jacking module.

The wall body is reinforced through the steel frame, the wall body serves as a support column of the wall body, bearing strength of the wall body is improved, and in addition, the wall body is penetrated through by the wall attaching supports and is sequentially hung on the steel frame, connection of the wall attaching supports is achieved, and installation of the jacking module is achieved.

In addition, the wall body is provided with a clamping groove which penetrates through the wall body along the vertical direction; and the wall-attached support is clamped with the clamping grooves and is sequentially arranged on the wall body along the extending direction of the clamping grooves so as to guide the installation of the wall-attached support.

In step S120, the jacking module is installed on two adjacent wall-attached brackets; and the jacking module moves upwards along the wall-attached support in sequence.

The method comprises the following specific steps: sequentially mounting the fixed end of the jacking module on two adjacent wall-attached supports, wherein the jacking module comprises a jacking oil cylinder and a supporting column connected with the jacking oil cylinder; the supporting column is driven by the jacking oil cylinder to protrude upwards; the supporting columns sequentially pass through the wall-attached support and are fixedly connected with the wall-attached support; the installation of the jacking oil cylinder is changed along with the jacking of the jacking oil cylinder, and the jacking module moves upwards along the wall-attached support in sequence.

In step S130, a platform is installed on the top of the jacking module, and each working area is constructed based on the platform.

The method comprises the following specific steps: mounting the platform on top of the support post; the supporting column is provided with a plurality of inclined columns outwards protruding along the peripheral side of the supporting column, and the top of each inclined column and the top of the supporting column are arranged in a staggered mode in the height direction; the platform is clamped at the tops of the supporting columns and the tops of the inclined columns and is limited by the tops of the inclined columns in the horizontal direction by taking the tops of the supporting columns as centers.

The platform is supported by support columns, the tops of the inclined columns and the tops of the support columns are arranged in a staggered mode in the height direction, so that the platform is limited and clamped in the horizontal direction and is fixedly mounted in the height direction, the platform is clamped at the tops of the support columns and the tops of the inclined columns, and the tops of the inclined columns are limited in the horizontal direction by taking the tops of the support columns as centers.

The top of platform is equipped with a plurality of different work areas, and is adjacent be equipped with a runner between the work area: the platform arranges each of the working areas along the flow path, the working areas being construction areas, rest areas, and the like.

Additionally, the platform includes a secondary truss, a primary truss, and a perimeter truss; the secondary truss is clamped at the top of the jacking module and extends according to the arrangement of the jacking module; the main truss is lapped on the secondary truss and extends along four sides of the secondary truss so as to enclose a rectangular supporting area; the main truss is inserted into the secondary truss in a penetrating way and is level with the secondary truss; the peripheral trusses enclose the outer contour of the rectangular supporting area and are sequentially connected with the secondary trusses and the main trusses.

Further, the method for installing the construction platform further comprises: after the construction of the building platform is completed, sequentially decomposing the building platform; and are sequentially decomposed along the reverse direction of the installation sequence and are gradually decomposed along the up-down direction.

Wherein, and decompose in proper order along the reverse of installation order, and decompose along upper and lower direction step by step, include: disassembling the platform and removing each working area; sequentially removing the peripheral truss and the main truss and reserving the secondary truss; removing the jacking module and releasing the connection relation between the jacking module and the wall-attached support; removing the wall attachment bracket and detaching and recovering outwardly to facilitate disassembly of the building platform.

According to the technical scheme, the embodiment of the invention at least has the following advantages and positive effects:

according to the installation method of the building platform, a plurality of wall attaching supports are installed on the outer surface of a wall body, and the wall attaching supports are arranged at intervals along the extending direction of the wall body; installing a jacking module on two adjacent wall-attached supports; the jacking module sequentially moves upwards along the wall-attached support; the platform is installed at the top of jacking module, and based on each work area is found to the platform, thereby based on the establishment of jacking realization platform of jacking module, and the jacking module is in follow the wall body and creep in proper order under the assistance of attaching the wall support, and then improve the roughness of platform in the horizontal direction avoids the platform to squint and remove in the air.

While the present invention has been described with reference to several exemplary embodiments, it is understood that the terminology used is intended to be in the nature of words of description and illustration, rather than of limitation. As the present invention may be embodied in several forms without departing from the spirit or essential characteristics thereof, it should also be understood that the above-described embodiments are not limited by any of the details of the foregoing description, but rather should be construed broadly within its spirit and scope as defined in the appended claims, and therefore all changes and modifications that fall within the meets and bounds of the claims, or equivalences of such meets and bounds are therefore intended to be embraced by the appended claims.