阅读说明:本技术 一种构造柱上料机及构造柱的施工方法 (Constructional column feeding machine and construction method of constructional column ) 是由 李发祥 周裕霞 曾晓波 李达伟 张平华 于 2019-08-23 设计创作,主要内容包括:本发明公开了一种构造上料机及其构造柱施工方法,涉及建筑施工的技术领域,其技术方案的要点是:包括机架,机架上设置有进料斗以及出料管,所述出料管位于进料斗上方,进料斗与出料管之间设置有用于将物料提升至出料管的驱动泵。本发明解决了施工构造柱时搭设脚手架并通过人工进行浇筑效率较低的技术问题,具有提高效率的优点。(The invention discloses a construction feeding machine and a construction column construction method thereof, relating to the technical field of building construction, and the key points of the technical scheme are as follows: including the frame, be provided with feeder hopper and discharging pipe in the frame, the discharging pipe is located the feeder hopper top, is provided with the driving pump that is used for promoting the material to the discharging pipe between feeder hopper and the discharging pipe. The invention solves the technical problems of low efficiency of erecting a scaffold and pouring manually during the construction of the constructional column, and has the advantage of improving the efficiency.)

1. The utility model provides a constructional column material loading machine which characterized in that: including frame (1), be provided with feeder hopper (2) and discharging pipe (3) on frame (1), discharging pipe (3) are located feeder hopper (2) top, are provided with between feeder hopper (2) and discharging pipe (3) to be used for promoting the material to the actuating pump of discharging pipe (3).

2. A construction post feeder according to claim 1, characterised in that: the discharging pipe (3) is connected with a soft injection pipe (4).

3. A construction post feeder according to claim 2, characterised in that: the discharging pipe (3) comprises an upper pipe (30), a middle pipe (31) and a lower pipe (32), a connecting piece (5) used for connecting two adjacent pipelines is arranged between the two adjacent pipelines, and the injection pipe (4) is connected to the upper pipe (30).

4. A construction post feeder according to claim 3, characterised in that: connecting piece (5) are including connecting in well pipe (31) keep away from connector link (50) and fixed connection in connecting hook (51) that well pipe (32) one end was close to in upper tube (30), link and connect hook (51) joint.

5. A construction post feeder according to claim 1, characterised in that: the bottom of the frame (1) is provided with a roller.

6. A construction method of a constructional column is characterized in that: the method comprises the following steps: the first step is as follows: constructing a serrated racking;

the second step is that: planting bars and stirrups of the stranded constructional column;

the third step: a fixed die plate (70);

the fourth step: pouring concrete;

the fifth step: maintaining;

and a sixth step: and (5) taking down the template.

7. The construction method of a construction column according to claim 6, wherein: the fixing mode of the template is as follows: the side, far away from each other, of the template is rotatably connected with a supporting leg (73), and one end, far away from the template, of the supporting leg (73) is abutted to the ground.

8. A construction method of a construction column according to claim 7, wherein: the supporting legs (73) are used for placing a heavy object to press the supporting legs (73) towards the direction of the template.

9. The construction method of a construction column according to claim 6, wherein: concrete modes of planting bars and hooping bars of the trapped constructional column are as follows: and pouring the planted ribs on the ground or a lower-layer building, wherein the planted ribs are positioned in the serrated racking.

Technical Field

The invention relates to the technical field of building construction, in particular to a constructional column feeding machine and a constructional column construction method.

Background

The constructional column is characterized in that in order to enhance the integrity and stability of a building, a reinforced concrete constructional column is arranged in a wall body of a multi-layer brick-concrete structure building and is connected with each layer of ring beam to form a space frame capable of resisting bending and shearing, and the constructional column is an effective measure for preventing a house from collapsing.

The construction method of the existing constructional column comprises the following steps: and (4) filling the concrete stirred by the stirrer into a cement bucket, and manually building a ladder to pour the concrete into the reinforcing steel bar ring one spoon by one spoon.

Disclosure of Invention

Aiming at the defects in the prior art, the invention aims to: provided is a construction method of a constructional column, which has the advantage of improving the construction efficiency.

Above-mentioned technical purpose is realized through following technical scheme, a constructional column material loading machine, including the frame, is provided with feeder hopper and discharging pipe in the frame, the discharging pipe is located the feeder hopper top, is provided with the driving pump that is used for promoting the material to the discharging pipe between feeder hopper and the discharging pipe.

Through above-mentioned technical scheme, pour the concrete from the top through the constructional column material loading machine, can conveniently not need to set up the scaffold frame again to pouring of concrete to put the concrete on the scaffold frame, the process is simple, and convenient operation saves the process.

Furthermore, a soft injection pipe is connected to the discharge pipe.

Through above-mentioned technical scheme, can conveniently aim at the filler opening of structure post with the filler pipe through soft filler pipe, convenient operation.

Further, the discharging pipe includes top tube, well pipe and low tube, is provided with the connecting piece that is used for connecting two adjacent pipelines between two adjacent pipelines, and the injection pipe is connected on the top tube.

Through above-mentioned technical scheme, through top tube, well pipe and low tube, can conveniently be to tearing open and connecting of top tube, well pipe and low tube, can conveniently control the height of discharging pipe, and then can control the construction that highly makes its actual constructional column of using different heights of injection pipe.

Further, the connecting piece is including connecting at well connector link and the fixed connection of keeping away from low tube one end in the pipe and being close to the coupling hook of well pipe one end at the upper tube, even detain and coupling hook joint.

Through the technical scheme, the connection of the upper pipe, the middle pipe and the lower pipe can be facilitated through the connecting buckles and the connecting hooks, so that the upper pipe, the middle pipe and the lower pipe can be conveniently connected and detached, and the height can be conveniently adjusted.

Further, the bottom of the frame is provided with rollers.

Through above-mentioned technical scheme, through the setting of gyro wheel, can conveniently remove, carry equipment, in the work progress, can conveniently adjust the position of filling tube, and then the position of pouring the constructional column is pour in the adjustment.

A construction method of a constructional column comprises the following steps: constructing a serrated racking;

the second step is that: planting bars and stirrups of the stranded constructional column;

the third step: fixing the template;

the fourth step: pouring concrete;

the fifth step: maintaining;

and a sixth step: and (5) taking down the template.

Through above-mentioned technical scheme, efficiency of construction is higher, need not set up the scaffold frame, and the constructional column is more level and more smooth.

Further, the fixing mode of the template is as follows: the side of the template far away from each other is rotationally connected with a supporting leg, one end of the supporting leg far away from the template is abutted against the ground,

furthermore, a heavy object is placed on the supporting legs to press the supporting legs towards the direction of the template.

Through the technical scheme, the template can be fixed more stably.

Through the technical scheme, the supporting of the template can be facilitated through the arrangement of the supporting legs, and the template is not prone to falling.

Further, the concrete mode of planting the muscle and the stirrup of the structure post of stranded and prick is: and pouring the planted ribs on the ground or a lower-layer building, wherein the planted ribs are positioned in the serrated racking.

Through the technical scheme, concrete is injected into the embedded steel bars to form the constructional column.

In conclusion, the invention has the following technical effects:

1. the constructional column feeder is used for pouring concrete from the upper part, so that the concrete can be conveniently poured, a scaffold does not need to be erected, the concrete is placed on the scaffold, and the process is simple, convenient to operate and saved;

2. the injection pipe can be conveniently aligned to the injection port of the constructional column through the soft injection pipe, and the operation is convenient;

3. the connection of upper tube, well pipe and low tube can be conveniently gone up through setting up of connector link and coupling hook, and then can conveniently be to the connection and the dismantlement of upper tube, well pipe, low tube, and then convenient height-adjusting.

Drawings

FIG. 1 is a schematic structural view of example 1;

FIG. 2 is an enlarged view of portion A of FIG. 1;

fig. 3 is an enlarged view of a portion B in fig. 1.

Reference numerals: 1. a frame; 2. a feed hopper; 3. a discharge pipe; 30. feeding a pipe; 31. a middle tube; 32. a lower pipe; 4. an injection pipe; 5. a connecting member; 50. a connecting buckle; 500. enlarging the tube; 501. a fixing plate; 502. a rotating shaft; 503. a drive rod; 504. a drive section; 505. pulling a shaft; 506. a stationary case; 507. pulling a rod; 508. locking a ring; 509. a slide bar; 51. a connecting hook; 6. a rolling wheel; 7. a wall body; 70. fixing the template; 71. rubbing with horse teeth; 72. a reinforcement cage; 73. and (7) supporting legs.

Detailed Description