Bank slope ecological protection method based on filling type water and soil protection blanket

文档序号:1857427 发布日期:2021-11-19 浏览:5次 中文

阅读说明:本技术 一种基于填充型水土保护毯的岸坡生态防护方法 (Bank slope ecological protection method based on filling type water and soil protection blanket ) 是由 张曙光 张亮亮 于 2020-05-15 设计创作,主要内容包括:本发明公开了一种基于填充型水土保护毯的岸坡生态防护方法,通过铺设填充性保护毯,结合种子的播撒、使毯体与植被、土壤形成一体,景观效果好,透水性高,植被生长佳,环保效果好,施工简单效率高成本低,抗短时高水流冲击力强,养护简单无岁修成本,使用周期长。(The invention discloses a bank slope ecological protection method based on a filling type water and soil protection blanket, wherein a blanket body, vegetation and soil are integrated into a whole by laying the filling type protection blanket and combining with the sowing of seeds, so that the landscape effect is good, the water permeability is high, the vegetation growth is good, the environmental protection effect is good, the construction is simple, the efficiency is high, the cost is high, the short-time high-water impact resistance is strong, the maintenance is simple, the repair cost is avoided, and the service cycle is long.)

1. A bank slope ecological protection method based on a filling type water and soil protection blanket is characterized in that: the protection method comprises the following steps: 1. before the construction of the whole slope, the slope surface needs to be repaired and leveled, the slope surface can be manually finished for the second time if necessary, the slope surface or the foundation needs to accord with the side-slope ratio of the drawing paper, a large amount of gravels, tree roots, tree piles or other garbage with overlarge grain sizes (larger than 50 mm) cannot be stored on the slope surface, the convex and concave parts cannot be allowed to appear, the slope surface is compacted by rolling, all accumulated water in the laying working range is removed, and when the slope surface (foundation) has no natural surface soil or the thickness of the surface soil is smaller than the thickness specified by the drawing paper, the surface soil is additionally laid until the requirement of the drawing paper is met; 2. grooves with the depth width not less than 30mm x30mm are respectively formed in the top and the bottom of the dike, the section form and the depth of the grooves must meet the requirements of construction drawings, if a large amount of accumulated water exists in the grooves, relevant drainage operation must be performed, and the vertical surfaces of the grooves are prevented from being softened; 3. seeds suitable for local growth are sown at one time, the sowing density of the area above the normal water level is 30 g/square meter, and aquatic plants (or a layer of tubers of the aquatic plants is paved before the filling type water and soil protection blanket is paved) are planted in the area below the normal water level; 4. uncoiling, namely, putting about 1m of one end of a coil into a side ditch and fixing the end ditch by using steel U-shaped nails, then unfolding the water and soil protection blanket, and unfolding the water and soil protection blanket from the bottom of the embankment to the top of the embankment or from the top of the embankment to the bottom of the embankment without transversely paving the water and soil protection blanket; 5. cutting the water and soil protective blanket into proper size with electric saw or cutting machine, placing the water and soil protective blanket into the groove at the other side with a reserved length of about 1m, and using U-shapedFixing with steel nails, if the filling type soil and water protection blanket needs to be temporarily placed at a side slope or a position close to the water edge, fixing the blanket to prevent the blanket from moving, and for safety, a constructor does not stand below the roll and needs to wear a protective eye shield when using a cutting machine; 6. after the two ends of the backfill groove filling type soil and water protection blanket are fixed in the groove, filling soil and compacting; 7. the lapping and the lapping of the anchoring water and soil protection blanket adopt the following water flow lapping (namely, the upstream and the downstream are pressed), a steel nail is driven into the position of a dike shoulder every one meter, a steel nail is driven into the lapping position every one meter, a U-shaped steel nail is driven into the rest positions every 2 to 3 square meters, the length of the steel nail is 300mm to 700mm, the diameter is more than or equal to 6mm, the checking and acceptance of the cleaning work of the paved surface is required before the water and soil protection blanket is paved, the thickness and the construction of a cushion layer are both in accordance with the construction drawing specification, the paving direction of the water and soil protection blanket is determined according to the stress direction of materials, the hydrological conditions of a river channel and other factors and is in accordance with the requirement of the construction drawing, when the water and soil protection blanket is paved, the front and back blankets are separated and laid (two-dimensional plane layers are laid downwards), the proper tightness is kept during the paving process to prevent deformation, the paving range is required to be greened, if the paving range is required, the related grass seeds are immediately sowed after a foundation or a slope is trimmed in time, paving the water and soil protection blanket, avoiding construction in high-temperature weather or immediately covering 50mm thin soil to avoid excessive heat absorption, tightly attaching the water and soil protection blanket to a foundation or a cushion layer to avoid overhead, preventing operators from wearing shoes with nails and directly unloading concrete slope protection blocks on the water and soil protection blanket, preventing steel bars with sharp heads from being used as a sledding tool, strictly prohibiting construction operation of beating stones and possibly damaging the water and soil protection blanket on the water and soil protection blanket, and performing related steel nail anchoring measures on all the water and soil protection blankets during paving, wherein the anchoring density of specific steel bars is not lower than the minimum design standard; the water and soil protection blanket laid on the same day needs to complete steel nail anchoring measures on the same day, the lapping mode and the lapping length of the water and soil protection blanket need to meet the requirements of construction drawings and relevant specifications, the lapping direction is carried out along the water flow direction, the water and soil protection blanket is found to be damaged and needs to be repaired or replaced immediately, the lapping surface needs to be cleaned before lapping, the tight and non-swelling lapping of the water and soil protection blanket is ensured, and the lapping part needs to adopt the methodRelevant measures such as steel nail anchoring and the like are taken, the stability of a lap joint is ensured, a construction road is planned when the water and soil protection blanket is constructed, when vehicles, equipment and the like cross the water and soil protection blanket, corresponding protection measures are required to be taken, when concrete or stone building construction on the water and soil protection blanket is carried out, the laying equipment cannot directly run or operate on the water and soil protection blanket at any time, materials are not damaged when the water and soil protection blanket is laid, the damaged water and soil protection blanket in the construction process is repaired in time according to the instruction of a supervisor, the qualified water and soil protection blanket is replaced to cover the damaged part at the damaged part of the damaged water and soil protection blanket part, relevant lap joint measures are made, and steel nails are used for strengthening anchoring; 8. covering soil suitable for vegetation growth on the water and soil protection blanket by covering soil, wherein the thickness of the soil is not less than 30mm, in the soil covering process, if landscape requirements and other factors need to place landscape stones or other landscape materials on the water and soil protection blanket, contractors need to take effective measures to prevent the landscape stones or other landscape materials from rolling and sliding on a slope surface and prevent mechanical transportation from damaging the paved water and soil protection blanket, and if grass seeds are adopted for sowing: the seeding should be sufficient and uniform, the engineering greening grass seeds should be accurate and pure in variety and free of diseases and insect pests; if the turf greening is adopted: the quality of the turf must meet the relevant greening requirements; if emergent aquatic plants are adopted for greening, organic clay soil such as field soil, pond sludge and the like is used as bottom soil, coarse sand with the diameter of 10-20mm is paved on the surface layer, the phenomenon of water turbidity caused by irrigation or vibration can be prevented, and if the soil in the original slope surface contains waste building soil and other harmful components, soil dressing or technical measures for improving the soil are adopted to meet the basic conditions of plant growth; 9. the secondary sowing can be carried out alternately to ensure uniform sowing and greening, turf greening or aquatic plant transplanting needs to be carried out after covering soil, watering and maintaining are needed after greening is finished, sowing needs to be started after the slope is completely leveled in the greening sowing, and when grass seeds are sowed, a layer of non-woven fabric (15 g/m) needs to be covered after the sowing and greening are finished2) The watering operation is carried out at the rear part to prevent the grass seeds from being scattered and influencing the lawn forming effect, and the watering and maintenance are carried out for one to two weeks according to the weather condition no matter the grass seeds are greened or the turf is greened, so as to be beneficial to the germination and growth of plants.

Technical Field

The invention belongs to the field of water and soil protection, and particularly relates to a bank slope ecological protection method based on a filling type water and soil protection blanket.

Background

Navigation river course or the faster river course of velocity of water, the stability of side slope and the scour resistance of bank protection are mainly considered from the angle of mechanics in the bank protection design, so traditional bank protection mostly adopts the slope formula such as the strong stone of bank protection ability, reinforced concrete, vertical type stereoplasm bank protection structural style, though stereoplasm bank protection impact resistance is stronger, can effectively protect soil erosion and water loss, and structural security, durability are better, but its shortcoming is also very outstanding. The hard slope protection structure is monotonous and hard in landscape effect, and the ecological property of a river channel system is destroyed because the hard slope protection isolates natural exchange between water bodies, so that the construction of the ecological diversity of the river channel system and the exertion of the ecological restoration function are not facilitated.

If a method which can meet the water and soil protection requirements and simultaneously give consideration to ecology exists, the problems can be easily solved.

The invention aims to solve the technical problem of providing the bank slope ecological protection method of the filling type water and soil protection blanket, which has the advantages of good landscape effect, high water permeability, good vegetation growth, good environmental protection effect, simple construction, high efficiency, low cost, strong short-time high water flow impact resistance, simple maintenance, no repair cost and long service cycle.

Disclosure of Invention

In order to solve the problems of poor landscape effect, low water permeability, unfavorable vegetation growth, troublesome construction, low efficiency, high manufacturing cost, poor short-time high water flow impact resistance, troublesome maintenance, high repair cost, short service cycle and the like in the prior art, the invention adopts the following technical scheme:

the invention provides a bank slope ecological protection method based on a filling type water and soil protection blanket, which comprises the following steps: 1. before the slope is constructed, the slope is required to be repaired and leveled, the slope can be manually subjected to secondary finishing under necessary conditions, the slope or the foundation is required to meet the graph paper slope ratio, and a large amount of gravels, tree roots, tree piles or other garbage with overlarge particle sizes (larger than 50 mm) cannot be stored on the slope. Convex and concave portions are not allowed to appear, and compaction should be performed. Removing all accumulated water in the laying working range, and additionally laying surface soil until the surface soil meets the requirements of the drawing when the slope (foundation) has no natural surface soil or the thickness of the surface soil is less than the thickness specified by the drawing; 2. grooves with the depth width not less than 30mm x30mm are respectively formed in the top and the bottom of the dike, the section form and the depth of the grooves must meet the requirements of construction drawings, if a large amount of accumulated water exists in the grooves, relevant drainage operation must be performed, and the vertical surfaces of the grooves are prevented from softening; 3. seeds suitable for local growth are sown at one time, the sowing density of the area above the normal water level is 30 g/square meter, and aquatic plants (or a layer of tubers of the aquatic plants is paved before the filling type water and soil protection blanket is paved) are planted in the area below the normal water level; 4. uncoiling, namely, putting about 1m of one end of a coil into a side ditch and fixing the end ditch by using a U-shaped steel nail, then unfolding the water and soil protection blanket, and unfolding the water and soil protection blanket from the bottom of the embankment to the top of the embankment or from the top of the embankment to the bottom of the embankment without transversely paving the water and soil protection blanket; 5. cutting the water and soil protection blanket into a proper size by using an electric saw or a cutting machine, reserving about 1m of the water and soil protection blanket after cutting, putting the water and soil protection blanket into a groove on the other side, fixing the water and soil protection blanket by using a U-shaped steel nail, and if the filling type water and soil protection blanket needs to be temporarily placed on a side slope or a position close to a water edge, fixing the water and soil protection blanket to prevent movement; 6. backfill groove filling type soil and water protection blanketAfter the two ends of the groove are fixed well, filling soil and compacting; 7. the lapping and the lapping of the anchoring water and soil protection blanket adopt downstream lapping (namely upstream and downstream pressing). And a steel nail is driven into the dike shoulder every other meter, and a steel nail is driven into the lap joint every other meter. And one U-shaped steel nail is punched into the rest parts of the square meter every 2 to 3. The length of the steel nail is 300 mm-700 mm, the diameter is more than or equal to 6mm, the cleaning work of the paved surface is checked and accepted before the water and soil protection blanket is paved, the thickness and the construction of the blanket layer are both in accordance with the construction drawing rules, the paving direction of the water and soil protection blanket is determined according to the stress direction of the material, the hydrological conditions of the river channel and other factors and is in accordance with the requirements of the construction drawing, when the water and soil protection blanket is paved, the front and back surfaces of the blanket are clearly distinguished (the two-dimensional plane layer is paved under), the proper tightness is kept in the paving process to prevent deformation, when the paving is carried out, if the paving range needs greening, after relevant grass seeds are immediately sown after the foundation or the slope surface is trimmed, the water and soil protection blanket is paved, the construction in high temperature weather or 50mm thin soil is immediately covered to avoid excessive heat absorption, the water and soil protection blanket is tightly adhered to the foundation or the blanket to avoid the excessive heat absorption, and the aerial paving process, the worker must not wear the shoes with the nails. Concrete slope protection blocks cannot be directly discharged from the water and soil protection blanket, reinforcing steel bars with sharp ends cannot be used as a sledding tool, stone knocking on the water and soil protection blanket and all construction operations which may damage the water and soil protection blanket are strictly forbidden, all the water and soil protection blankets need to be subjected to related steel nail anchoring measures during laying, and the specific reinforcing steel bar anchoring density is not lower than the design minimum standard; the water and soil protection blanket laid on the same day should complete steel nail anchoring measures on the same day, and the lap joint mode and the lap joint length of the water and soil protection blanket should meet the requirements of construction drawings and relevant specifications. The lapping direction is carried out along the water flow direction. When the water and soil protection blanket is found to be damaged and needs to be repaired or replaced immediately, the lap joint surface needs to be cleaned before lap joint, the water and soil protection blanket is ensured to be in tight lap joint and not to be bulged, measures such as related steel nail anchoring and the like need to be taken at the lap joint part, the stability of the lap joint part is ensured, a construction road needs to be planned when the water and soil protection blanket is constructed, corresponding protection measures need to be taken when vehicles, equipment and the like cross over the water and soil protection blanket, and concrete or masonry on the water and soil protection blanket is constructed at any timeThe laying equipment does not need to directly run or operate on the water and soil protection blanket, the material is not damaged when the laying equipment is laid, the damaged water and soil protection blanket in the construction process needs to be repaired in time according to the instruction of a supervisor, the damaged water and soil protection blanket part needs to be replaced with a qualified water and soil protection blanket to cover the damaged part, relevant lap joint measures are made, and meanwhile, steel nails are used for strengthening anchoring; 8. covering soil suitable for vegetation growth on the water and soil protection blanket by covering soil, wherein the thickness of the soil is not less than 30mm, in the soil covering process, if landscape requirements and other factors need to place landscape stones or other landscape materials on the water and soil protection blanket, contractors need to take effective measures to prevent the landscape stones or other landscape materials from rolling and sliding on a slope surface and prevent mechanical transportation from damaging the paved water and soil protection blanket, and if grass seeds are adopted for sowing: the seeding should be sufficient and uniform, the engineering greening grass seeds should be accurate and pure in variety and free of diseases and insect pests; if the turf greening is adopted: the quality of the turf must meet the relevant greening requirements; if emergent aquatic plants are adopted for greening, organic clay soil such as field soil, pond sludge and the like is used as bottom soil, coarse sand with the diameter of one to two centimeters is paved on the surface layer, the phenomenon of water turbidity caused by irrigation or vibration can be prevented, and if the soil in the original slope surface contains waste building soil and other harmful components, soil dressing or technical measures for improving the soil are adopted to meet the basic conditions of plant growth; 9. the secondary sowing is to ensure uniform sowing and greening, the sowing operation can be carried out alternately, and turf greening or aquatic plant transplanting needs to be carried out after soil covering. After greening, watering and maintaining are needed, seeding is needed after the slope is completely planted, and when grass seeds are sowed, a layer of non-woven fabric (15 g/m) needs to be covered after the steps are finished2) The watering operation is carried out at the rear part to prevent the grass seeds from being scattered and influencing the lawn forming effect, and the watering and maintenance are carried out for one to two weeks according to the weather condition no matter the grass seeds are greened or the turf is greened, so as to be beneficial to the germination and growth of plants.

The invention has the beneficial effects that: the vegetation is grown by spreading seeds through laying and filling the protection blanket and is integrated with soil, the landscape effect is good, the water permeability is high, the vegetation growth is good, the environmental protection effect is good, the construction is simple, the efficiency is high, the cost is low, the short-time high water flow impact resistance is strong, the maintenance is simple, the repair cost is avoided, and the service cycle is long.

Detailed Description

Preferred embodiments of the present invention are described in detail below.

A bank slope ecological protection method based on a filling type water and soil protection blanket comprises the following steps: 1. before the slope is constructed, the slope is required to be repaired and leveled, the slope can be manually subjected to secondary finishing under necessary conditions, the slope or the foundation is required to meet the graph paper slope ratio, and a large amount of gravels, tree roots, tree piles or other garbage with overlarge particle sizes (larger than 50 mm) cannot be stored on the slope. Convex and concave portions are not allowed to appear, and compaction should be performed. Removing all accumulated water in the laying working range, and additionally laying surface soil until the surface soil meets the requirements of the drawing when the slope (foundation) has no natural surface soil or the thickness of the surface soil is less than the thickness specified by the drawing; 2. grooves with the depth width not less than 30mm x30mm are respectively formed in the top and the bottom of the dike, the section form and the depth of the grooves must meet the requirements of construction drawings, if a large amount of accumulated water exists in the grooves, relevant drainage operation must be performed, and the vertical surfaces of the grooves are prevented from being softened; 3. seeds suitable for local growth are sown at one time, the sowing density of the area above the normal water level is 30 g/square meter, and aquatic plants (or a layer of tubers of the aquatic plants is paved before the filling type water and soil protection blanket is paved) are planted in the area below the normal water level; 4. uncoiling, namely, putting about 1m of one end of a coil into a side ditch and fixing the end ditch by using a U-shaped steel nail, then unfolding the water and soil protection blanket, and unfolding the water and soil protection blanket from the bottom of the embankment to the top of the embankment or from the top of the embankment to the bottom of the embankment without transversely paving the water and soil protection blanket; 5. cutting the water and soil protection blanket into a proper size by using an electric saw or a cutting machine, reserving about 1m of the water and soil protection blanket after cutting, putting the water and soil protection blanket into a groove on the other side, fixing the water and soil protection blanket by using a U-shaped steel nail, and if the filling type water and soil protection blanket needs to be temporarily placed on a side slope or a position close to a water edge, fixing the water and soil protection blanket to prevent movement; 6. after the two ends of the backfill groove filling type soil and water protection blanket are fixed in the groove, filling soil and compacting; 7. the lapping and the lapping of the anchoring water and soil protection blanket adopt downstream lapping (namely upstream and downstream pressing). A steel nail is driven into the dike shoulder every other meter,And a steel nail is driven into the lap joint every other meter. And one U-shaped steel nail is punched into the rest parts of the square meter every 2 to 3. The length of the steel nail is 300 mm-700 mm, the diameter is more than or equal to 6mm, the cleaning work of the paved surface is checked and accepted before the water and soil protection blanket is paved, the thickness and the construction of the blanket layer are both in accordance with the construction drawing rules, the paving direction of the water and soil protection blanket is determined according to the stress direction of the material, the hydrological conditions of the river channel and other factors and is in accordance with the requirements of the construction drawing, when the water and soil protection blanket is paved, the front and back surfaces of the blanket are clearly distinguished (the two-dimensional plane layer is paved under), the proper tightness is kept in the paving process to prevent deformation, when the paving is carried out, if the paving range needs greening, after relevant grass seeds are immediately sown after the foundation or the slope surface is trimmed, the water and soil protection blanket is paved, the construction in high temperature weather or 50mm thin soil is immediately covered to avoid excessive heat absorption, the water and soil protection blanket is tightly adhered to the foundation or the blanket to avoid the excessive heat absorption, and the aerial paving process, the worker must not wear the shoes with the nails. Concrete slope protection blocks cannot be directly discharged from the water and soil protection blanket, reinforcing steel bars with sharp ends cannot be used as a sledding tool, stone knocking on the water and soil protection blanket and all construction operations which may damage the water and soil protection blanket are strictly forbidden, all the water and soil protection blankets need to be subjected to related steel nail anchoring measures during laying, and the specific reinforcing steel bar anchoring density is not lower than the design minimum standard; the water and soil protection blanket laid on the same day should complete steel nail anchoring measures on the same day, and the lap joint mode and the lap joint length of the water and soil protection blanket should meet the requirements of construction drawings and relevant specifications. The lapping direction is carried out along the water flow direction. When finding that the water and soil protection blanket is damaged, the water and soil protection blanket should be repaired or replaced immediately, the lap joint surface must be cleaned before lap joint, the lap joint of the water and soil protection blanket is ensured to be tight and have no bulge, measures such as related steel nail anchoring and the like must be taken at the lap joint, the stability of the lap joint is ensured, when the water and soil protection blanket is constructed, a construction road is planned, when vehicles, equipment and the like cross the water and soil protection blanket, corresponding protection measures must be taken, when concrete or masonry on the water and soil protection blanket is constructed, laying equipment cannot directly run or operate on the water and soil protection blanket at any time, materials are not damaged when the laying equipment is laid, and the water and soil protection blanket damaged in the construction process is timely monitoredIndicating to repair, and for the damaged water and soil protection blanket part, replacing a qualified water and soil protection blanket to cover the damaged part, making related lap joint measures, and simultaneously using steel nails to strengthen anchoring; 8. covering soil suitable for vegetation growth on the water and soil protection blanket by covering soil, wherein the thickness of the soil is not less than 30mm, in the soil covering process, if landscape requirements and other factors need to place landscape stones or other landscape materials on the water and soil protection blanket, contractors need to take effective measures to prevent the landscape stones or other landscape materials from rolling and sliding on a slope surface and prevent mechanical transportation from damaging the paved water and soil protection blanket, and if grass seeds are adopted for sowing: the seeding should be sufficient and uniform, the engineering greening grass seeds should be accurate and pure in variety and free of diseases and insect pests; if the turf greening is adopted: the quality of the turf must meet the relevant greening requirements; if emergent aquatic plants are adopted for greening, organic clay soil such as field soil, pond sludge and the like is used as bottom soil, coarse sand with the diameter of 10-20mm is paved on the surface layer, the phenomenon of water turbidity caused by irrigation or vibration can be prevented, and if the soil in the original slope surface contains waste building soil and other harmful components, soil dressing or technical measures for improving the soil are adopted to meet the basic conditions of plant growth; 9. the secondary sowing is to ensure uniform sowing and greening, the sowing operation can be carried out alternately, and turf greening or aquatic plant transplanting needs to be carried out after soil covering. After greening, watering and maintaining are needed, seeding is needed after the slope is completely planted, and when grass seeds are sowed, a layer of non-woven fabric (15 g/m) needs to be covered after the steps are finished2) The watering operation is carried out at the rear part to prevent the grass seeds from being scattered and influencing the lawn forming effect, and the watering and maintenance are carried out for one to two weeks according to the weather condition no matter the grass seeds are greened or the turf is greened, so as to be beneficial to the germination and growth of plants.

The filled water and soil protecting blanket is produced through special technological process, and is produced through filling crushed stone and adhering asphalt. Because of special process treatment, the sufficient softness and water permeability of the product are ensured. Because this product is heavier than a water and soil protective blanket made of polyamide (PA 6) alone, it can withstand extremely high water loads and can be used for greening even under high water pressure where vegetation is not readily grown. The anti-impact capacity is outstanding, the short-time flow rate of 6m/s at most can be resisted, the safety of a bank slope can be fully ensured, and the hard revetment can be completely replaced and applied to the normal water level and the part below the normal water level.

Compared with the prior art, the bank slope ecological protection technology based on the filling type water and soil protection blanket and the construction method thereof provided by the invention have the following advantages:

1. the filling type water and soil protection blanket has good openness and high water permeability, can ensure that an environment-friendly ecological revetment with natural river bank permeability is built, although the blanket body is filled with gravels and asphalt, the porosity can still reach more than 40 percent, not only can ensure the water exchange and regulation functions between the river bank and the river water body, but also can ensure that the root system of a plant can easily penetrate through the blanket body to grow upwards or downwards, and form good vegetation coverage effect and landscape effect on the slope surface, and the hard closed revetment can obstruct the natural exchange of river water and peripheral underground water, cut off the migration path of microorganisms in the water and destroy the environment of the laying derivation of the natural ecology.

2. Through the tests of various domestic and foreign test institutions such as river and sea university, Colorado State University (USA) and the like, the filling type water and soil protection blanket can resist the short-time flow rate of 6m/s under the condition of vegetation combination, and can replace hard slope protection materials paved at the normal water level and the parts below the normal water level to ensure the stability of slopes, banks and riverways.

The filling type water and soil protection blanket has good environmental protection performance, the raw material is polyamide (PA 6), the high polymer material cannot be naturally precipitated and absorbed, and the filling type water and soil protection blanket does not have chemical reaction with common substances in water and soil. The product passes the European Union environmental protection certification and can be used for drinking water source engineering.

The filling type water and soil protection blanket is used as a structure with good integrity and flexibility, better adapts to the local settlement of the foundation soil, can release the concentrated stress in the structure through small internal deformation, cannot generate structural damage, and avoids the problems of uneven settlement cracking and easy rapid diffusion of damage points which are possibly generated by adopting a rigid masonry structure.

5. The filling type water and soil protection blanket can be put into use after construction, and the problems that the cement masonry structure needs to be maintained for a certain period and the structure needs to be delayed in efficiency are solved.

6. Compared with the traditional scheme of mortar masonry or concrete precast blocks, the bank slope ecological protection technology of the filling type water and soil protection blanket is adopted, and the engineering cost is saved by 12-20% through rough estimation.

The above embodiments are not intended to limit the form and style of the present invention, and any suitable changes or modifications made by those skilled in the art should be considered as not departing from the scope of the present invention.