Splicing type floor mat paving structure and paving method

文档序号:1426244 发布日期:2020-03-17 浏览:21次 中文

阅读说明:本技术 一种拼接式的地胶垫铺贴结构及铺贴方法 (Splicing type floor mat paving structure and paving method ) 是由 杨震 张国强 陈泓昕 杜菊如 杜湘竹 赵玉良 蒋尹华 于 2019-11-19 设计创作,主要内容包括:本发明提供了一种拼接式的地胶垫铺贴结构,其包括土建地面,土建地面上设置有第一水泥砂浆层和第二水泥砂浆层,第一水泥砂浆层的铺设高度低于第二水泥砂浆层的铺设高度,第一水泥砂浆层和第二水泥砂浆层之间设置有通长木条,第一水泥砂浆层的表面固定铺设有石材层,第二水泥砂浆层的表面固定铺设有自流平层,自流平层的表面固定铺设有地胶层,通长木条沿着其长度方向抵住第一水泥砂浆层和石材层的挤压,第一水泥砂浆层和石材层的高度和等于第二水泥砂浆层、自流平层和地胶层的高度和。本发明还提供了一种铺贴方法。本发明相较于现有技术可以有效地解决石材和地胶垫拼缝处的变形问题,提高地面的使用寿命。(The invention provides a splicing type floor mat paving structure which comprises a civil engineering ground, wherein a first cement mortar layer and a second cement mortar layer are arranged on the civil engineering ground, the paving height of the first cement mortar layer is lower than that of the second cement mortar layer, a through long wood strip is arranged between the first cement mortar layer and the second cement mortar layer, a stone layer is fixedly paved on the surface of the first cement mortar layer, a self-leveling layer is fixedly paved on the surface of the second cement mortar layer, a floor glue layer is fixedly paved on the surface of the self-leveling layer, the through long wood strip abuts against the first cement mortar layer and the stone layer to be extruded along the length direction of the through long wood strip, and the height sum of the first cement mortar layer and the stone layer is equal to the height sum of the second cement mortar layer, the self-leveling layer and the floor glue layer. The invention also provides a paving method. Compared with the prior art, the invention can effectively solve the deformation problem of the joint between the stone and the ground rubber pad and prolong the service life of the ground.)

1. The utility model provides a ground cushion of concatenation formula spreads pastes structure, a serial communication port, including civil engineering ground (1), be provided with first cement mortar layer (11) and second cement mortar layer (12) on civil engineering ground (1), the height of laying of first cement mortar layer (11) is less than the height of laying of second cement mortar layer (12), first cement mortar layer (11) with be provided with logical long stuff (13) between second cement mortar layer (12), the edge of second cement mortar layer (12) is provided with to logical long breach (121) that second cement mortar layer (12) inside extends, logical long stuff (13) fixed plug in logical long breach (121), stone material layer (14) have been laid to the fixed surface of first cement mortar layer (11), the fixed surface of second cement mortar layer (12) is laid and is flowed flat bed (15), the surface fixing of flowing flat layer (15) certainly has laid adhesive tape layer (16), logical long stuff (13) support along its length direction first cement mortar layer (11) with the extrusion of stone material layer (14), first cement mortar layer (11) with the height sum of stone material layer (14) equals second cement mortar layer (12) from the adhesive tape layer (15) with the height sum of adhesive tape layer (16).

2. The splicing type floor mat paving structure according to claim 1, wherein a groove (17) is further formed in the civil engineering ground (1), a wood wedge strip (171) is filled in the groove (17), and the through long wood strip (13) is fixedly connected to the wood wedge strip (171) through a plurality of first screws (131).

3. The structure of claim 2, wherein the width of the wood wedge strip (171) is smaller than the width of the through-length wood strip (13), and the length of the wood wedge strip (171) is greater than the length of the through-length wood strip (13).

4. A spliced type flooring mat application structure as claimed in claim 3, wherein the width of the wood wedge strip (171) is 1/2 times the width of the through-length wood strip (13), and the length of the wood wedge strip (171) is 2 times the length of the through-length wood strip (13).

5. The splicing type floor mat paving structure according to claim 1, characterized in that a partition plate (18) is further arranged between the first cement mortar layer (11) and the second cement mortar layer (12), the bottom end of the partition plate (18) is fixedly connected with the side surface of the through wood strip (13) through a second screw (181), and the top end of the partition plate (18) extends to the position between the stone layer (14) and the floor mat (16).

6. The splicing type floor mat paving structure as claimed in claim 5, wherein the top end of the partition board (18) forms an L-shaped bending part (182) which presses the floor mat (16).

7. The splicing type floor mat paving structure as claimed in claim 1, 5 or 6, characterized in that a doorsill layer (19) is further arranged between the stone layer (14) and the floor mat layer (16).

8. The splicing type floor mat paving structure as claimed in claim 1, wherein the floor mat layer (16) is a PVC coil.

9. A spliced type floor mat paving structure as claimed in claim 1, characterized in that a cement paste layer (141) is further provided between the first cement mortar layer (11) and the stone layer (14).

10. A paving method of a splicing type ground rubber mat paving structure is characterized by comprising the following steps:

1) base layer treatment: the civil engineering ground (1) is ground by a grinding machine, and dust is cleaned by a broom and a dust collector; the surface of the base layer cannot have defects of honeycombs, holes and gaps, and the surface is clean and flat without sand rise, hollowing and cracks;

2) paving a first cement mortar layer (11) and a second cement mortar layer (12) which are high and low on the civil engineering ground (1), and embedding a through-length batten (13) between the first cement mortar layer (11) and the second cement mortar layer (12);

3) roll-coating self-leveling interface agent: adding water according to the ratio of 1: 1, uniformly rolling and coating on the second cement mortar layer (12), and performing next construction after the surface of the base coat is air-dried, wherein no obvious liquid is accumulated on the surface of the base coat;

4) self-leveling construction: pouring the self-leveling powder into a container according to the proportion of adding 6-6.5L of water into 25KG powder, and stirring while pouring to ensure that the self-leveling powder is uniformly stirred; pouring the self-leveling slurry uniformly stirred onto the second cement mortar layer (12), performing self-leveling construction by using a professional rake, and draining air bubbles in the self-leveling slurry by using an exhaust rolling brush; after the construction is finished, airing; people are prohibited from walking or passing objects within 24 hours.

5) Polishing and grinding the self-leveling layer (15) by using a polisher and special abrasive paper to ensure that the base layer reaches the required flatness;

6) paving the ground adhesive: cleaning the ground, placing the plastic mat on the site for pre-typesetting, keeping arrows of the ground adhesive consistent when the plastic mat is laid and pasted, and splicing and cutting according to the terrain and the design scheme;

7) and (3) scraping and pasting construction: sequentially turning up the ground adhesive, sequentially and uniformly scraping the ground adhesive on the ground by using adhesive water and a tooth scraping tool, and pasting the ground adhesive after drying the ground adhesive; slightly pushing and releasing the paste in sequence, discharging air at the bottom of the glue, and sequentially rolling by using an iron press roller of 30KG or more;

8) a partition plate (18) is inserted between the first cement mortar layer (11) and the second cement mortar layer (12), and the bottom of the partition plate (18) is fixedly connected with the side surface of the through long batten (13) through a second screw (181);

9) paving a stone layer (14) on the first cement mortar layer (11);

10) seam treatment: after the floor adhesive layer (16) is paved and attached, cleaning redundant glue in time, waiting for 12 hours, cutting a standard straight seam with the length of 3mm at the joint by using a slotting machine after the glue of the floor adhesive layer (16) is dried and hardened, and leading out and bending the top end of the partition plate (18) to form an L-shaped bending part (182) for pressing the floor adhesive layer (16);

11) and after construction, the ground is cleaned, and finished product protection is well performed.

Technical Field

The invention relates to a floor mat paving structure, in particular to a splicing type floor mat paving structure and a paving method.

Background

The floor rubber pad is another method of PVC floor, the main component is PVC material, the PVC floor can be made into two kinds, one is homogeneous and transparent, and the other is composite, namely, the uppermost layer is pure PVC transparent layer, and the lower layer is added with printing layer and foaming layer. The PVC floor mat is widely used in various fields of homes and businesses, such as indoor homes, hospitals, schools, office buildings, factories, public places, supermarkets, businesses, stadiums, etc., due to its rich colors and various colors.

In a plurality of exhibition halls on the ground of a museum with the theme of children at present, splicing construction of ground rubber mats and stone ground can be met, and the whole exhibition hall is fresh, popular and creative due to the fact that the ground rubber mats with different colors are matched with different stones for paving. However, in the splicing construction of the floor slab rubber and the stone, because the weight of one side of the stone is obviously greater than that of the other side of the floor slab rubber, the stone is easily extruded on the ground slab rubber side in the treading process of a human body, so that the deformation problem of the splicing seam between the stone and the floor slab rubber is easily caused, and the service life of the whole floor is influenced in time.

Disclosure of Invention

In view of the above, the invention provides a splicing type floor mat paving structure and a paving method, which mainly adopt a mode of additionally arranging a through long batten at the bottom of a floor mat to resist the extrusion of a stone side, and because the batten has the characteristic of elasticity, the extrusion force can be reduced or even counteracted by means of the principle of a reaction force, thereby protecting a joint, solving the problem of deformation of the joint of the stone and the floor mat, and prolonging the service life of the ground.

Therefore, in one aspect, the invention provides a spliced type floor mat paving structure, which comprises a civil engineering ground, wherein a first cement mortar layer and a second cement mortar layer are arranged on the civil engineering ground, the paving height of the first cement mortar layer is lower than that of the second cement mortar layer, a through long wood strip is arranged between the first cement mortar layer and the second cement mortar layer, the edge of the second cement mortar layer is provided with a through long notch extending towards the inside of the second cement mortar layer, the through long wood strip is fixedly plugged in the through long notch, a stone material layer is fixedly paved on the surface of the first cement mortar layer, a self-leveling layer is fixedly paved on the surface of the second cement mortar layer, a floor glue layer is fixedly paved on the surface of the self-leveling layer, the through long wood strip is propped against the extrusion of the first cement mortar layer and the stone material layer along the length direction of the through long wood strip, the height sum of the first cement mortar layer and the stone material layer is equal to that of the second cement mortar layer, The height of the self-leveling layer is equal to that of the floor glue layer.

Furthermore, the civil engineering ground is also provided with a groove, a wood wedge strip is filled in the groove, and the through long wood strip is fixedly connected to the wood wedge strip through a plurality of first screws.

Further, the width of the wood wedge strip is smaller than that of the full-length wood strip, and the length of the wood wedge strip is larger than that of the full-length wood strip.

Further, the width of the wood wedge strip is 1/2 of the width of the through-length wood strip, and the length of the wood wedge strip is 2 times of the length of the through-length wood strip.

Further, still be provided with the baffle between above-mentioned first cement mortar layer and the second cement mortar layer, the side of second screw fixed connection logical long stuff is passed through to the bottom of baffle, and the top of baffle extends to between stone material layer and the glue film.

Furthermore, the top end of the clapboard forms an L-shaped bending part which presses the floor adhesive layer.

Further, a doorsill stone layer is arranged between the stone layer and the floor adhesive layer.

Further, the floor glue layer is a PVC coiled material.

Further, a cement paste layer is arranged between the first cement mortar layer and the stone layer.

On the other hand, the invention provides a paving method of a splicing type ground rubber mat paving structure, which comprises the following steps:

1) base layer treatment: grinding the ground of the civil engineering ground by using a grinding machine, and cleaning dust by using a broom and a dust collector; the surface of the base layer cannot have defects of honeycombs, holes and gaps, and the surface is clean and flat without sand rise, hollowing and cracks;

2) paving a first cement mortar layer and a second cement mortar layer which are high and low on the civil engineering ground, and embedding through-length battens between the first cement mortar layer and the second cement mortar layer;

3) roll-coating self-leveling interface agent: according to the following steps: 1, uniformly rolling and coating on the second cement mortar layer without obvious liquid accumulation with the ground, and performing next construction after the surface of the base coat is air-dried;

4) self-leveling construction: pouring the self-leveling powder into a container according to the proportion of adding 6-6.5L of water into 25KG powder, and stirring while pouring to ensure that the self-leveling powder is uniformly stirred; pouring the self-leveling slurry uniformly stirred onto a second cement mortar layer, performing self-leveling construction by using a special rake, and draining bubbles in the self-leveling slurry by using an exhaust rolling brush; after the construction is finished, airing; people are prohibited from walking or passing objects within 24 hours.

5) Polishing and grinding the self-leveling layer by using a polisher and special abrasive paper to ensure that the base layer reaches the required flatness;

6) paving the ground adhesive: cleaning the ground, placing the plastic mat on the site for pre-typesetting, keeping arrows of the ground adhesive consistent when the plastic mat is laid and pasted, and splicing and cutting according to the terrain and the design scheme;

7) and (3) scraping and pasting construction: sequentially turning up the ground adhesive, sequentially and uniformly scraping the ground adhesive on the ground by using adhesive water and a tooth scraping tool, and pasting the ground adhesive after drying the ground adhesive; slightly pushing and releasing the paste in sequence, discharging air at the bottom of the glue, and sequentially rolling by using an iron press roller of 30KG or more;

8) a partition plate is inserted between the first cement mortar layer and the second cement mortar layer, and the bottom of the partition plate is fixedly connected with the side surface of the through long batten through a second screw;

9) paving a stone layer on the first cement mortar layer;

10) seam treatment: after the paving and sticking of the ground adhesive layer are finished, cleaning redundant glue in time, waiting for 12 hours, cutting a standard straight seam with the length of 3mm at the joint by using a slotting machine after the glue of the ground adhesive layer is dried and hardened, and leading out the top end of the partition plate and bending to form an L-shaped bending part pressed on the ground adhesive layer;

11) and after construction, the ground is cleaned, and finished product protection is well performed.

The splicing type floor mat paving structure and the paving method provided by the invention mainly adopt a mode of additionally arranging the through long battens at the bottom of the floor mat to resist the extrusion of the stone side, and the battens have the characteristic of elasticity, so that the extrusion force can be reduced or even counteracted by means of the principle of the reaction force, thereby protecting the abutted seam;

therefore, compared with the prior art, the invention can effectively solve the deformation problem of the joint between the stone and the ground rubber pad and prolong the service life of the ground.

Drawings

Various other advantages and benefits will become apparent to those of ordinary skill in the art upon reading the following detailed description of the preferred embodiments. The drawings are only for purposes of illustrating the preferred embodiments and are not to be construed as limiting the invention. Also, like reference numerals are used to refer to like parts throughout the drawings. In the drawings:

fig. 1 is a schematic structural diagram of a splicing-type floor mat paving structure according to an embodiment of the present invention;

fig. 2 is a schematic structural view of a splicing type floor mat paving structure according to another embodiment of the present invention.

Detailed Description

Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. While exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be embodied in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the disclosure to those skilled in the art.

10页详细技术资料下载
上一篇:一种医用注射器针头装配设备
下一篇:一种浮筑楼板保温隔声系统材料的施工工艺

网友询问留言

已有0条留言

还没有人留言评论。精彩留言会获得点赞!

精彩留言,会给你点赞!