Deviation rectifying method for inclined extra-high voltage transmission iron tower in coal mine subsidence area

文档序号:1872687 发布日期:2021-11-23 浏览:21次 中文

阅读说明:本技术 一种煤矿沉陷区歪斜特高压输电铁塔纠偏方法 (Deviation rectifying method for inclined extra-high voltage transmission iron tower in coal mine subsidence area ) 是由 袁广林 李建国 刘萌 王浩 黄晨 赵子贤 舒前进 于 2021-09-23 设计创作,主要内容包括:本发明提供了一种煤矿沉陷区歪斜特高压输电铁塔纠偏方法,在上下游侧输电铁塔分别埋设过轮临锚地锚;在歪斜输电铁塔埋设临时拉线地锚;先停电,然后拆除歪斜输电铁塔两侧的相邻输电铁塔之间导线上的间隔棒;在上下游侧输电铁塔分别挂导地线放线滑车,将导线从线夹内移至滑车内,并设置过轮临锚和挂胶锚绳;在歪斜输电铁塔外角侧设置双钢丝绳拉线;在歪斜输电铁塔上下游侧的线夹前分别连接钢丝绳套,将单根导线的内拉力降低到设定值;利用绞车,通过缆绳和卡线器收紧导线,摘开线夹后串接相应长度的钢丝绳套,缓慢回松绞车,使导线松至规定长度;依次对塔脚四、塔脚一和塔脚三进行提升作业。该方法可以实现重量大、沉降不均匀输电铁塔的纠偏。(The invention provides a deviation rectifying method for a skew extra-high voltage power transmission iron tower in a coal mine subsidence area, wherein a wheel-passing anchor-facing anchor ground anchor is respectively embedded in the power transmission iron towers at the upstream side and the downstream side; burying a temporary stay anchor in the inclined power transmission iron tower; firstly, power failure occurs, and then the spacing rods on the conducting wires between the adjacent transmission towers at the two sides of the skew transmission tower are dismantled; respectively hanging a ground wire paying-off pulley on the transmission towers at the upstream and downstream sides, moving a wire from a wire clamp into the pulley, and arranging a passing wheel adjacent anchor and a rubberizing anchor rope; arranging double steel wire rope stay wires at the outer corner side of the skew power transmission iron tower; respectively connecting a steel wire rope sleeve in front of a wire clamp on the upstream side and the downstream side of the skew power transmission iron tower, and reducing the internal tension of a single wire to a set value; the wire is tightened by a winch through a cable and a wire clamping device, the wire clamp is removed, then a wire rope sleeve with a corresponding length is connected in series, and the winch is slowly loosened to loosen the wire to a specified length; and sequentially carrying out lifting operation on the tower foot four, the tower foot one and the tower foot three. The method can realize the deviation correction of the power transmission iron tower with heavy weight and uneven settlement.)

1. A skew extra-high voltage transmission tower deviation rectifying method in a coal mine subsidence area comprises a skew transmission tower (1), an upstream side transmission tower (2) and a downstream side transmission tower (3), wherein the upstream side transmission tower (2) is positioned in front of the upstream side of the skew transmission tower (1), the downstream side transmission tower (3) is positioned in front of the downstream side of the skew transmission tower (1), and the upstream side transmission tower (2), the skew transmission tower (1) and the downstream side transmission tower (3) are arranged on a same-tower double-circuit transmission line in a pairwise adjacent manner; the skew power transmission tower (1) is provided with four tower legs, wherein a first tower leg (11) and a fourth tower leg (14) are arranged on the upstream side, a second tower leg (12) and a third tower leg (13) are arranged on the downstream side, and the first tower leg (11) and the second tower leg (12) are respectively positioned in front of the fourth tower leg (14) and the third tower leg (13);

the method is characterized by comprising the following steps:

the method comprises the following steps: the power transmission iron tower (2) at the upstream side and the power transmission iron tower (3) at the downstream side are respectively embedded with a wheel adjacent anchor ground anchor;

for over-wheel adjacent anchor ground anchors, two ground anchors are arranged on each phase of lead, and one ground anchor is arranged on each ground wire and OPGW;

step two: burying a temporary stay wire ground anchor (5) in the inclined power transmission iron tower (1);

for the temporary stay wires, the temporary stay wires are respectively arranged at a cross partition surface between the upper lead cross arm and the ground wire bracket, at a cross partition surface at the middle lead cross arm and at a cross partition surface at the lower lead cross arm;

step three: firstly, power failure occurs, and then the spacing rods on the conducting wires (6) between the adjacent power transmission towers at the two sides of the skew power transmission tower (1) are dismantled;

step four: respectively hanging a ground wire paying-off pulley on an upstream side power transmission iron tower (2) and a downstream side power transmission iron tower (3), moving a wire (6) into the pulley (7) from a wire clamp, and arranging a pulley adjacent anchor and a rubberizing anchor rope (4); the upper end of the adhesive-coated anchor rope (4) penetrates through the right-angle hanging plate and then is connected with the wire clamping device (8), and the lower end of the adhesive-coated anchor rope is connected with the steel wire rope in series and then is connected with the hand-operated hoist on the adjacent anchor frame; after the hand hoist is tightened, the tail wire is sleeved at the single end of the adhesive-coated anchor rope (4) and is clamped by a plurality of cable clamps;

step five: a double-steel-wire-rope stay wire is arranged on the outer corner side of the skew power transmission iron tower (1);

step six: the front parts of wire clamps at the upstream side and the downstream side of the skew power transmission iron tower (1) are respectively connected with a steel wire rope sleeve with a certain length, and the internal tension of a single lead (6) is reduced to a set value;

step seven: the wire (6) is tightened by a winch (9) through a cable (10) and a wire clamping device (8), a wire clamp is removed and then a wire rope sleeve with a corresponding length is connected in series, and the winch (9) is slowly loosened to loosen the wire (6) to a specified length;

step eight: lifting the tower foot four (14); loosening foundation bolts at the position of a tower foot four (14), keeping the loosening state of a lead (6) at the upstream side and the downstream side of the skew power transmission iron tower (1), hanging three-phase leads at the inner angle of the downstream side of the skew power transmission iron tower (1), enabling the skew power transmission iron tower (1) to receive the internal tension of the lead at the inner angle of the downstream side, jacking the height of the tower foot four (14) by using a hydraulic jacking device, synchronously loosening the foundation bolts at the positions of a tower foot one (11) and a tower foot three (13), enabling the tower foot one (11) and the tower foot three (13) to lift together with the tower foot four (14), and adding heightening gaskets at the bottoms of the tower foot one (11) and the tower foot three (13) respectively for heightening support; after the tower foot four (14) is jacked to a preset height, heightening the preset height of the tower foot four (14) so as to improve the supporting height of the tower foot four (14);

step nine: lifting the tower foot I (11); keeping the wires (6) at the upstream side and the downstream side of the skew power transmission iron tower (1) in a fully relaxed state, enabling the three-phase wires at the inner corner side of the downstream side to be in a tightened state, then hooking the wires at the outer corner side of the downstream side of the skew power transmission iron tower (1), enabling the skew power transmission iron tower (1) to be subjected to internal tension of the wires (6) at the downstream side, jacking the height of a tower foot I (11) by using a hydraulic jacking device, in the process, enabling the height of a tower foot II (14) to be lifted along with the tower foot I (11), and then adding a heightening gasket at the bottoms of the tower foot I (11) and the tower foot II (14) respectively to heighten and support;

step ten: lifting the tower foot III (13); keeping the tightening state of the leads (6) at the inner corner side of the upstream side and the inner corner side of the downstream side of the skew power transmission iron tower (1), keeping the loosening state of the leads (6) at the outer corner side of the upstream side, enabling the skew power transmission iron tower (1) to be subjected to the internal tension of the leads (6) at the inner corner side, jacking the height of a tower foot III (13) by using a hydraulic jacking device, in the process, enabling the height of a tower foot IV (14) to be lifted along with the tower foot III (13), and then respectively adding a heightening gasket at the bottoms of the tower foot III (13) and the tower foot IV (14) for heightening and supporting;

step eleven: measuring the settlement after lifting the tower foot I (11), the tower foot II (12), the tower foot III (13) and the tower foot IV (14), selecting the tower foot with the minimum settlement as a reference height, respectively lifting the heights of the other three tower feet by using a hydraulic lifting device until the four tower feet reach the same height, then keeping the four tower feet at the same height in a mode of adding heightening gaskets at the bottoms of the corresponding tower feet, and finally screwing down foundation bolts at the tower feet to fix the tower feet.

2. The method for rectifying the deviation of the inclined extra-high voltage transmission tower in the coal mine subsidence area according to claim 1, wherein in the step one, an included angle between an anchor rope of the ground anchor and the ground is not more than 30 degrees.

3. The deviation rectifying method for the inclined extra-high voltage transmission tower in the coal mine subsidence area according to claim 1 or 2, wherein in the second step, the included angle between the temporary pull line and the ground is not more than 30 degrees.

4. The deviation rectifying method for the inclined extra-high voltage transmission tower in the coal mine subsidence area according to claim 3, wherein in the sixth step, the set value is 0.5 t.

5. The deviation rectifying method for the inclined extra-high voltage transmission tower in the coal mine subsidence area according to claim 4, wherein in the fourth step, the anchor approaching direction of the passing wheel adjacent anchor is the same as the line direction, and the included angle of the passing wheel adjacent anchor to the ground is less than 30 degrees.

6. The deviation rectifying method for the tilted extra-high voltage transmission tower in the coal mine subsidence area according to claim 5, wherein in the fourth step, the number of the cable clamps is four, and the distance between every two adjacent cable clamps is 10 cm.

Technical Field

The invention belongs to the technical field of deviation correction of transmission towers, and particularly relates to a deviation correction method for a skew extra-high voltage transmission tower in a coal mine subsidence area.

Background

At the present stage, with the wide exploitation of coal resources and the increase of exploitation depth, a large number of coal mining subsidence areas are formed in various places. Meanwhile, with the continuous development of power grid construction, the line corridor is increasingly tense. A large number of power transmission lines are inevitably constructed in a coal mining subsidence area, so that some power transmission towers are inevitably sunk and inclined in different degrees in a long-term movement process, and serious threats are caused to the safe operation of the power transmission lines after the power transmission towers are sunk and inclined.

At present, for a power transmission iron tower with small uneven settlement, small load and low voltage grade, a method of lengthening foundation bolts or adopting a hydraulic device can be adopted for deviation rectification treatment. The following problems mainly exist in the prior art: on one hand, the thickness of coal seam mining is larger and larger, so that the sinking depth of an iron tower is larger and larger, and meanwhile, the uneven settling amount is larger and larger; on the other hand, the grade of the power transmission line is higher and higher, the load is larger and larger, and the deep sinking depth and the uneven settling amount are further aggravated. Therefore, for the power transmission iron tower with larger settling volume and larger load, such as a double-loop extra-high voltage power transmission iron tower, the correction by adopting the conventional method is difficult. Therefore, a deviation rectifying method which is simple to operate, fast in speed, short in construction period and good in effect is urgently needed to be researched.

Disclosure of Invention

Aiming at the problems in the prior art, the invention provides a deviation rectifying method for a tilted extra-high voltage transmission tower in a coal mine subsidence area, which can realize the deviation rectifying operation of the transmission tower with large weight, uneven settlement and large settlement; meanwhile, the method has the advantages of simple construction, short construction period, quick response, lasting effect, high reliability and low cost.

In order to achieve the purpose, the invention provides a deviation rectifying method for a skewed extra-high voltage transmission iron tower in a coal mine subsidence area, which comprises a skewed transmission iron tower, an upstream side transmission iron tower and a downstream side transmission iron tower, wherein the upstream side transmission iron tower is positioned in front of the upstream side of the skewed transmission iron tower, the downstream side transmission iron tower is positioned in front of the downstream side of the skewed transmission iron tower, and the upstream side transmission iron tower, the skewed transmission iron tower and the downstream side transmission iron tower are arranged on a same-tower double-loop transmission line in a pairwise adjacent manner; the skew power transmission iron tower is provided with four tower legs, wherein a first tower leg and a fourth tower leg are arranged on the upstream side, a second tower leg and a third tower leg are arranged on the downstream side, and the first tower leg and the second tower leg are respectively positioned in front of the fourth tower leg and the third tower leg;

the method comprises the following steps:

the method comprises the following steps: respectively embedding a wheel-passing anchor ground anchor in an upstream power transmission iron tower and a downstream power transmission iron tower;

for over-wheel adjacent anchor ground anchors, two ground anchors are arranged on each phase of lead, and one ground anchor is arranged on each ground wire and OPGW;

step two: burying a temporary stay anchor in the inclined power transmission iron tower;

for the temporary stay wires, the temporary stay wires are respectively arranged at a cross partition surface between the upper lead cross arm and the ground wire bracket, at a cross partition surface at the middle lead cross arm and at a cross partition surface at the lower lead cross arm;

step three: firstly, power failure occurs, and then the spacing rods on the conducting wires between the adjacent transmission towers at the two sides of the skew transmission tower are dismantled;

step four: respectively hanging a ground wire paying-off pulley on an upstream side power transmission iron tower and a downstream side power transmission iron tower, moving a wire into the pulley from a wire clamp, and arranging a pulley adjacent anchor and a rubberizing anchor rope; the upper end of the adhesive hanging anchor rope penetrates through the right-angle hanging plate and then is connected with the wire clamping device, and the lower end of the adhesive hanging anchor rope is connected with the hand-operated hoist on the adjacent anchor frame after being connected with the steel wire rope in series; after the hand hoist is tightened, the tail wire is sleeved at the single end of the adhesive-coated anchor rope and is clamped by a plurality of cable clamps;

step five: arranging double steel wire rope stay wires at the outer corner side of the skew power transmission iron tower;

step six: the method comprises the following steps that steel wire rope sleeves with certain lengths are respectively connected in front of wire clamps on the upstream side and the downstream side of the skew power transmission iron tower, and the internal tension of a single wire is reduced to a set value;

step seven: the wire is tightened by a winch through a cable and a wire clamping device, the wire clamp is removed, then a wire rope sleeve with a corresponding length is connected in series, and the winch is slowly loosened to loosen the wire to a specified length;

step eight: lifting the tower foot four; loosening foundation bolts at four positions of a tower foot, keeping the loose state of the wires at the upstream side and the downstream side of the skew power transmission iron tower, hanging three-phase wires at the inner angle of the downstream side of the skew power transmission iron tower, enabling the inner angle of the skew power transmission iron tower at the downstream side to be subjected to the internal tension of the wires, jacking the height of the tower foot four by using a hydraulic jacking device, synchronously loosening the foundation bolts at the tower foot one and the tower foot three, enabling the tower foot one and the tower foot three to be lifted together by legs of the tower foot four, and respectively adding a heightening gasket at the bottoms of the tower foot one and the tower foot three for heightening and supporting; after the tower foot four is jacked to the preset height, heightening the preset height of the tower foot four to improve the supporting height of the tower foot four;

step nine: lifting the tower foot I; keeping the wires at the upstream side and the downstream side of the skew power transmission iron tower in a fully relaxed state, enabling the three-phase wires at the inner corner side of the downstream side to be in a tightened state, then hooking the outer corner side wires at the downstream side of the skew power transmission iron tower, enabling the skew power transmission iron tower to be subjected to the internal tension of the wires at the downstream side, jacking the height of the tower foot I by using a hydraulic jacking device, lifting the height of the tower foot IV along with the tower feet one by one in the process, and then adding a heightening gasket at the bottoms of the tower foot I and the tower foot IV for heightening and supporting;

step ten: lifting the tower foot III; keeping the tightening state of the wires at the inner angle side of the upstream side and the inner angle side of the downstream side of the skew power transmission iron tower, keeping the loosening state of the wires at the outer angle side of the upstream side, enabling the skew power transmission iron tower to be subjected to the internal tension of the wires at the inner angle side, jacking the height of the tower foot III by using a hydraulic jacking device, lifting the height of the tower foot IV along with the tower foot III in the process, and then adding a heightening gasket at the bottoms of the tower foot III and the tower foot IV for heightening and supporting;

step eleven: measuring the settlement of the first tower leg, the second tower leg, the third tower leg and the fourth tower leg after lifting, selecting one tower leg with the minimum settlement as a reference height, respectively lifting the heights of the other three tower legs by utilizing a hydraulic lifting device until the four tower legs reach the same height, then keeping the four tower legs at the same height in a mode of adding heightening gaskets at the bottoms of the corresponding tower legs, and finally screwing down foundation bolts at the tower legs to fix the tower legs.

Further, in order to better and firmly fix the object to be fixed on the ground, the anchor rope of the ground anchor has an included angle to the ground of not more than 30 degrees in the first step.

Further, in order to maintain the force balance state of the skewed power transmission tower in each direction and ensure that the skewed power transmission tower cannot topple over in the deviation rectifying process, in the second step, the included angle between the temporary pull line and the ground is not more than 30 degrees.

Preferably, in step six, the set value is 0.5 t.

Furthermore, in order to achieve a better fixing effect, in the fourth step, the anchor facing direction of the over-wheel adjacent anchor is the same as the line direction, and the included angle of the over-wheel adjacent anchor to the ground is smaller than 30 degrees.

Preferably, in step four, the number of the cable clamps is four, and the distance between two adjacent cable clamps is 10 cm.

Compared with the existing deviation rectifying method, the method fully utilizes the internal tension of the lead, thereby effectively reducing the pressure of each tower foot in the deviation rectifying process, and reducing the jacking pressure requirement of the hydraulic jacking device, so that the power source with low power can be used for supplying power liquid, the equipment investment cost in the deviation rectifying process can be effectively reduced, and the deviation rectifying operation of the power transmission iron tower with heavy weight and large settling volume can be conveniently and quickly realized; in addition, through the auxiliary action of the pulling force in the wire, the probability that the iron tower topples over in the deviation rectifying operation process can be favorably reduced, and therefore the safety factor in the deviation rectifying operation process is favorably improved. The method has the advantages of simple process, easy implementation, short deviation rectifying period, quick response, low input cost, capability of ensuring the safe and stable operation of the power transmission iron tower and wide practicability.

Drawings

FIG. 1 is a schematic diagram of a deviation rectifying method for a skew extra-high voltage transmission tower in a coal mine subsidence area, provided by the invention;

FIG. 2 is a plan view of the deviation rectifying method for the inclined extra-high voltage transmission iron tower in the coal mine subsidence area provided by the invention;

FIG. 3 is a schematic view of an upstream power transmission tower or a downstream power transmission tower earth wire hanging and guiding paying-off tackle in the invention;

FIG. 4 is a schematic illustration of a method of lifting a tower leg four of the present invention;

FIG. 5 is a schematic diagram of a method of lifting a first tower leg of the present invention;

fig. 6 is a schematic diagram of a lifting method of a tower leg three in the invention.

In the figure: 1. the device comprises a skew power transmission iron tower, 2, an upstream power transmission iron tower, 3, a downstream power transmission iron tower, 4, a glue hanging anchor rope, 5, a stay wire ground anchor, 6, a lead, 7, a pulley, 8, a wire clamping device, 9, a winch, 10, a cable, 11, tower feet I, 12, tower feet II, 13, tower feet III, 14 and a tower foot IV.

Detailed Description

The invention will be further explained with reference to the drawings.

As shown in fig. 1 to 6, the invention provides a skew extra-high voltage transmission tower deviation rectifying method in a coal mine subsidence area, which comprises a skew transmission tower 1, an upstream side transmission tower 2 and a downstream side transmission tower 3, wherein the upstream side transmission tower 2 is positioned in front of the upstream side of the skew transmission tower 1, the downstream side transmission tower 3 is positioned in front of the downstream side of the skew transmission tower 1, and the upstream side transmission tower 2, the skew transmission tower 1 and the downstream side transmission tower 3 are arranged on a same-tower double-loop transmission line in a pairwise adjacent manner; the skew power transmission tower 1 is provided with four tower legs, wherein a first tower leg 11 and a fourth tower leg 14 are arranged on the upstream side, a second tower leg 12 and a third tower leg 13 are arranged on the downstream side, and the first tower leg 11 and the second tower leg 12 are respectively positioned in front of the fourth tower leg 14 and the third tower leg 13;

the method comprises the following steps:

the method comprises the following steps: the power transmission iron tower 2 at the upstream side and the power transmission iron tower 3 at the downstream side are respectively embedded with over-wheel anchor-facing ground anchors;

for over-wheel adjacent anchor ground anchors, each phase of conductor is provided with two ground anchors, and each ground wire and OPGW (optical fiber composite overhead ground wire) is provided with one ground anchor;

step two: burying a temporary stay wire ground anchor 5 in the inclined power transmission iron tower 1;

for the temporary stay wires, the temporary stay wires are respectively arranged at a cross partition surface between the upper lead cross arm and the ground wire bracket, at a cross partition surface at the middle lead cross arm and at a cross partition surface at the lower lead cross arm;

step three: firstly, power failure occurs, and then the spacing rods on the conducting wires 6 between the adjacent transmission towers at two sides of the skew transmission tower 1 are dismantled;

step four: respectively hanging a ground wire paying-off pulley on an upstream side power transmission iron tower 2 and a downstream side power transmission iron tower 3, moving a wire 6 into a pulley 7 from a wire clamp, and arranging a pulley adjacent anchor and a rubberizing anchor rope 4; the upper end of the rubberizing anchor rope 4 penetrates through the right-angle hanging plate and then is connected with the wire clamping device 8, and the lower end of the rubberizing anchor rope is connected with the steel wire rope in series and then is connected with the hand-drive block on the adjacent anchor frame; after the hand hoist is tightened, the tail wire is sleeved at the single end of the adhesive-coated anchor rope 4 and is clamped by a plurality of cable clamps;

step five: arranging double steel wire rope stay wires at the outer corner side of the skew power transmission iron tower 1;

step six: the method comprises the following steps that steel wire rope sleeves with certain lengths are respectively connected in front of wire clamps on the upstream side and the downstream side of the skew power transmission iron tower 1, and the internal tension of a single lead 6 is reduced to a set value;

step seven: the wire 6 is tightened by a winch 9 through a cable 10 and a wire clamping device 8, a wire clamp is removed and then a wire rope sleeve with a corresponding length is connected in series, and the winch 9 is slowly loosened to loosen the wire 6 to a specified length;

step eight: lifting the tower foot four 14, as shown in fig. 4; loosening foundation bolts at the position of a tower foot four 14, keeping the loose state of a lead 6 at the upstream side and the downstream side of the skew power transmission iron tower 1, hanging three-phase leads (namely two-line skew power transmission iron tower 1 downstream side three-phase leads) at the downstream side inner corner of the skew power transmission iron tower 1, enabling the skew power transmission iron tower 1 to be subjected to the internal tension of the lead at the downstream side inner corner, jacking the height of the tower foot four 14 by using a hydraulic jacking device, synchronously loosening the foundation bolts at the positions of a tower foot one 11 and a tower foot three 13, enabling the tower foot one 11 and the tower foot three 13 to be lifted together with the tower foot four 14, and respectively adding heightening gaskets at the bottoms of the tower foot one 11 and the tower foot three 13 for heightening and supporting; after the tower foot four 14 is jacked to the preset height, heightening the preset height of the tower foot four 14 to improve the supporting height of the tower foot four 14;

step nine: lifting the tower foot I11, as shown in fig. 5; keeping the wires 6 at the upstream side and the downstream side of the skew power transmission iron tower 1 in a fully relaxed state, enabling the three-phase wires at the inner corner side of the downstream side to be in a tightened state, then hooking the wires at the outer corner side of the downstream side of the skew power transmission iron tower 1 (namely a first-line three-phase wire at the downstream side of the skew power transmission iron tower 1), enabling the skew power transmission iron tower 1 to receive the internal tension of the wires 6 at the downstream side, jacking the height of the tower foot I11 by using a hydraulic jacking device, in the process, enabling the height of the tower foot II 14 to be lifted along with the tower foot I11, and then respectively adding a heightening gasket at the bottoms of the tower foot I11 and the tower foot II 14 for heightening and supporting;

step ten: lifting the tower leg III 13 as shown in fig. 6; keeping the tightening state of the wires 6 at the inner angle side of the upstream side and the inner angle side of the downstream side of the skew power transmission iron tower 1, keeping the loosening state of the wires 6 at the outer angle side of the upstream side, enabling the skew power transmission iron tower 1 to be subjected to the internal tension of the wires 6 at the inner angle side, jacking the height of the tower foot III 13 by using a hydraulic jacking device, lifting the height of the tower foot IV 14 along with the tower foot III 13 in the process, and then respectively adding a heightening gasket at the bottoms of the tower foot III 13 and the tower foot IV 14 for supporting and heightening;

step eleven: measuring the settlement after lifting the first tower leg 11, the second tower leg 12, the third tower leg 13 and the fourth tower leg 14, selecting one tower leg with the smallest settlement as a reference height, respectively lifting the heights of the other three tower legs by using a hydraulic lifting device until the four tower legs reach the same height, then keeping the four tower legs at the same height in a mode of adding heightening gaskets at the bottoms of the corresponding tower legs, and finally screwing down foundation bolts at the tower legs to fix the tower legs.

In order to better fix the object to be fixed on the ground stably, the anchor line of the ground anchor has an included angle to the ground of not more than 30 degrees in the first step.

In order to maintain the force balance state of the skew power transmission iron tower in all directions and ensure that the skew power transmission iron tower cannot topple in the deviation rectifying process, in the second step, the included angle between the temporary pull line and the ground is not more than 30 degrees.

Preferably, in step six, the set value is 0.5 t.

In order to achieve a better fixing effect, in the fourth step, the anchor facing direction of the over-wheel adjacent anchor is the same as the line direction, and the included angle of the over-wheel adjacent anchor to the ground is smaller than 30 degrees.

Preferably, in step four, the number of the cable clamps is four, and the distance between two adjacent cable clamps is 10 cm.

Compared with the existing deviation rectifying method, the method fully utilizes the internal tension of the lead, thereby effectively reducing the pressure of each tower foot in the deviation rectifying process, and reducing the jacking pressure requirement of the hydraulic jacking device, so that the power source with low power can be used for supplying power liquid, the equipment investment cost in the deviation rectifying process can be effectively reduced, and the deviation rectifying operation of the power transmission iron tower with heavy weight and large settling volume can be conveniently and quickly realized; in addition, through the auxiliary action of the pulling force in the wire, the probability that the iron tower topples over in the deviation rectifying operation process can be favorably reduced, and therefore the safety factor in the deviation rectifying operation process is favorably improved. The method has the advantages of simple process, easy implementation, short deviation rectifying period, quick response, low input cost, capability of ensuring the safe and stable operation of the power transmission iron tower and wide practicability.

13页详细技术资料下载
上一篇:一种医用注射器针头装配设备
下一篇:基于砂浆快速置换的砌体结构低干预加固方法

网友询问留言

已有0条留言

还没有人留言评论。精彩留言会获得点赞!

精彩留言,会给你点赞!