Fabricated floor slab, construction method using fabricated floor slab and building structure

文档序号:482350 发布日期:2022-01-04 浏览:18次 中文

阅读说明:本技术 一种装配式楼板及应用其的施工方法和建筑构造 (Fabricated floor slab, construction method using fabricated floor slab and building structure ) 是由 盛博 盛雄 于 2021-11-01 设计创作,主要内容包括:本发明公开了一种装配式楼板及应用其的施工方法和建筑构造,涉及楼板施工技术领域,解决了常见楼板模板的安装以及拆卸工程由于其操作复杂烦琐的缘故,拆除过程会产生大量的人工成本和时间成本,并对楼板施工造成不便的问题,其技术方案要点是,包括:第一加强筋笼体、第一定位件、楼板模组、凝固定型层;第一加强筋笼体通过第一定位件设置于楼板模组上,第一加强筋笼体与楼板模组之间形成有第一间距;本发明采用装配式的楼板模组来直接形成现浇混泥土楼板,其能够有效地节省现场施工时间和施工成本,施工过程无需拆除模板,能够准确地固定定位于楼板模组的内壁上,可避免凝固定型层浇灌时容易造成空洞的问题。(The invention discloses an assembled floor slab, a construction method and a building structure applying the same, relating to the technical field of floor slab construction and solving the problems that the assembly and disassembly engineering of common floor slab templates generates a large amount of labor cost and time cost due to complex and troublesome operation and the disassembly process causes inconvenience to the floor slab construction, and the technical scheme has the key points that: the first reinforcing rib cage body, the first positioning piece, the floor slab module and the solidification shaping layer; the first reinforcing rib cage body is arranged on the floor slab module through the first positioning piece, and a first space is formed between the first reinforcing rib cage body and the floor slab module; the invention adopts the assembled floor slab module to directly form the cast-in-situ concrete floor slab, can effectively save the field construction time and the construction cost, does not need to dismantle a template in the construction process, can be accurately fixed and positioned on the inner wall of the floor slab module, and can avoid the problem that a cavity is easily caused when a solidification shaping layer is poured.)

1. An assembled floor slab, comprising:

a first stiffener cage;

the number of the first positioning pieces is a plurality;

the floor slab modules are a plurality of;

the first reinforcing rib cage body is arranged on the floor slab module through the first positioning piece, and a first interval is formed between the first reinforcing rib cage body and the floor slab module.

2. The fabricated floor of claim 1, wherein two adjacent floor modules are connected side by side, and at least one of the first positioning members is disposed at a junction of two adjacent floor modules.

3. The fabricated floor of claim 1, further comprising:

and the wire pipe is arranged in the floor slab module and is positioned between the two adjacent first positioning pieces.

4. An assembled floor slab as claimed in claim 1, wherein the first locating member comprises:

the first longitudinal part is fixedly connected with the first reinforcing rib cage body;

and the first transverse part is arranged on the side wall of the first longitudinal part in an intersecting manner and is connected with the inner wall of the floor slab module.

5. The fabricated floor of claim 4, wherein the first positioning member further comprises:

and the second longitudinal part is intersected with the first transverse part and is fixedly connected with the first reinforcing rib cage body.

6. The fabricated floor of claim 1, further comprising a setting layer filled in the floor slab module by setting after casting.

7. The fabricated floor of claim 1, further comprising a fixing device, wherein the first positioning member is fixed to the floor slab module by the fixing device.

8. A construction method using a fabricated floor as claimed in any one of claims 1 to 7, comprising the steps of:

pre-installation:

a floor slab mounting position is preset;

dividing the floor slab into a plurality of floor slab modules according to the floor slab installation positions, wherein each floor slab module is correspondingly provided with a plurality of first reinforcing rib cages through first positioning;

the assembling process comprises the following steps:

arranging a plurality of floor slab modules along the bottom surface of the floor slab installation position;

and (3) casting:

and pouring a solidification shaping layer in the floor slab installation position to fill the floor slab module.

9. A building construction, characterized in that it is applied with a fabricated floor as claimed in any one of claims 1 to 7, further comprising:

a second stiffener cage;

a plurality of second positioning pieces;

the beam modules are connected to the bottom surface of the floor slab module and communicated with the floor slab module;

the second reinforcing rib cage body is fixed on the beam module through the second positioning piece; a second space is formed between the second reinforcing rib cage body and the beam module;

the solidification shaping layer is filled in the beam module and the floor slab module at the same time.

10. A building construction, characterized in that it is applied with a fabricated floor as claimed in any one of claims 1 to 7, further comprising:

a third stiffener cage;

a plurality of third positioning pieces;

the column modules are connected to the bottom surface of the floor slab module and communicated with the floor slab module;

the third reinforcing rib cage body is fixed on the column module through the third positioning piece; a third space is formed between the third reinforcing rib cage body and the column module;

the solidification shaping layer is filled in the column module and the floor module at the same time.

Technical Field

The invention relates to the technical field of floor slab construction, in particular to an assembled floor slab, a construction method using the same and a building structure.

Background

In traditional building construction process, concrete floor all need finalize the design through the template of installing in advance before pouring the shaping, then the reuse bracing piece supports the template, still need demolish after concrete placement accomplishes.

In the construction process of the floor slab template installation project, the template and the support rod piece which are generally made of complete wood are cut according to the variable sizes of cast-in-place concrete members, so a large amount of raw wood is wasted in the cutting process; after the concrete floor is formed, the formwork around the concrete floor is manually dismantled, and it is known that the installation and dismantling of the formwork is complicated and troublesome in operation, and the dismantling process generates a large amount of labor cost and time cost, which is a long time-consuming processing procedure with high construction cost, and further causes inconvenience to the floor construction.

Disclosure of Invention

The invention aims to provide an assembled floor slab, a construction method and a building structure applying the assembled floor slab, wherein the assembled floor slab module is adopted to directly form a cast-in-place concrete floor slab, the on-site construction time and the construction cost can be effectively saved, a template is not required to be dismantled in the construction process, and the assembled floor slab can be accurately fixed and positioned on the inner wall of the floor slab module so as to avoid the problem that a cavity is easily caused when a solidification shaping layer is poured.

The technical purpose of the invention is realized by the following technical scheme: an assembled floor slab comprising:

a first stiffener cage;

the number of the first positioning pieces is a plurality;

the floor slab modules are a plurality of;

the first reinforcing rib cage body is arranged on the floor slab module through the first positioning piece, and a first space is formed between the first reinforcing rib cage body and the floor slab module;

the invention further provides the following steps: and solidifying and shaping the layer, and solidifying and filling the solidified layer in the floor slab module after pouring.

Through adopting above-mentioned technical scheme, floor installation position and predetermined floor phase-match, the first strengthening rib cage body and first locating piece can be fixed on the floor module in advance according to the size of floor installation position, and when the field installation, each floor module can the snap-on become whole, and then reduces the work load of arranging the first strengthening rib cage body on the spot to improve the efficiency of construction effectively. The first reinforcing rib cage body is formed by bending and combining a plurality of reinforcing steel bars, so that an error exists between the actual size and the preset size, the positioning of the first reinforcing rib cage body in the floor slab module is prone to being deviated, and the linear shape of the first positioning piece is fixedly attached to the side wall of the first reinforcing rib cage body, so that the problem that the size of the first reinforcing rib cage body is not easy to control can be solved; therefore, the problem that the first reinforcing rib cage body cannot be accurately installed and positioned in the floor slab module is solved, and the reasonable distance between the first reinforcing rib cage body and the concrete floor slab surface layer of the floor slab module is reserved so as to avoid the problem that a cavity is easily caused when a solidification setting layer is poured; secondly, first strengthening rib cage body can be accurately fixed the inner wall of being positioned the floor module through first setting element, and it is thus visible, through first setting element, first strengthening rib cage body can become the fixed and the basic frame who fixes a position of floor module in the floor module, and then improves the wholeness.

Secondly, through first setting element, formed accurate, the first interval that agrees with between the first strengthening rib cage body and the floor module, because the laminating of first setting element is fixed in on the lateral wall of the first strengthening rib cage body, consequently can make this first interval more accurate, and then improve the volume of the solidification design layer of pouring in the first interval and the precision of shape to the machining precision of engineering has been improved effectively.

Secondly, when a large number of solidification shaping layers are poured into the floor slab module, the floor slab module needs to bear huge external force generated during pouring (the external force is from impact force generated when the weight of the solidification shaping layers falls), but because the first reinforcing rib cage body, the first positioning piece and the floor slab module form a firm plane transverse stress floor slab model, the pouring process can be more stable and safe;

secondly, because the first positioning piece is a prefabricated piece, the width of the first positioning piece can be widened by adjusting before construction, so that the scheme has a good self-supporting effect; in the pouring process, the first positioning piece is arranged, so that the first positioning piece can be crossed with the on-site temporary transverse supporting die beam positioned below the floor slab module to form the bearing grid of the concrete floor slab module in a crossed mode.

The floor slab module in the scheme is a fiber cement board; in the scheme, the cast-in-place concrete floor is directly formed by adopting the assembled floor module, so that the construction processes of manufacturing, installing and dismantling the traditional cast-in-place concrete floor template can be saved, and the site construction time and the construction cost can be effectively saved;

secondly, the scheme does not need to dismantle a template, and also eliminates the working procedure of leveling and decorating after the traditional cast-in-place concrete floor slab is formed, so that the concrete floor slab is hidden in the floor slab formed by the floor slab module, namely, the floor slab module for the exterior decoration suspended ceiling and the concrete floor slab (namely, the solidified setting layer is formed after the floor slab module is solidified) are integrated; only need with the gap between two adjacent floor slab modules carry out the processing of caulking can, need not to carry out whole batch ash to whole floor once more and handle. To sum up, this scheme combines together through the assembled floor module with traditional concrete load-bearing structure (first strengthening rib cage body + solidification design layer) and energy-concerving and environment-protective, can be through the time and the cost of saving field operation effectively, and then can reduce the pollution that traditional concrete work progress led to the fact the environment.

According to the invention, two adjacent floor slab modules are connected in parallel, and at least one first positioning piece is arranged at the joint of the two adjacent floor slab modules.

Through adopting above-mentioned technical scheme, first locating piece can be on accomplishing the basis of first strengthening rib cage body location in the floor module, it can also be used for the lap seam formula sealing connection of junction between two adjacent floor modules, so that improve the waterproof nature behind the floor shaping, with the concrete thick liquid condition of leaking outward that can avoid pouring concrete fashion not solidify, the pin bolt connection between the floor module has been formed again, be favorable to the seam control and the filling of ceiling type floor module.

The invention further provides the following steps:

and the wire pipe is arranged in the floor slab module and is positioned between the two adjacent first positioning pieces.

By adopting the technical scheme, specifically, the wire pipe is positioned on the central line of the distance between two adjacent first positioning pieces, extends along the size of the floor slab module and has two closed ends; when the solidification shaping layer is solidified after pouring, the pre-embedded wire pipe can facilitate wiring (such as arrangement of wires, communication optical fiber wires and the like) of constructors so as to reduce damage to the integral structure of the floor slab; before the wiring, because the first locating piece of this scheme adopts steel material to make, consequently constructor accessible magnet finds the first locating piece of hiding in floor module rear fast, and in addition the wire rod pipe sets up in the central line of interval or certain concrete position between two adjacent first locating pieces, and then realizes under the condition that does not destroy floor module, finds out pre-buried wire rod pipe fast to in the efficiency of improvement construction wiring.

In a further aspect of the invention, the first positioning element comprises:

the first longitudinal part is fixedly connected with the first reinforcing rib cage body;

and the first transverse part is arranged on the side wall of the first longitudinal part in an intersecting manner and is connected with the inner wall of the floor slab module.

Through adopting above-mentioned technical scheme, constitute the first locating piece concrete structure that the cross-section is the L type after first longitudinal portion and the combination of first horizontal portion.

In a further aspect of the present invention, the first positioning element further comprises:

and the second longitudinal part is intersected with the first transverse part and is fixedly connected with the first reinforcing rib cage body.

Through adopting above-mentioned technical scheme, first longitudinal portion, first horizontal portion, the longitudinal portion three of second have constituted the first locating piece concrete structure that a cross-section is the C type.

According to the further arrangement of the invention, the number of the first reinforcing rib cages is at least two, and two adjacent first reinforcing rib cages are fixedly connected.

By adopting the technical scheme, according to the actual area of the floor installation position, the first reinforcing rib cage body can be formed by the first reinforcing rib cage bodies with at least two subclasses in number in order to facilitate the pre-installation and transportation of the first reinforcing rib cage body; when the first reinforcing rib cage body is transported to a floor slab installation site, the installation can be directly finished. And because two adjacent first reinforcing rib cages are fixedly connected, the integrity of the whole structure can be kept.

The first positioning piece is fixed on the floor slab module through the fixing device.

By adopting the technical scheme, in the scheme, the fixing device is a screw, in particular a self-tapping screw; after the fixing device sequentially penetrates through the floor slab module and the first positioning piece, the first positioning piece is fixed on the floor slab module at the moment, a pin joint structure between the first positioning piece and the floor slab module is formed, and the first reinforcing rib cage body, the first positioning piece and the floor slab module form a firm plane transverse stress model; so that the pouring process is more stable and safer.

The invention further provides a construction method, which is applied to the fabricated floor slab, and comprises the following steps:

pre-installation:

a floor slab mounting position is preset;

dividing the floor slab into a plurality of floor slab modules according to the floor slab installation positions, wherein each floor slab module is correspondingly provided with a plurality of first reinforcing rib cages through first positioning;

the assembling process comprises the following steps:

arranging a plurality of floor slab modules along the bottom surface of the floor slab installation position;

and (3) casting:

and pouring a solidification shaping layer into the floor slab installation position.

Through adopting above-mentioned technical scheme, this scheme provides one kind with the concrete construction method of assembled floor assorted. The first reinforcing rib cage body and the first positioning piece can be fixed on the floor slab module in advance according to the size of the floor slab installation position, and when the floor slab module is installed on site, each floor slab module can be directly fixed into a whole, so that the workload of arranging the first reinforcing rib cage body on site is reduced, and the construction efficiency is effectively improved.

In a further aspect of the present invention, a building structure to which the fabricated floor is applied further includes:

a second stiffener cage;

a plurality of second positioning pieces;

the beam modules are connected to the bottom surface of the floor slab module and communicated with the floor slab module;

the second reinforcing rib cage body is fixed on the beam module through the second positioning piece; a second space is formed between the second reinforcing rib cage body and the beam module;

the solidification shaping layer is filled in the beam module and the floor slab module at the same time.

By adopting the technical scheme, the beam mounting position is communicated with the floor mounting position, namely the beam module and the floor module are communicated, so that when the solidification shaping layer is poured into the floor module, the solidification shaping layer can be poured into the beam module at the same time, so that the floor and the beam have good integrity and are connected more firmly; similarly, the second positioning piece can also be used for solving the problem that the size of the second reinforcing rib cage is not well controlled, and the reasonable space of a concrete surface layer (a solidification layer) between the second reinforcing rib cage and the beam module is reserved so as to avoid the problem that the concrete is easy to cause a hole during concrete pouring.

Through the setting of second setting element, formed accurate, the second interval that agrees with between the second strengthening rib cage body and the roof beam module to because on the laminating of second setting element is fixed in the lateral wall of the second strengthening rib cage body, consequently can make this second interval more accurate, and then improve the volume of the solidification design layer of pouring in the second interval and the precision of shape, thereby improved the machining precision of engineering effectively.

Secondly, in a similar way, the scheme does not need to additionally increase a supporting and reinforcing structure at the periphery of the beam module in the pouring process. Therefore, the scheme provides the bearing structure combining the building structure and the floor slab, the installation and the disassembly of the template are not needed in the construction process, the beam and the floor slab are made to have higher integrity, and the bearing structure after combination is firmer.

In a further aspect of the present invention, a building structure to which the fabricated floor is applied further includes:

a third stiffener cage;

a plurality of third positioning pieces;

the number of the column modules is a plurality;

the third reinforcing rib cage body is fixed on the column module through the third positioning piece; a third space is formed between the third reinforcing rib cage body and the column module;

the solidification shaping layer is filled in the column module and the floor module at the same time.

By adopting the technical scheme, the column module is communicated with the floor slab module, so that when the solidification shaping layer is poured into the column module, the solidification shaping layer can be poured into the floor slab module at the same time, the integration of the column and the top floor is stronger, and the connection between the column and the top floor is firmer; similarly, the third positioning piece can also be used for solving the problem that the size of the third reinforcing rib cage is not easy to control, and the reasonable space of the concrete surface layer (solidification and shaping layer) between the third reinforcing rib cage and the column module is reserved so as to avoid the problem that the concrete is easy to cause holes during concrete pouring.

Through the third setting element, formed accurate, the third interval that agrees with between the third strengthening rib cage body and the post module, because the laminating of third setting element is fixed in on the lateral wall of the third strengthening rib cage body, consequently can make this third interval more accurate, and then the volume of the solidification shaping layer of pouring in improving the third interval and the precision of shape to the machining precision of engineering has been improved effectively.

Secondly, in a similar way, the scheme does not need to additionally increase a supporting and reinforcing structure at the periphery of the column module in the pouring process. Therefore, the scheme provides the bearing structure combining the building structure and the floor slab, the installation and the disassembly of the template are not needed in the construction process, the column and the floor slab are made to have higher integrity, and the bearing structure after combination is firmer.

In summary, the present invention has the following beneficial effects:

1. the cast-in-place concrete floor is directly formed by adopting the assembled floor slab module, and a template does not need to be dismantled in the construction process;

2. the construction processes of manufacturing, installing and dismantling the traditional cast-in-place concrete floor slab template are saved, and the site construction time and the construction cost can be effectively saved;

3. the problem that the traditional first reinforcing rib cage body is inconvenient to install due to self size difference is solved, and the first reinforcing rib cage body can be accurately fixed and positioned on the inner wall of the floor slab module, so that the first reinforcing rib cage body has good construction precision;

4. a reasonable space between the first reinforcing rib cage body and the concrete floor surface layer of the floor module is reserved, so that the problem that a cavity is easily caused when a solidification setting layer is poured can be avoided;

5. can be crossed with the on-site temporary transverse supporting die beams positioned below the floor slab module to form the bearing grid of the concrete floor slab module in a crossed manner.

In general, the cast-in-place concrete floor is directly formed by the assembled floor slab module, the on-site construction time and the construction cost can be effectively saved, a template does not need to be dismantled in the construction process, the assembled floor slab module can be accurately fixed and positioned on the inner wall of the floor slab module, and the problem that a cavity is easily caused when a solidification shaping layer is poured can be avoided.

Drawings

FIG. 1 is a schematic structural diagram of the first embodiment;

FIG. 2 is an enlarged view at A in FIG. 1;

FIG. 3 is an enlarged view at B in FIG. 1;

FIG. 4 is a schematic structural view of a T-shaped combination of a floor slab and a beam in the third embodiment;

FIG. 5 is an enlarged view at C in FIG. 4;

FIG. 6 is an enlarged view at D of FIG. 4;

FIG. 7 is a schematic view of a half-section structure of a T-shaped floor and beam combination in the third embodiment;

FIG. 8 is an enlarged view at E in FIG. 7;

FIG. 9 is a schematic view of a 7-shaped half-section structure of a floor slab and a beam in the third embodiment;

FIG. 10 is an enlarged view at F of FIG. 9;

FIG. 11 is a schematic structural view of a fourth pillar according to an embodiment;

fig. 12 is an enlarged view at G in fig. 11.

Reference numerals: 11. a first pitch; 12. a second pitch; 13. a third pitch; 21. a floor slab mounting position; 22. a beam mounting position; 221. a C-shaped member; 23. a post mounting location; 31. a first stiffener cage; 32. a second stiffener cage; 33. a third stiffener cage; 41. a first positioning member; 411. a first longitudinal portion; 412. a first lateral portion; 413. a second longitudinal portion; 42. a second positioning member; 43. a third positioning member; 51. a floor slab module; 52. a beam module; 521. a beam wall panel; 522. an interlayer; 53. a column module; 6. solidifying and shaping the layer; 7. a wire tube; 8. and (4) a fixing device.

Detailed Description

The present invention will be described in further detail with reference to the accompanying drawings.

The first embodiment is as follows:

the utility model provides an assembled floor, as shown in fig. 1, fig. 2 and fig. 3, includes floor installation position 21, first strengthening rib cage 31, the first locating piece 41 of a plurality of, a plurality of floor module 51, solidifies design layer 6, specifically as follows:

the floor installation position 21 is matched with the preset specification of the floor.

The floor slab modules 51 are arranged along the bottom surface of the floor slab installation site 21; the floor slab module 51 in this scheme is a fiber cement board.

The number of the first reinforcing rib cages 31 is at least two, and the two adjacent first reinforcing rib cages 31 are fixedly connected. According to the actual area of the floor installation site 21, in order to facilitate the pre-installation and transportation of the first reinforcement cage body 31, the first reinforcement cage body 31 may be composed of at least two subclasses of first reinforcement cage bodies 31; the first reinforcement cage body 31 is transported to the floor installation site 21 and can be directly installed. And because of the fixed connection between two adjacent first reinforcement cage bodies 31, it is able to maintain the integrity of the overall structure.

The first reinforcing cage body 31 is arranged on the floor slab module 51 through the first positioning piece 41; specifically, the present embodiment further includes a fixing device 8, and the first positioning element 41 is fixed on the floor slab module 51 through the fixing device 8. In the present embodiment, the fixing device 8 is a screw, specifically a self-tapping screw; after the fixing device 8 sequentially penetrates through the floor slab module 51 and the first positioning piece 41, the first positioning piece 41 is fixed on the floor slab module 51 at the moment, a pin joint structure between the first positioning piece 41 and the floor slab module 51 is formed, and the first reinforcing rib cage body 31, the first positioning piece 41 and the floor slab module 51 form a firm plane transverse stress model; so that the pouring process is more stable and safer.

A first gap 11 is formed between the first reinforcement cage 31 and the floor slab module 51.

The solidification setting layer 6 is solidified and filled in the floor slab module 51 after being poured. In this embodiment, the setting bed 6 is concrete.

Because the first reinforcing rib cage body 31 is formed by bending and combining a plurality of reinforcing steel bars, the actual size of the first reinforcing rib cage body 31 is easy to have an error with the preset size, so that the positioning of the first reinforcing rib cage body 31 in the floor installation position 21 is easy to cause deviation, and the linear type of the first positioning piece 41 is fixedly attached to the side wall of the first reinforcing rib cage body 31 at the moment, so that the problem that the size of the first reinforcing rib cage body 31 is not easy to control can be solved; therefore, the scheme not only solves the problem that the first reinforcing rib cage body 31 cannot be accurately installed and positioned in the floor slab module 51, but also reserves a reasonable distance between the first reinforcing rib cage body 31 and the concrete floor slab surface layer of the floor slab module 51 so as to avoid the problem that a cavity is easily caused when the solidification shaping layer 6 is poured; secondly, first strengthening rib cage body 31 can be fixed the location on the inner wall of floor module 51 through first locating piece 41 accurately, and from this it can be seen that, through first locating piece 41, first strengthening rib cage body 31 can become the fixed foundation frame with the location of floor module 51 in floor module 51, and then improves the wholeness that solidifies after the pouring.

Secondly, through first locating piece 41, formed accurate, the first interval 11 that agrees with between first strengthening rib cage body 31 and the floor module 51, because the laminating of first locating piece 41 is fixed in on the lateral wall of first strengthening rib cage body 31, consequently can make this first interval 11 more accurate, and then improve the volume of the solidification shaping layer 6 of pouring in first interval 11 and the precision of shape to the machining precision of engineering has been improved effectively.

Secondly, when a large number of solidification shaping layers 6 are poured into the floor slab module 51, the floor slab module 51 needs to bear a huge external force generated during pouring (the external force is from the impact force generated when the weight of the solidification shaping layers 6 falls down), but because the first reinforcing rib cage body 31, the first positioning piece 41 and the floor slab module 51 form a firm floor slab model with a horizontal stress on the plane, the pouring process can be more stable and safe;

secondly, because the first positioning piece 41 is a prefabricated piece, the width of the first positioning piece 41 can be widened by adjusting before construction, so that the scheme has a good self-supporting effect; in the pouring process, the first positioning piece 41 is arranged, so that the first positioning piece can be crossed with the on-site temporary transverse supporting die beam positioned below the floor slab module 51 to form the bearing grid of the concrete floor slab module 51 in a crossed mode.

Secondly, the scheme does not need to disassemble a template, and also eliminates the process of performing lime leveling and decoration treatment after the traditional cast-in-place concrete floor is formed, so that the concrete floor is hidden in the floor formed by the floor module 51, namely the floor module 51 for decorating the suspended ceiling by external decoration and the concrete floor (namely the floor module 51 formed by solidifying the solidification shaping layer 6 in the floor module 51) are integrated; only the gap between two adjacent floor slab modules 51 needs to be filled, and the surface of the whole floor slab does not need to be subjected to full-batch ash treatment again. In conclusion, this scheme combines together traditional concrete load-bearing structure (first strengthening rib cage body 31+ solidification design layer 6) and energy-concerving and environment-protective assembled floor module 51, can be through saving field operation's time and cost effectively, and then can reduce the pollution that traditional concrete work progress led to the fact the environment.

Specifically, the number of the floor slab modules 51 may be at least two according to the area of the actual floor slab installation position 21, two adjacent floor slab modules 51 are connected side by side, and at least one first positioning member 41 is disposed at the connection position of the two adjacent floor slab modules 51.

Because the assembled floor slab module 51 is adopted to directly form the cast-in-place concrete floor slab, the construction processes of the manufacturing, installation and dismantling operation of the traditional cast-in-place concrete floor slab template can be saved, and the field construction time and the construction cost can be effectively saved; first locating piece 41 can be on the basis of accomplishing first strengthening rib cage body 31 location in floor module 51, it can also be used for the lap seam formula sealing connection of junction between two adjacent floor modules 51, so that improve the waterproof nature behind the floor shaping, with the condition that can avoid the concrete thick liquid that the pouring concrete fashion did not solidify to leak outward, the pin bolt connection between floor module 51 has been formed again, be favorable to ceiling type floor module 51's seam control and fill.

As shown in fig. 1 and fig. 3, the present embodiment further includes a wire tube 7, and the wire tube 7 is disposed in the floor slab module 51 and located between two adjacent first positioning members 41. Specifically, the wire pipe 7 is located on a center line of a distance between two adjacent first positioning members 41, and the wire pipe 7 extends along the dimension of the floor slab module 51 and is closed at both ends thereof.

When the solidification shaping layer 6 is solidified after pouring, the pre-embedded wire pipe 7 can facilitate wiring of constructors (such as arrangement of wires such as electric wires and communication optical fiber wires) so as to reduce damage to the integral structure of the floor slab; before the wiring, because the first locating piece 41 of this scheme adopts steel material to make, consequently constructor accessible magnet finds the first locating piece 41 of hiding in floor module 51 rear fast, in addition wire rod pipe 7 sets up in the central line of interval or certain concrete size position between two adjacent first locating pieces 41, and then realizes under the condition that does not destroy floor module 51, finds out pre-buried wire rod pipe 7 fast to in the efficiency of improvement construction wiring.

As shown in fig. 1 and 2, the first positioning member 41 includes a first longitudinal portion 411, a first transverse portion 412, and a second longitudinal portion 413, and the first longitudinal portion 411 is fixedly connected to the first cage 31; the first longitudinal portion 411 is parallel to the second longitudinal portion 413. The first longitudinal portion 411 is perpendicular to the first transverse portion 412, the second longitudinal portion 413 is perpendicular to the first transverse portion 412, and the first transverse portion 412 is attached to the inner wall of the floor slab module 51. The first longitudinal portion 411 and the second longitudinal portion 413 are both fixedly connected to the first cage 31.

The first longitudinal portion 411, the first transverse portion 412 and the second longitudinal portion 413 form a specific structure of the first positioning element 41 with a C-shaped cross section. However, the first longitudinal portion 411 and the first transverse portion 412 can also form a specific structure of the first positioning member 41 with an L-shaped cross section. The first longitudinal portion 411 and the second longitudinal portion 413 are both steel members having an L-shaped cross section.

Example two

A construction method using a fabricated floor as described in the first embodiment, comprising the steps of:

pre-installation:

a floor slab mounting position 21 is preset;

dividing the floor slab installation position 21 into a plurality of floor slab modules 51, wherein each floor slab module 51 is correspondingly provided with a plurality of first reinforcing rib cage bodies 31 through first positioning;

the assembling process comprises the following steps:

arranging a plurality of floor slab modules 51 along the bottom surface of the floor slab installation position 21;

and (3) casting:

and pouring the solidification shaping layer 6 into the floor slab installation position 21 until the solidification shaping layer 6 covers the first reinforcing rib cage body 31.

From this, this scheme provides one kind with the concrete construction method of assembled floor assorted, divides floor module 51 into a plurality of according to the size of floor installation position 21, then accomplishes prefabricating first strengthening rib cage body 31 in the mill to with first strengthening rib cage body 31 correspondence be fixed in on every floor module 51, and then make it can accomplish the equipment with each floor module 51 at the job site conveniently, with the time of reduction site operation.

EXAMPLE III

A building structure, which is applied with a fabricated floor as described in the first embodiment, as shown in fig. 4, 5 and 6, further comprising a beam installation site 22, a second reinforcement cage 32, a second positioning member 42 and a beam module 52, specifically as follows:

the beam mounting position 22 is matched with the preset specification of the beam and communicated with the floor slab mounting position 21; as shown in fig. 7 and 8, in the present embodiment, the beam installation site 22 and the floor installation site 21 are in a "T" shape; but not limited thereto, the beam installation site 22 and the floor installation site 21 may also be in a "7" shape, as shown in fig. 9 and 10; the beam mounting site 22 is constituted by a C-shaped member 221, which enables the specification of the beam mounting site 22 to be more flat.

The second reinforcing rib cage body 32 is fixedly connected with the first reinforcing rib cage body 31, and particularly is welded and fixed, so that the floor slab and the beam are more integrated after concrete is poured and formed;

a plurality of second positioning parts 42; the second positioning member 42 has the same structure as the first positioning member 41. Similarly, the joint of the second positioning member 42 and the first positioning member 41 is fixedly connected by welding.

A plurality of beam modules 52, which are arranged around the outer circumference of the beam mounting position 22, attached to the bottom surface of the floor slab module 51, and communicated with the floor slab module 51; the beam module 52 comprises an interlayer 522 and at least two beam wall plates 521, and the interlayer 522 is arranged between two adjacent beam wall plates 521;

the second rebar cage 32 is secured to the beam module 52 by a second locator 42, so that the second rebar cage 32 is mounted to the beam mounting location 22; a second spacing 12 is formed between the second reinforcement cage 32 and the beam module 52;

the solidification setting layer 6 is simultaneously filled in the beam installation position 22 and the floor installation position 21.

Because the beam installation position 22 is communicated with the floor installation position 21, when the solidification shaping layer 6 is poured into the floor installation position 21, the solidification shaping layer 6 can be poured into the beam installation position 22 at the same time, so that the floor and the beam have good integrity and are connected more firmly; similarly, the second positioning element 42 can also be used to solve the problem of the size of the second stiffener cage 32 being difficult to control, and a reasonable distance between the second stiffener cage 32 and the floor slab module 51 is reserved for the concrete surface layer (the solidification layer 6) to avoid the problem of void formation during concrete pouring.

Through the setting of second setting element 42, accurate, the second interval 12 that agrees has been formed between second strengthening rib cage 32 and the roof beam module 52 to because the laminating of second setting element 42 is fixed in on the lateral wall of second strengthening rib cage 32, consequently can make this second interval 12 more accurate, and then the volume of the solidification shaping layer 6 of pouring in improving second interval 12 and the precision of shape, thereby improved the machining precision of engineering effectively.

Secondly, in a similar way, the scheme does not need to additionally increase a supporting and reinforcing structure at the periphery of the beam module 52 in the casting process. Therefore, the scheme provides the bearing structure combining the building structure and the floor slab, the installation and the disassembly of the template are not needed in the construction process, the beam and the floor slab are made to have higher integrity, and the bearing structure after combination is firmer.

Example four

A building structure, as shown in fig. 11 and 12, to which a fabricated floor as described in the first embodiment is applied, further comprising a column installation site 23, a third reinforcement cage 33, a third positioning member 43, a column module 53:

the column mounting position 23 is matched with the preset specification of the column and is communicated with the floor mounting position 21;

the third reinforcing rib cage body 33 and the third reinforcing rib cage body 33 are fixedly connected with the first reinforcing rib cage body 31, and particularly are welded and fixed, so that the column and the floor slab can be more integrated after concrete is poured and formed;

a plurality of third positioning members 43; the third positioning member 43 has the same structure as the first positioning member 41; the joint of the third positioning element 43 and the first positioning element 41 is fixedly connected by welding.

A plurality of column modules 53 arranged so as to surround the outer peripheral side of the column mounting portion 23;

the third reinforcement cage 33 is fixed to the column module 53 by the third positioning member 43, so that the third reinforcement cage 33 is mounted to the column mounting position 23; a third space 13 is formed between the third reinforcing rib cage 33 and the column module 53;

the solidification setting layer 6 is simultaneously filled in the column installation position 23 and the floor installation position 21, specifically in the column module 53 and the floor module 51.

Because the column installation position 23 is communicated with the floor installation position 21, when the solidification shaping layer 6 is poured into the column module 53, the solidification shaping layer 6 can be poured into the floor module 51 at the same time, so that the column and the top floor are integrated more firmly, and the connection between the column and the top floor is firmer; similarly, the third positioning element 43 can also be used to solve the problem that the size of the third reinforcement cage 33 is not easy to control, and a reasonable distance between the third reinforcement cage 33 and the column module 53 is reserved for the concrete surface layer (the solidification layer 6) to avoid the problem that a void is easily caused during concrete pouring.

Through the third positioning piece 43, an accurate and fit third distance 13 is formed between the third reinforcing rib cage body 33 and the column module 53, and the third positioning piece 43 is attached and fixed to the side wall of the third reinforcing rib cage body 33, so that the third distance 13 is more accurate, the volume and the shape accuracy of the solidification shaping layer 6 poured in the third distance 13 are improved, and the engineering processing accuracy is effectively improved.

Secondly, in a similar way, the scheme does not need to additionally increase a supporting and reinforcing structure at the periphery of the column module 53 in the pouring process. Therefore, the scheme provides the bearing structure combining the building structure and the floor slab, the installation and the disassembly of the template are not needed in the construction process, the column and the floor slab are made to have higher integrity, and the bearing structure after combination is firmer.

The present embodiment is only for explaining the present invention, and it is not limited to the present invention, and those skilled in the art can make modifications of the present embodiment without inventive contribution as needed after reading the present specification, but all of them are protected by patent law within the scope of the claims of the present invention.