Construction method of concrete slope protection with green plant ecological capsules

文档序号:1933383 发布日期:2021-12-07 浏览:2次 中文

阅读说明:本技术 具有绿植生态囊混凝土护坡的修筑方法 (Construction method of concrete slope protection with green plant ecological capsules ) 是由 高小涛 马浩 甘天源 马玉涛 郭东茹 王晓晓 随裕芬 于 2021-09-16 设计创作,主要内容包括:本发明公开了一种具有绿植生态囊混凝土护坡的修筑方法,包括①修整岸坡②岸坡垫层施工,然后绑扎下层钢筋网和面层钢筋网③按照设计位置安装固定各生态囊单元④浇筑混凝土⑤向各生态囊中装填种植土,并栽种绿植,完成施工。本发明采用在混凝土护坡上的埋设生态囊的方式,其在安装时不需要断开受力钢筋网的改进,不影响护坡配筋面积,即原有混凝土现浇护坡板不会因为埋入生态囊而产生应力集中点,因此,在生态囊内种植观赏植物进行护坡绿化不影响混凝土护坡的结构安全及排水导流功能;施工时能够减少2-8%的混凝土用量,使施工成本降低;生态囊自重较轻,且具有一定的形状,在进行混凝土护坡浇筑时无需另外设置模板,简化了施工。(The invention discloses a construction method of concrete revetment with green plant ecological sacs, which comprises the steps of trimming a bank slope, constructing a bank slope cushion layer, binding a lower layer reinforcing mesh and a surface layer reinforcing mesh, installing and fixing each ecological sac unit according to the designed position, pouring concrete, filling planting soil into each ecological sac, planting green plants and completing construction. The method adopts the mode of embedding the ecological bag on the concrete slope protection, does not need to break the improvement of a stressed reinforcing steel bar net during installation, and does not influence the reinforcing bar area of the slope protection, namely the original cast-in-place concrete slope protection plate does not generate a stress concentration point because the ecological bag is embedded, so that the structure safety and the drainage and flow guide functions of the concrete slope protection are not influenced when ornamental plants are planted in the ecological bag for slope protection greening; the consumption of concrete can be reduced by 2-8% during construction, so that the construction cost is reduced; the ecological bag dead weight is lighter, and has certain shape, need not to set up in addition the template when carrying out concrete bank protection and pour, has simplified the construction.)

1. A construction method of a concrete revetment with green plant ecological capsules is characterized by comprising the following construction steps:

firstly, trimming a bank slope;

secondly, constructing a bank slope cushion layer, and then binding a lower layer reinforcing mesh and a surface layer reinforcing mesh;

thirdly, installing and fixing each ecological capsule unit according to the design position, wherein each ecological capsule unit comprises:

the ecological bag is used for containing planting soil and is provided with a hard bag neck and a bag body, the top opening of the hard bag neck is flush with the surface of the concrete slope protection, and the bottom of the hard bag neck is provided with a flaring structure used for connecting the bag body;

the sealing cover is arranged at the opening at the top of the hard capsule neck;

the water stop ring is integrally arranged on the hard bag neck;

the support columns are arranged around the water stop rings, the tops of the support columns are connected with the sealing covers, and the bottoms of the support columns are connected with the flaring structures and used for connecting the concrete slope protection surface layer reinforcing mesh;

fourthly, pouring concrete;

and fifthly, filling planting soil into each ecological bag, planting green plants and finishing construction.

2. The construction method of the concrete slope protection with green plant ecological capsules as claimed in claim 1, wherein: the hard bag neck is provided with drip irrigation joint pipes, and when the ecological bag unit is fixed, the drip irrigation joint pipes are connected with a drip irrigation header pipe.

3. The construction method of the concrete slope protection with green plant ecological capsules as claimed in claim 1, wherein: the capsule body is a hard material part or a flexible material part formed by pressurization.

4. The construction method of the concrete slope protection with green plant ecological capsules as claimed in claim 1, wherein: the bottom of the bag body is provided with a drainage joint pipe; the second step also comprises the step of constructing a main drainage pipe near the lower layer of the reinforcing mesh; the third step further includes bolting the drain connector pipe to the main drain pipe.

5. The construction method of the concrete slope protection with green plant ecological capsules as claimed in claim 1, wherein: the bottom of the bag body is provided with a water seepage hole with an autolysis structure.

6. The construction method of the concrete slope protection with green plant ecological capsules as claimed in claim 1, wherein: the utricule bottom is provided with solid fixed ring, when fixed ecological bag unit, need with gu fixed ring and concrete bank protection lower floor's reinforcing bar net ligature are connected.

7. The construction method of the concrete slope protection with green plant ecological capsules as claimed in claim 1, wherein: the sealing cover is a pull ring cover.

8. The construction method of the concrete slope protection with green plant ecological capsules as claimed in claim 1, wherein: the water stop rings are arranged twice at intervals.

Technical Field

The invention relates to the technical field of concrete slope protection, in particular to a construction method of a concrete slope protection with green plant ecological capsules.

Background

The water gate inlet and outlet wing wall side slopes in hydraulic engineering, the upstream and downstream wing wall side slopes of a rubber dam or a flap gate are subjected to larger hydraulic erosion, the seepage-proofing requirement is higher, a concrete panel slope is usually adopted, and the concrete panel slope has remarkable advantages in the aspects of structural stability, durability, high-speed water flow erosion resistance, convenience in construction, easiness in operation management and the like compared with the slope of other structural forms. However, the concrete panel slope protection is single and rigid, difficult to green, and can not meet the landscape requirements.

Disclosure of Invention

In order to solve the problems, the invention provides a construction method of a concrete slope protection with green plant ecological capsules, which can specifically adopt the following technical scheme:

the construction method of the concrete slope protection with the green plant ecological capsules comprises the following construction steps:

firstly, trimming a bank slope;

secondly, constructing a bank slope cushion layer, and then binding a lower layer reinforcing mesh and a surface layer reinforcing mesh;

thirdly, installing and fixing each ecological capsule unit according to the design position, wherein each ecological capsule unit comprises:

the ecological bag is used for containing planting soil and is provided with a hard bag neck and a bag body, the top opening of the hard bag neck is flush with the surface of the concrete slope protection, and the bottom of the hard bag neck is provided with a flaring structure used for connecting the bag body;

the sealing cover is arranged at the opening at the top of the hard capsule neck;

the water stop ring is integrally arranged on the hard bag neck;

the support columns are arranged around the water stop rings, the tops of the support columns are connected with the sealing covers, and the bottoms of the support columns are connected with the flaring structures and used for connecting the concrete slope protection surface layer reinforcing mesh;

fourthly, pouring concrete;

and fifthly, filling planting soil into each ecological bag, planting green plants and finishing construction.

The hard bag neck is provided with drip irrigation joint pipes, and when the ecological bag unit is fixed, the drip irrigation joint pipes are connected with a drip irrigation header pipe.

The capsule body is a hard material part or a flexible material part formed by pressurization.

The bottom of the bag body is provided with a drainage joint pipe; the second step also comprises the step of constructing a main drainage pipe near the lower layer of the reinforcing mesh; the third step further includes bolting the drain connector pipe to the main drain pipe.

The bottom of the bag body is provided with a water seepage hole with an autolysis structure.

The utricule bottom is provided with solid fixed ring, when fixed ecological bag unit, need with gu fixed ring and concrete bank protection lower floor's reinforcing bar net ligature are connected.

The sealing cover is a pull ring cover.

The water stop rings are arranged twice at intervals.

The construction method of the concrete slope protection with the green planting ecological sacs adopts a mode of embedding the ecological sacs in the concrete slope protection, the ecological sacs do not need to be improved by breaking a stress reinforcing mesh when being installed, the reinforcing area of the slope protection is not influenced, namely, the original cast-in-place concrete slope protection plate does not generate a stress concentration point due to the fact that the ecological sacs are embedded, and therefore, ornamental plants are planted in the ecological sacs for slope protection greening, and the structural safety and the drainage and flow guide functions of the concrete slope protection are not influenced. And secondly, due to the embedding of the ecological bag, compared with the traditional concrete slope protection, the ecological bag can reduce the concrete consumption by 2-8% during construction, so that the construction cost is reduced. And the ecological bag has light self weight and a certain shape, so that a template is not required to be additionally arranged when the concrete slope protection is poured, and the construction is simplified.

Drawings

Fig. 1 is a schematic structural view of the concrete slope protection with green plant ecological capsules of the invention.

Fig. 2 is a schematic structural view of the ecological sac unit N1 in fig. 1.

Fig. 3 is a schematic structural view of the ecological sac unit N2 in fig. 1.

Fig. 4 is a schematic structural view of the ecological sac unit N3 in fig. 1.

Detailed Description

The following describes embodiments of the present invention in detail with reference to the drawings, and the embodiments are implemented on the premise of the technical solution of the present invention, and detailed embodiments and specific construction processes are given, but the scope of the present invention is not limited to the following embodiments.

The construction method of the concrete slope protection with the green plant ecological capsules comprises the following construction steps:

firstly, trimming a bank slope;

secondly, constructing a bank slope cushion layer, and then binding a lower layer reinforcing mesh and a surface layer reinforcing mesh;

thirdly, installing and fixing each ecological sac unit according to the designed position;

fourthly, pouring concrete;

and fifthly, filling planting soil into each ecological bag, planting green plants and finishing construction.

The concrete slope protection in the embodiment comprises an underwater horizontal section M1, an underwater inclined section M2, an overwater inclined section I M3 and an overwater inclined section II M4 (see figure 1) which are connected in sequence. Wherein the content of the first and second substances,

the ecological sac units N1 (shown in figure 2) installed in the underwater horizontal segment M1 and the underwater inclined segment M2 are uniformly distributed at intervals according to a rectangular lattice shape, and can also be distributed among the stressed reinforcing meshes of the concrete slope protection by adopting other distribution modes according to actual conditions, and are all positioned in a concrete layer below a water level line, and the concrete structure of the ecological sac units is as follows:

every ecological bag unit all includes the ecological bag 1 that is used for the splendid attire soil of planting, and it comprises stereoplasm bag neck 101 and utricule 102, and the open-top of stereoplasm bag neck 101 and concrete bank protection surface parallel and level are sealed through closing cap 2, and the bottom is passed through flaring structure and is linked to each other with utricule 102. The capsule 102 may be a hard capsule made of engineering plastics, and has certain strength and certain shape, so that the capsule can be used as a concrete pouring template; the above-mentioned capsule 102 can also adopt a flexible capsule with a lower price, which is usually made of materials such as polyethylene and polypropylene through blow molding and injection molding, and in order to overcome the disadvantage that the materials are soft and easy to deform, the ecological capsule 1 needs to be pressurized before the installation of the cover 2, so that the ecological capsule can keep a certain shape and can be used as a concrete pouring template.

The diameter of the sealing cover 2 is larger than that of the hard bag neck 101, a pull ring cover convenient to open is adopted, and planting soil is filled into the ecological bag 1 after concrete pouring is finished. In order to provide a good growth environment for green plants, drip irrigation joint pipes 103 are arranged on the hard bag neck 101 of each ecological bag 1, and each drip irrigation joint pipe 103 is in threaded connection with a drip irrigation header pipe. During drought, water and nutrients can be supplemented through the drip irrigation header pipe. In this case, the bottom of capsule 102 does not need to be provided with a drainage structure.

The hard bag neck 101 is integrally provided with two water stop rings 3 with a distance not less than 5cm for preventing the occurrence of permeation damage. In order to fix the water stop ring 3, a plurality of support columns 4 are arranged around the water stop ring, the top of each support column 4 is fixedly connected with the sealing cover 2, and the bottom of each support column 4 is connected with the flaring structure of the ecological sac 1. The support columns 4 are bound and connected with the concrete slope protection surface layer reinforcing mesh and are used for fixing the ecological sac 1 in position; secondly, a fixing ring 5 used for binding and connecting with a concrete slope protection lower layer reinforcing mesh is arranged at the bottom of the capsule body 102; through the solid fixed ring 5 and the connection of stereoplasm bag neck 101 department support column and concrete bank protection reinforcing bar net, can prevent to pour the in-process at the concrete vibration, ecological bag 1 is extruded or takes place the displacement because of the dead weight is lighter under the exogenic action.

(II) the ecological bag units N2 (see figure 3) installed in the overwater inclined I section M3 are distributed at even intervals according to the rectangular lattice shape, and can also be distributed among the concrete slope protection stress reinforcing meshes by adopting other distribution modes according to the actual situation, and are all positioned in the concrete layer above the waterline, and the concrete structure is as follows:

every ecological bag unit all includes the ecological bag 1 that is used for the splendid attire soil of planting, and it comprises stereoplasm bag neck 101 and utricule 102, and the open-top of stereoplasm bag neck 101 and concrete bank protection surface parallel and level are sealed through closing cap 2, and the bottom is passed through flaring structure and is linked to each other with utricule 102. The capsule 102 may be a hard capsule made of engineering plastics, and has certain strength and certain shape, so that the capsule can be used as a concrete pouring template; the above-mentioned capsule 102 can also adopt a flexible capsule with a lower price, which is usually made of materials such as polyethylene and polypropylene through blow molding and injection molding, and in order to overcome the disadvantage that the materials are soft and easy to deform, the ecological capsule 1 needs to be pressurized before the installation of the cover 2, so that the ecological capsule can keep a certain shape and can be used as a concrete pouring template.

The diameter of the sealing cover 2 is larger than that of the hard bag neck 101, a pull ring cover convenient to open is adopted, and planting soil is filled into the ecological bag 1 after concrete pouring is finished. In order to provide a good growth environment for green plants, drip irrigation joint pipes 103 are arranged on the hard bag neck 101 of each ecological bag 1, and each drip irrigation joint pipe 103 is in threaded connection with a drip irrigation header pipe. During drought, water and nutrients can be supplemented through the drip irrigation header pipe. In order to prevent the humidity of the planting soil from being too high, a drain joint pipe 104 is installed at the bottom of the capsule 102 and is connected with a drain main pipe in a threaded manner. The main drainage pipe is laid near the lower layer of reinforcing mesh during the second construction.

The hard bag neck 101 is integrally provided with two water stop rings 3 with a distance not less than 5cm for preventing the occurrence of permeation damage. In order to fix the water stop ring 3, a plurality of support columns 4 are arranged around the water stop ring, the top of each support column 4 is fixedly connected with the sealing cover 2, and the bottom of each support column 4 is connected with the flaring structure of the ecological sac 1. The support columns 4 are bound and connected with the concrete slope protection surface layer reinforcing mesh and are used for fixing the ecological sac 1 in position; secondly, a fixing ring 5 used for binding and connecting with a concrete slope protection lower layer reinforcing mesh is arranged at the bottom of the capsule body 102; through the solid fixed ring 5 and the connection of stereoplasm bag neck 101 department support column and concrete bank protection reinforcing bar net, can prevent to pour the in-process at the concrete vibration, ecological bag 1 is extruded or takes place the displacement because of the dead weight is lighter under the exogenic action.

(III) ecological bag unit N3 (see figure 4) of installation in II sections M4 of slope on water is according to the even interval distribution of rectangle lattice form, also can adopt other ways of laying to lay between concrete bank protection atress reinforcing bar net according to actual conditions, and above-mentioned ecological bag unit is located the waterline, and every ecological bag unit upper portion is located the concrete layer of bank protection, and the lower part is located the soil property bank slope of bank protection, and its concrete structure is as follows:

every ecological bag unit all includes the ecological bag 1 that is used for the splendid attire soil of planting, and it comprises stereoplasm bag neck 101 and utricule 102, and the open-top of stereoplasm bag neck 101 and concrete bank protection surface parallel and level are sealed through closing cap 2, and the bottom is passed through flaring structure and is linked to each other with utricule 102. The capsule 102 may be a hard capsule made of engineering plastics, and has certain strength and certain shape, so that the capsule can be used as a concrete pouring template; the above-mentioned capsule 102 can also adopt a flexible capsule with a lower price, which is usually made of materials such as polyethylene and polypropylene through blow molding and injection molding, and in order to overcome the disadvantage that the materials are soft and easy to deform, the ecological capsule 1 needs to be pressurized before the installation of the cover 2, so that the ecological capsule can keep a certain shape and can be used as a concrete pouring template. And in the second construction step, digging a pit in the section of soil cushion layer according to the designed position so as to install and fix the ecological sacs 1.

The diameter of the sealing cover 2 is larger than that of the hard bag neck 101, a pull ring cover convenient to open is adopted, and planting soil is filled into the ecological bag 1 after concrete pouring is finished. In order to provide a good growth environment for green plants, drip irrigation joint pipes 103 are arranged on the hard bag neck 101 of each ecological bag 1, and each drip irrigation joint pipe 103 is in threaded connection with a drip irrigation header pipe. During drought, water and nutrients can be supplemented through the drip irrigation header pipe. In order to prevent the humidity of the planting soil from being too high, an opening is formed in the bottom of the capsule body 102, and an agricultural polyvinyl alcohol membrane which is self-soluble when meeting water is covered on the opening to form a self-soluble water seepage hole.

The hard bag neck 101 is integrally provided with two water stop rings 3 with a distance not less than 5cm for preventing the occurrence of permeation damage. In order to fix the water stop ring 3, a plurality of support columns 4 are arranged around the water stop ring, the top of each support column 4 is fixedly connected with the sealing cover 2, and the bottom of each support column 4 is connected with the flaring structure of the ecological sac 1. Above-mentioned support column 4 links to each other with the ligature of concrete bank protection surface course reinforcing bar net for carry out the position fixing to ecological bag 1 to and through the fixed of ecological utricule lower part in the soil property side slope, prevent to vibrate at the concrete and pour the in-process, ecological bag 1 is extruded or takes place the displacement because of the dead weight is lighter under the exogenic action.

Compared with the prior art, it has following advantage:

1) plant habitat conditions are provided for riverway slopes, green plant areas are effectively increased, the landscape effect of hydraulic engineering is improved, and the ecological environment of land and water transition spaces is improved;

2) the ecological bag green planting facility does not generate adverse effects such as newly increased land, flood passage invasion, river sedimentation and the like;

3) the structural design meets the requirements of relevant specifications, the structure is safe and reliable, and the device can be applied to the side slopes and the bottom guards of riverways and pools, walls of concrete structures and the like.

It should be noted that in the description of the present invention, terms of orientation or positional relationship such as "front", "rear", "left", "right", "vertical", "horizontal", "inner", "outer", etc., are based on the orientation or positional relationship shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.