阅读说明:本技术 一种可以缩短工期、用于城墙修复的夯土墙工艺 (Rammed earth wall process capable of shortening construction period and used for urban wall restoration ) 是由 黄伟 任伟 黄嘉诚 于 2021-08-16 设计创作,主要内容包括:本发明公开了一种可以缩短工期、用于城墙修复的夯土墙工艺,包括以下制备方法,(1)测量放线主体结构检查校正;(2)打孔预埋6*8膨胀螺丝,夯土墙外侧面横向上中下3组预埋膨胀螺丝,间隔60~70厘米,安装牢固;(3)焊接钢筋,采用6mm冷拔钢筋点焊连接;(4)挂网,夯土墙侧面挂0.6*0.6铁丝网,夯土墙顶面挂1.5*1.5厘米电焊网;(5)采用水泥沙灰打底,水泥砂灰塑性,仿黄土质感漆上色。采用上述技术方案制作的中药配方,用于仿土墙的施工工艺制备,采用上述施工工艺,可以有效地缩短其工艺流程,制备出的仿土墙的颜色自然均匀一致,缩短了施工时间,施工方法简单,建议推广使用。(The invention discloses a rammed earth wall process capable of shortening construction period and used for repairing city walls, which comprises the following preparation methods of (1) measuring and paying-off main body structure inspection and correction; (2) 6, perforating and embedding expansion screws 8, and embedding expansion screws 3 groups of the outer side surface of the rammed earth wall transversely up, middle and down at intervals of 60-70 cm, wherein the rammed earth wall is firmly installed; (3) welding reinforcing steel bars, and adopting 6mm cold-drawn reinforcing steel bar spot welding connection; (4) hanging a net, hanging 0.6 x 0.6 wire netting on the side surface of the rammed earth wall, and hanging 1.5 x 1.5 cm electric welding net on the top surface of the rammed earth wall; (5) and (3) priming by adopting cement sand ash, plasticizing the cement sand ash and coloring the paint imitating the loess texture. The traditional Chinese medicine formula manufactured by the technical scheme is used for the preparation of the construction process of the soil-like wall, the process flow can be effectively shortened by adopting the construction process, the color of the prepared soil-like wall is natural, uniform and consistent, the construction time is shortened, the construction method is simple, and the popularization and the use are suggested.)

1. A rammed earth wall process for repairing city wall with shortened construction period is characterized by comprising the following steps,

(1) measuring the structure of the pay-off main body, and checking and correcting;

(2) 6, perforating and embedding expansion screws 8, and embedding expansion screws 3 groups of the outer side surface of the rammed earth wall transversely up, middle and down at intervals of 60-70 cm, wherein the rammed earth wall is firmly installed;

(3) welding reinforcing steel bars, and adopting 6mm cold-drawn reinforcing steel bar spot welding connection;

(4) hanging a net, hanging 0.6 x 0.6 wire netting on the side surface of the rammed earth wall, and hanging 1.5 x 1.5 cm electric welding net on the top surface of the rammed earth wall;

(5) the cement mortar is used for priming at a ratio of 1:1, the cement mortar is plastic at a ratio of 1:1, and the paint is colored in a manner of imitating the texture of loess.

2. The rammed earth wall process capable of shortening construction period and used for repairing the urban wall is characterized in that inclined deformities on the wall body are corrected and repaired in the step (1).

3. A rammed earth wall process capable of shortening construction period and used for repairing city walls is characterized in that in the step (3), 6mm cold-drawn steel bars are transversely welded on expansion screws.

4. The rammed earth wall process capable of shortening construction period and used for repairing the urban wall is characterized in that yellow earth texture paint is sprayed in the step (5).

Technical Field

The invention relates to a construction process flow, in particular to a rammed earth wall process which can shorten the construction period and is used for repairing an urban wall.

Background

The construction process adopted by the soil-like wall often causes cracks on the soil-like outer wall, the construction process is complex, and the construction time is too long; and cracks appearing outside the soil-imitation wall are generally caused by the fact that the proportion of cement mortar is too large and the maintenance is not timely, so that the color of the whole soil-imitation wall is not uniform, the quality is poor, and the manufactured soil-imitation wall can not meet the requirements of people for the soil-imitation wall gradually.

For the above reasons, a rammed earth wall process capable of shortening the construction period and used for repairing urban walls is a technical problem to be solved urgently by those skilled in the art.

Disclosure of Invention

The invention designs a rammed earth wall process which can shorten the construction period and is used for repairing urban walls, and the rammed earth wall process comprises the following preparation methods,

1. measuring the structure of the pay-off main body, and checking and correcting;

2. 6, perforating and embedding expansion screws 8, and embedding expansion screws 3 groups of the outer side surface of the rammed earth wall transversely up, middle and down at intervals of 60-70 cm, wherein the rammed earth wall is firmly installed;

3. welding reinforcing steel bars, and adopting 6mm cold-drawn reinforcing steel bar spot welding connection;

4. hanging a net, hanging 0.6 x 0.6 wire netting on the side surface of the rammed earth wall, and hanging 1.5 x 1.5 cm electric welding net on the top surface of the rammed earth wall;

5. the cement mortar is used for priming at a ratio of 1:1, the cement mortar is plastic at a ratio of 1:1, and the paint is colored in a manner of imitating the texture of loess.

Further, the wall body in the step (1) has inclined deformity to correct and fill up.

Further, the 6mm cold-drawn steel bar in the step (3) is transversely welded on the expansion screw.

Further, yellow earth texture paint is adopted for spraying in the step (5).

By adopting the technical scheme, the process has the following technical effects that the process manufactured by the technical scheme is used for the preparation of the construction process of the soil-like wall, the process flow can be effectively shortened by adopting the construction process, the prepared soil-like wall is natural, uniform and consistent in color, natural, smooth, firm in material, short in construction time, simple in construction method and suggested to be popularized and used.

Detailed Description

The present invention will be further explained below in order to make the technical means, inventive features, objectives and effects of the present invention easy to understand.

A rammed earth wall process for repairing city wall with short construction period includes the following steps,

1. measuring the structure of the pay-off main body, and checking and correcting;

2. 6, perforating and embedding expansion screws 8, and embedding expansion screws 3 groups of the outer side surface of the rammed earth wall transversely up, middle and down at intervals of 60-70 cm, wherein the rammed earth wall is firmly installed; 3. welding reinforcing steel bars, and adopting 6mm cold-drawn reinforcing steel bar spot welding connection;

4. hanging a net, hanging 0.6 x 0.6 wire netting on the side surface of the rammed earth wall, and hanging 1.5 x 1.5 cm electric welding net on the top surface of the rammed earth wall;

5. the cement mortar is used for priming at a ratio of 1:1, the cement mortar is plastic at a ratio of 1:1, and the paint is colored in a manner of imitating the texture of loess.

As a further elaboration of the invention, in the step (1), the wall body has the inclined deformity correction and completion.

As a further elaboration of the invention, in the step (3), the 6mm cold-drawn steel bar is transversely welded on the expansion screw.

As a further illustration of the invention, the step (5) is carried out by spraying a yellow earth texture paint.

As further elaboration of the invention, the material composition, the special cement and the low-alkalinity 425-degree high-grade raw material play a role in reinforcement. The embedded expansion screws, the cold-drawn steel bar connection and the iron-hanging wire mesh play a role of a framework, the thickness of the cement mortar is 3-3.5 centimeters, the cement mortar is durable, and the color of the stone paint imitated loess is natural and attractive.

As further elaboration of the invention, the technology is used in the field of urban wall restoration, relates to a technology for ramming earth walls outside all buildings, including steel structures, and has a wide application range.

Having thus described the basic principles and principal features of the invention, it will be appreciated by those skilled in the art that the invention is not limited by the embodiments described above, which are given by way of illustration only, but that various changes and modifications may be made therein without departing from the spirit and scope of the invention as defined by the appended claims and their equivalents.

4页详细技术资料下载
上一篇:一种医用注射器针头装配设备
下一篇:门窗洞口预留超标后的处理方法

网友询问留言

已有0条留言

还没有人留言评论。精彩留言会获得点赞!

精彩留言,会给你点赞!