Large-diameter long-distance linear jacking pipe jacking method

文档序号:826591 发布日期:2021-03-30 浏览:12次 中文

阅读说明:本技术 一种大直径长距离直线顶管顶进方法 (Large-diameter long-distance linear jacking pipe jacking method ) 是由 余世祥 林键 安刚建 王伟超 杜美 曹广勇 林青龙 沃云舟 李朝蒙 于 2020-12-09 设计创作,主要内容包括:本发明公开一种大直径长距离直线顶管顶进方法,包括步骤:勘察顶进区域的深度和土层性质;进行始发井和接收井洞口的土体加固;在地面设置抽水井;安装顶管设备;设置激光经纬仪;出洞前,采用所述激光经纬仪测量顶管机的轴线位置,确保顶进方向沿着顶进设计轴线进行;打开封门和所述顶管设备,使顶管机开始切削土体出洞;在顶管机进洞前,再次测量顶管机的轴线位置,确保偏移在允许范围内,确保顶管机顺利进洞;本技术方案所采用的装置操作简单,费用低,各个装置和总控制系统的紧密连接使整个顶管顶进过程协调进行,提高了工作效率,具有良好的经济效益。(The invention discloses a large-diameter long-distance linear jacking pipe jacking method, which comprises the following steps of: surveying the depth and soil layer properties of the jacking region; soil body reinforcement of the starting well and the receiving well opening is carried out; arranging a pumping well on the ground; installing pipe jacking equipment; setting a laser theodolite; before exiting the tunnel, measuring the axis position of the pipe jacking machine by using the laser theodolite, and ensuring that the jacking direction is carried out along the jacking design axis; opening a sealing door and the pipe jacking equipment to enable the pipe jacking machine to start cutting soil to exit; before the push bench enters the hole, measuring the axis position of the push bench again to ensure that the deviation is within an allowable range and the push bench enters the hole smoothly; the device adopted by the technical scheme is simple to operate and low in cost, the tight connection between each device and the master control system enables the whole jacking process of the jacking pipe to be coordinated, the working efficiency is improved, and the device has good economic benefits.)

1. A large-diameter long-distance linear jacking pipe jacking method is characterized by comprising the following steps:

s1, surveying the depth and soil layer properties of the jacking area;

s2, soil body reinforcement of the starting well and the receiving well opening is carried out;

s3, arranging a pumping well on the ground;

s4, installing pipe jacking equipment;

s5, setting a laser theodolite;

s6, before exiting the tunnel, measuring the axis position of the pipe jacking machine by using the laser theodolite, and ensuring that the jacking direction is carried out along the jacking design axis;

s7, opening the sealing door and the pipe jacking equipment to enable the pipe jacking machine to start cutting soil to exit;

and S8, before the push bench enters the hole, measuring the axial position of the push bench again to ensure that the deviation is within the allowable range and the push bench enters the hole smoothly.

2. The large-diameter long-distance linear jacking pipe jacking method of claim 1, wherein a drag reduction mode of jacking while grouting is adopted, a plurality of annular grouting ports are arranged on the pipe wall of the tool pipe, and drag reduction slurry is injected to the outer side of the tool pipe through the grouting ports by arranging a grouting pipe.

3. The large diameter long reach linear pipe jacking method of claim 1, wherein said laser theodolite is placed on the ground of said originating well, a plurality of laser survey points are spaced apart in the tool pipe conduit, a lightplate is located at the nose, and a laser line emitted by said laser theodolite passes through each of said laser survey points and said lightplate center to coincide with the jacking axis.

4. The large-diameter long-distance linear jacking pipe jacking method of claim 1, wherein the machine head is provided with a deviation rectifying jack; during jacking of the pipe jacking machine, the axis track of the laser theodolite is monitored in real time, and when the axis curve of the laser theodolite and the actual jacking curve of the pipe jacking machine deviate by more than 5mm, the deviation is corrected through the deviation correcting jack.

5. The large-diameter long-distance linear push pipe jacking method according to claim 4, wherein pressure sensors are arranged around the grouting pipe and the push pipe machine, and when the push pipe machine jacks, the pressure value of the pressure sensor is monitored in real time, and the deviation direction of the push pipe machine is predicted according to the pressure value of the pressure sensor, so that deviation correction preparation is made in advance.

6. The large-diameter long-distance linear pipe jacking method according to claim 5, wherein a master control system is arranged on the ground, and the master control system is connected with the deviation rectifying jack, the laser theodolite, the pressure sensor and the pipe jacking machine.

7. The large-diameter long-distance linear jacking pipe jacking method according to claim 2, wherein a grouting central station is arranged on the ground, and the grouting central station injects the anti-drag slurry to the outer side of the tool pipe through the connection of the grouting pipe and the grouting port.

8. The large-diameter long-distance linear jacking pipe jacking method according to claim 7, wherein an intermediate station and a grouting replenishment station are arranged in said pipeline at an interval of 500m, and said grouting replenishment station and said grouting main station are connected through said grouting pipe.

9. The large-diameter long-distance linear pipe jacking method according to claim 1, wherein in step S2, high-pressure jet grouting piles are driven around the originating well and lined with 0.8m thick lining walls; the receiving well is reinforced by adopting a high-pressure jet grouting pile, and the reinforcing strength of the soil body at the hole opening of the receiving well is higher than that of the soil body at the hole opening of the starting well.

10. The large-diameter long-distance linear jacking pipe jacking method of claim 9, wherein in step S2, grouting holes are preset at the high-pressure jet grouting piles in the direction of entering and exiting, grouting reinforcement is performed on the soil body at the hole opening through the grouting holes, steel plates are used for sealing the door, cement slurry is used as grouting material, and the grouting strength is less than 2 MPa.

Technical Field

The invention relates to the technical field of pipe jacking construction, in particular to a large-diameter long-distance linear pipe jacking method.

Background

The pipe-jacking construction technology is a trenchless technology for laying underground pipelines developed after the shield technology, and has great advantages compared with the traditional technology for laying underground pipelines. The method does not need to excavate stratum, does not need to dismantle peripheral buildings and facilities, can effectively protect ground traffic and earth surface buildings even if the method is constructed in cities, does not generate overlarge noise, does not influence the surrounding environment, has safe and high construction efficiency and low construction cost, develops rapidly in recent years, and is more and more widely applied to municipal traffic, water conservancy and roads, electric power and communication line laying and other aspects of construction. With the more mature construction technology of the jacking pipe, the trend is towards the direction of the jacking distance and the diameter of the jacking pipe becoming larger and larger.

Compared with curve pipe jacking construction, the jacking direction of the straight pipe jacking needs to be strictly controlled in the jacking process, the technical requirements on pipe jacking construction are higher, and more research and development are needed particularly in the aspect of jacking control technology of large-diameter long-distance straight pipe jacking. According to the prior related technical documents, the existing jacking control technology research on large-diameter long-distance linear jacking pipes is very few, most of the existing jacking control technology research is about curved jacking pipes or jacking pipe technology with short jacking distance, and the existing technology control has the advantages of long construction period, high cost and complex operation and is not beneficial to the construction process of the whole project.

In view of the above-mentioned drawbacks, the inventors of the present invention have finally obtained the present invention through a long period of research and practice.

Disclosure of Invention

In order to solve the technical defects, the technical scheme adopted by the invention is to provide a large-diameter long-distance linear jacking pipe jacking method, which comprises the following steps:

s1, surveying the depth and soil layer properties of the jacking area;

s2, soil body reinforcement of the starting well and the receiving well opening is carried out;

s3, arranging a pumping well on the ground;

s4, installing pipe jacking equipment;

s5, setting a laser theodolite;

s6, before exiting the tunnel, measuring the axis position of the pipe jacking machine by using the laser theodolite, and ensuring that the jacking direction is carried out along the jacking design axis;

s7, opening the sealing door and the pipe jacking equipment to enable the pipe jacking machine to start cutting soil to exit;

and S8, before the push bench enters the hole, measuring the axial position of the push bench again to ensure that the deviation is within the allowable range and the push bench enters the hole smoothly.

Preferably, a resistance reducing mode of jacking and grouting is adopted, a plurality of annular grouting ports are arranged on the pipe wall of the tool pipe, and resistance reducing slurry is injected to the outer side of the tool pipe through the grouting ports by arranging the grouting pipes.

Preferably, the laser theodolite is arranged on the ground of the starting well, a plurality of laser measuring points are arranged in the pipeline of the tool pipe at intervals, the light plate is positioned at the machine head, and laser lines emitted by the laser theodolite penetrate through the laser measuring points and the center of the light plate to be consistent with the jacking axis.

Preferably, the machine head is provided with a deviation rectifying jack; during jacking of the pipe jacking machine, the axis track of the laser theodolite is monitored in real time, and when the axis curve of the laser theodolite and the actual jacking curve of the pipe jacking machine deviate by more than 5mm, the deviation is corrected through the deviation correcting jack.

Preferably, pressure sensors are arranged around the grouting pipe and the push bench, and when the push bench pushes in, the pressure value of the pressure sensors is monitored in real time, the offset direction of the push bench is predicted according to the pressure value of the pressure sensors, and correction preparation is made in advance.

Preferably, the ground is provided with a master control system, and the master control system is connected with the deviation rectifying jack, the laser theodolite, the pressure sensor and the pipe jacking machine.

Preferably, a grouting central station is arranged on the ground, and the grouting central station is connected with the grouting port through the grouting pipe and injects the anti-drag slurry to the outer side of the tool pipe.

Preferably, a relay room and a grouting replenishing station are arranged in the pipeline at an interval of 500m, and the grouting replenishing station and the grouting main station are connected through the grouting pipe.

Preferably, in step S2, driving high-pressure jet grouting piles around the starting well, and lining 0.8m thick lining walls around the starting well; the receiving well is reinforced by adopting a high-pressure jet grouting pile, and the reinforcing strength of the soil body at the hole opening of the receiving well is higher than that of the soil body at the hole opening of the starting well.

Preferably, in step S2, a grouting hole is preset at the high-pressure jet grouting pile in the hole entering and exiting directions, a grouting pipe for reinforcing a soil body is installed at the grouting hole, the soil body at the hole opening is reinforced by grouting, a steel plate is used for sealing the door, cement paste is used as a grouting material, the grouting strength is less than 2MPa, and a sealant material is used for filling a gap between the grouting pipe and the grouting hole.

Compared with the prior art, the invention has the beneficial effects that: the reinforcement of the soil body at the hole opening can prevent the jacking deviation when entering or exiting the hole, protect the safe proceeding of the engineering and prevent the pipe wall from cracking. The sealing performance of the device is guaranteed by adopting the combined sealing relay, and meanwhile, the sealing device can be adjusted, combined and damaged sealing rings can be replaced. A plurality of grouting stations are arranged, and the defect of insufficient grouting of a long-distance jacking pipe is overcome. A pressure sensor is arranged around the pipe wall of the tool, and the direction in which the jacking pipe is likely to deviate is predicted by monitoring the pressure of the pipe wall, so that the nose is adjusted in time in the opposite direction to prevent possible deviation. The device adopted by the technical scheme is simple to operate and low in cost, the tight connection between each device and the master control system enables the whole jacking process of the jacking pipe to be coordinated, the working efficiency is improved, and the device has good economic benefits.

Drawings

FIG. 1 is a flow chart of the large-diameter long-distance linear jacking method;

FIG. 2 is a schematic connection diagram of the main structure of the push bench;

FIG. 3 is a schematic illustration of reinforcement of the work well;

fig. 4 is a schematic view of the center of the light panel of the top-hat head.

The figures in the drawings represent:

1-originating well; 2-a receiving well; 3-a pipe jacking machine; 4-laser theodolite; 5-laser measuring points; 6-a light panel; 7-a tripod; 8-a rail system; 9-back wall; 10-a base plate; 11-grouting main station; 12-grouting pipes; 13-grouting supplementary station; 14-grouting port; 15-deviation rectifying jacks; 16-a pressure sensor; 17-an inter-relay; 18-the overall control system; 19-dewatering well; 20-high pressure jet grouting pile; 21-main jack; 61-center of light panel.

Detailed Description

The above and further features and advantages of the present invention are described in more detail below with reference to the accompanying drawings.

Example one

As shown in fig. 1, fig. 1 is a flow chart of the large-diameter long-distance linear jacking method; the invention relates to a large-diameter long-distance linear jacking pipe jacking method, which comprises the following steps:

s1, preparing construction, and surveying the depth and soil layer properties of the jacking area;

s2, reinforcing the hole soil of the starting well 1 and the receiving well 2;

s3, arranging water pumping wells on the ground, uniformly arranging the water pumping wells along the periphery of the ground, and reducing the underground water level to 2.5m below the working well by using a water pumping pump;

s4, installing pipe jacking equipment;

s5, arranging a laser theodolite 4, wherein the laser theodolite 4 is fixed on the ground of the starting well 1 by adopting a steel pipe, arranging laser measuring points 5 at intervals in a tool pipe pipeline and fixed on the upper part of a push bench 3, a light plate 6 is positioned at a head, and a light plate center 61 of the light plate 6 is positioned right above the head center, so that a laser line emitted by the laser theodolite 4 penetrates through each laser measuring point 5 and the light plate center 61 of the light plate 6 and is consistent with a jacking axis;

s6, before exiting the tunnel, measuring the axis position of the push bench 3 by using the laser theodolite 4, and ensuring that the jacking direction is carried out along the jacking design axis;

the back seat of working well is set up and is measured the frame, measure the base and introduce the underground by ground, avoid the error that the deformation of working well arouses, will laser theodolite 4 places leveling back on it, makes the laser of laser theodolite 4 transmission jets out along the direction level of advancing in the top, hits the aircraft nose on the worn-out fur 6, read out through the telescope the deviation of aircraft nose. Every 0.5 m.

And tracking and measuring by the laser theodolite 4 in the whole range of 300m before the push pipe is pushed. And (3) tracking and measuring the jacking direction of the pipeline by adopting a laser guide and laser measuring point 5 method for setting stations in the pipeline after jacking for 300m, wherein the measuring time of the method is carried out after the jacking of the pipe joint is stopped. The measurement contents comprise a pipeline transverse deviation value, an elevation deviation value, a horizontal diameter, a vertical diameter and ovality.

S7, opening a sealing door and the pipe jacking equipment to enable the pipe jacking machine 3 to start cutting soil to exit;

and S8, measuring the axis position of the push bench 3 again before the push bench 3 enters the hole, ensuring that the deviation is within an allowable range, installing a receiving guide rail on the premise that the push bench 3 realizes linear jacking, and ensuring that the push bench 3 smoothly enters the hole.

As shown in fig. 2 and 4, fig. 2 is a connection schematic diagram of the main structure of the push bench; FIG. 4 is a schematic view of the center of the optical plate of the push bench head; in step S5, the laser theodolite 4 is placed on the support plate, the support plate is welded in the working well through a tripod 7, the tripod 7 is the measuring base, the laser theodolite 4 can move on the support plate to change the position, and the axis sent by the laser theodolite passes through each measuring point center and the jacking direction coincidence.

The ground is provided with a master control system 18 and a grouting central station; an intermediate station 17 and a grouting supplement station 13 are arranged in the pipeline at an interval of 500m, and the grouting supplement station 13 is connected with the grouting main station 11 through a grouting pipe 12; and pressure sensors 16 are arranged around the grouting pipe 12 and the push bench 3, the machine head is provided with a deviation rectifying jack 15, and the pressure sensors 16, the deviation rectifying jack 15 and the master control system 18 are connected.

The invention adopts a mode of carrying out grouting drag reduction while jacking, four grouting ports 14 are arranged at the pipe wall of the tool pipe, namely an upper grouting port, a lower grouting port, a left grouting port and a right grouting port, the grouting pipe 12 is arranged to inject drag reduction mud into the grouting ports 14, and the drag reduction mud is mixed liquid of bentonite, soda and the like.

During 3 jacking of push bench, through total control system 18 acquire pressure sensor 16's numerical value with the axis orbit of laser theodolite 4 works as the axis curve of laser theodolite 4 with when the actual jacking curve skew of push bench 3 surpasses 5mm, start at once rectify jack 15 and slowly rectify a deviation, whole control 3 axes of push bench adopt the small-angle to rectify a deviation for the straight line when rectifying a deviation, the angle of rectifying a deviation at every turn is less than 0.4, and the process of rectifying a deviation should remain steady. Meanwhile, the direction of the possible deviation of the push bench 3 can be predicted according to the pressure value around the push bench 3 monitored by the pressure sensor 16, and correction preparation is made in advance.

The tube push bench rectifying system that rectifying jack 15 formed is located the aircraft nose position, generally is provided with four hydro-cylinders of rectifying, during rectifying, through controlling each the flexible of hydro-cylinder of rectifying, make the resultant force of the hydro-cylinder piston rod of rectifying promote the rectifying section to rotate certain angle towards the opposite direction that the fuselage section is inclined, at this moment rectify the annular overexcavation clearance between section and the fuselage section and change, the jacking resistance of aircraft nose just loses original balance, under the combined action of rear jacking force and soil pressure, force fuselage section and follow-up pipeline to the direction of rectifying the section deflection and move forward.

The deviation of the pipe position is found to be about 5mm in the jacking process, and the correction is needed. The correction should be performed slowly to gradually reset the pipe joint without hard adjustment. The correction method adopts a nose self-correcting method: the state of the machine head is controlled (downwards, upwards, leftwards and rightwards), the method is good in deviation rectifying method, the deviation rectifying amplitude is 5mm as a unit each time, when the machine head is jacked for 1m, if the deviation rectifying trend measured by the inclinometer of the machine head and the laser theodolite 4 is not reduced, the deviation rectifying strength is increased (8 mm is used as a unit), if the deviation rectifying strength measured by the inclinometer of the machine head and the laser theodolite is stable or reduced, the deviation rectifying strength is kept, jacking is continued, and when the deviation trends are opposite, the deviation rectifying strength is required to be gradually reduced.

The jacking force of the jack is obtained to change in size, so that adjustment can be timely made according to the jacking force, the relay 17 is started, and insufficient jacking force in a long distance is prevented.

As shown in fig. 3, fig. 3 is a schematic reinforcement view of the working well; in step S2, the reinforcement of the opening soil of the originating well 1 and the receiving well 2 includes:

s21, driving high-pressure jet grouting piles 20 around the starting well 1, and lining a lining wall with the thickness of 0.8m on the periphery;

and reinforcing the entrance and exit of the hole by adopting double rows of the high-pressure jet grouting piles 20 with the diameter of 0.6m, wherein the pile spacing is 0.5m, and the pile length is 15 m. When the tunnel portal is broken, horizontal hole probing construction is carried out, and if quicksand and running water are found, grouting is carried out in time (double glass: cement is 1: 1)

And constructing the high-pressure jet grouting pile 20 after the open caisson is sunk, wherein the curing agent of the high-pressure jet grouting pile 20 is 42.5R cement.

Rechecking each control point before setting out, setting out according to a design drawing, and accurately determining the position of a technological test pile; measuring the elevation of a construction platform, and lofting a pile position; the pile position of the high-pressure jet grouting pile 20 is positioned on site by adopting bamboo chips or laths, a lime point is scattered to be marked, a drilling machine needs to accurately hole, and the hole aligning error is not more than 50 mm.

And (3) carrying out jet grouting to ensure that a re-jet measure is taken for a part needing to enlarge a reinforcing range or improve the strength, and the height of the actual pile top is 0.3-0.5 m higher than the designed elevation.

S22, presetting grouting holes at the positions of the high-pressure jet grouting piles 20 in the hole entering and exiting directions, installing grouting pipes for reinforcing soil at the grouting holes, adopting grouting reinforcement for the soil at the hole openings, adopting steel plates for sealing doors, adopting cement slurry as grouting materials, enabling the grouting strength to be less than 2MPa, reducing the resistance of a machine head passing through a reinforcement area, enabling the push bench 3 to smoothly enter and exit the holes, and filling gaps between the grouting pipes and the grouting holes with sealant materials.

S23, the receiving well 2 is reinforced by the high-pressure jet grouting pile 20, the reinforcing strength of the soil body at the hole opening is higher than that of the starting well 1, and the soil body is collapsed due to the fact that a head knocking phenomenon is prone to occurring when the push bench 3 enters the hole.

The water stop measures of rubber rings and pressure plates are adopted at the hole inlet and the hole outlet, and a steel ring is embedded in the working well, and a hole reinforcing and hole connecting structure is adopted.

In order to prevent the muddy water loss of the inlet and outlet holes of the jacking pipe and cause the damage of the engineering, a water stopping device is arranged at the inlet and outlet holes. The adopted hole water-stopping device is generally of a rubber structure, and particularly, in order to enable the water-stopping device entering and exiting the hole to play a good water-stopping role, the requirement of being coaxial with a designed axis must be met when the device is installed. The sealing flange of the rubber structure can be uniformly compressed all around, and the water stopping effect is achieved.

And after the pipe jacking is finished for 48 hours, the pipeline is basically stable in line shape, and at the moment, cement slurry can be injected from the hole to the outside, so that the effects of reinforcing the soil body around the pipe and stopping water are achieved. And then sealing gaps between the opening and the periphery of the pipeline and connecting the pipeline and the well wall by using bricks and cement mortar.

In order to firmly embed the embedded steel ring on the wall of the opening well, a plurality of forked anchor rods are welded on one surface of the embedded steel ring, which is contacted with concrete, so that the underground diaphragm wall opening is conveniently chiseled off when a pipe jacking machine goes out of the opening, the upper structure of the underground diaphragm wall is stabilized, and other parts are not influenced by chiseling off the opening; a plurality of bolts are welded on the mounting steel ring for mounting the rubber ring and the pressing plate, and the pressing plate is used for fixing the position of the rubber water stop ring and preventing the rubber water stop ring from deforming and shifting. The outer rubber water stop ring is meshed with the inner annular reinforced concrete ring to form flexible and rigid lap joints, the rubber water stop ring is arranged at the portal, and the rubber water stop ring can better seal the pipe joint and the upper structure to prevent water seepage due to the elastic expansion characteristic of the rubber water stop ring.

The working well is reinforced by adopting a high-pressure jet grouting pile 20 with the radius of 10cm, and the proportion of cement is not less than 30%; 4 dewatering wells 19 are arranged around the working well, and the underground water level is reduced to 2m below the working well before the push bench 3 works.

In step S4, the method specifically includes:

s41 sets up the back wall 9 of H shaped steel as pipe push bench 3 on the rear high pressure jet grouting pile 20 of jacking direction, back wall 9 should be perpendicular to well bottom, in order to prevent the influence of back wall 9 skew to ejector pin jacking direction hangs a plumb bob line on ground and measures back wall 9' S angle makes back wall 9 skew is at the certain limit, and uses laser theodolite 4 and line weigh down the cooperation, make back wall 9 plane is perpendicular with the jacking axis, back wall 9 pastes closely with the well wall of a well. After the back wall 9 is installed, a small gap between the back wall 9 and the wall of the working well is filled and compacted by using mortar;

s42, guide rail systems 8 are arranged in the starting well 1 and the receiving well 2, each guide rail system 8 comprises a starting guide rail positioned in the starting well 1 and a receiving guide rail positioned in the receiving well 2, a steel cross beam at the bottom of each guide rail system 8 is arranged on the bottom plate 10 of the working well and welded with an embedded part on the bottom plate 10 of the working well, so that the guide rail systems 8 are integrally and firmly integrated without displacement in use, the lower parts of the guide rails of the guide rail systems 8 are made of square steel pipes made of section steel, the square steel pipes are fixedly connected with the guide rails and the steel cross beams, and the guide rail systems 8 are arranged 30cm away from a hole door when being installed; in the present embodiment, the working well is the originating well 1 or the receiving well 2;

and S43, main jacking equipment is arranged in the starting well 1, and the main jacking equipment comprises a jack frame, a main jack 21 and jacking iron of an oil pressure pump station. The oil pressure pump station top iron does main jack 21 provides power, main jack 21 generally includes a plurality of jacks, the jack frame is used for fixing a plurality of the jack.

Preferably, each of the tube push bench 3 is equipped with 18 jacks, the jacking force of each jack is 200T, the stroke of each jack is 3.5m, the length of each tube joint is 2.5m, and the maximum extending stroke of each jack is about 10cm smaller than that of each oil cylinder.

In the jacking process of the pipe jacking machine 3, some emergency situations and uncontrollable factors are inevitably encountered, and in order to ensure the safety problem of high-voltage power supply in a pipe jacking pipeline, an emergency lighting system is arranged at a machine head and a relay 17 so as to ensure the safe evacuation and approach maintenance of workers when power is suddenly cut off; because the air circulation in the pipeline is poor, the oxygen content can be reduced gradually, and some poisonous and harmful gases can also be produced in succession, thereby influencing the safety and health of operating personnel and causing the engineering construction to be influenced. Therefore, in the process of pipeline construction, the air flow quantity in the pipeline is increased, and the ventilation pipe and the air detector are installed, so that the air supply speed is higher than 0.2m/s, and the quality of the air in the pipeline is ensured to reach the safety index; the pipe jacking engineering has a high requirement on the authenticity of geological and soil exploration data, but the geological exploration data are representative data of the soil texture of the stratum and can not be absolutely the same as the actual geological condition, and errors always exist, so that a treatment measure under special geology and complex conditions needs to be made, and the type of pipe jacking equipment is selected according to different soil textures.

When the pipe jacking machine 3 leaks in and out of the hole, the following emergency measures are adopted:

emergency water pumping is carried out in a working well;

the bamboo plywood is placed outside the opening, and then the bamboo plywood is plugged by the woven bag filled with soil and cement. Then hoisting the steel plate to be plugged by a crane;

and (4) supporting the gap between the frame and the pipe joint by using square timber in the working well (withdrawing the operator when the control cannot be performed). And in the working well, bagged cement is used for building a retaining wall, and local leakage exists in the building process. Plugging the starting hole;

and grouting and reinforcing the ground surface downwards.

The foregoing is merely a preferred embodiment of the invention, which is intended to be illustrative and not limiting. It will be understood by those skilled in the art that various changes, modifications and equivalents may be made therein without departing from the spirit and scope of the invention as defined in the appended claims.