Lower hanging construction platform module of high-altitude large-cantilever steel roof truss and construction method

文档序号:1054400 发布日期:2020-10-13 浏览:25次 中文

阅读说明:本技术 高空大悬挑钢屋架的下挂施工平台模块及施工方法 (Lower hanging construction platform module of high-altitude large-cantilever steel roof truss and construction method ) 是由 *** 许丽华 许雷 翟宏 毛应斌 曾大泉 施华峰 李钦 陈学光 于 2020-07-14 设计创作,主要内容包括:本发明涉及一种高空大悬挑钢屋架的下挂施工平台模块及施工方法,特征在于:包括平台踏板、由桁架和多个水平连接杆连接构成的作业平台架,在作业平台架对应施工墙体的一侧上固定有多个反挂连接杆,作业平台架装有反挂连接杆一侧上和与反挂连接杆相邻的一侧上设有防护栏杆,在作业平台架底部对应反挂连接杆的一侧上设有多个下连接附杆,水平连接杆两端分别与桁架连接。优点是:在高空大悬挑钢筋混凝土坡屋面施工中,采用本挂施工平台模块,可根据工作面大小要求灵活布设,调运速度快,周转效率高,大幅度提高施工效率,且不会受建筑物周围土体承载力限制,应用极为范围广泛,其安全防护设施可根据实际施工情况灵活配置,大幅提升施工人员的人身安全。(The invention relates to a lower hanging construction platform module of a high-altitude large-cantilever steel roof truss and a construction method, which are characterized in that: including the platform footboard, connect the operation platform frame that constitutes by truss and a plurality of horizontal connecting rod, be fixed with a plurality of anti-connecting rods that hang on one side that the operation platform frame corresponds the construction wall body, the operation platform frame is equipped with on anti-connecting rod one side and is equipped with the guardrail bar on the one side adjacent with anti-connecting rod, is equipped with a plurality of lower connections and attaches the pole on one side that the operation platform frame bottom corresponds anti-connecting rod, the horizontal connecting rod both ends respectively with truss connection. The advantages are that: in the construction of the high-altitude large-cantilever reinforced concrete sloping roof, the construction platform module can be flexibly arranged according to the size requirement of a working face, is high in transferring speed and turnover efficiency, greatly improves the construction efficiency, is not limited by the bearing capacity of soil around a building, is wide in application range, and can be flexibly configured according to the actual construction condition, so that the personal safety of constructors is greatly improved.)

1. The utility model provides a hang construction platform module under steel roof truss that encorbelments greatly in high altitude which characterized in that: including the platform footboard, connect the operation platform frame that constitutes by truss and a plurality of horizontal connecting rod, be fixed with a plurality of anti-connecting rods that hang on one side that the operation platform frame corresponds the construction wall body, operation platform frame is equipped with on anti-connecting rod one side and is equipped with the guardrail bar on one side adjacent with anti-connecting rod, is equipped with a plurality of lower connections and attaches the pole on one side that the operation platform frame bottom corresponds anti-connecting rod, the horizontal connecting rod both ends respectively with truss connection.

2. The high altitude big cantilever steel roof truss hang construction platform module down according to claim 1, characterized in that: the working platform frame is equipped with on the one side of anti-hanging connecting rod and with the adjacent one side of anti-hanging connecting rod rigid coupling have a guardrail bar, horizontal connecting rod both ends respectively with truss fixed connection, the guardrail bar comprises square steel pipe welding.

3. The high altitude big cantilever steel roof truss hang construction platform module down according to claim 1, characterized in that: the anti-hanging connecting rod is formed by welding square steel pipes, a square hook portion used for being hung in a metal gutter of the high-altitude large-cantilever steel roof truss in a reverse mode is arranged at the upper end of the anti-hanging connecting rod, two inclined supporting rods are welded in the square hook portion at the upper end of the anti-hanging connecting rod, and anti-bending inclined rods are arranged at the lower portion of the anti-hanging connecting rod.

4. The high altitude big cantilever steel roof truss hang construction platform module down according to claim 1, characterized in that: the platform pedal is installed on the truss of the operation platform frame, and at least two layers of horizontal connecting rods are connected to the operation platform frame.

5. The high altitude big cantilever steel roof truss hang construction platform module down according to claim 1, characterized in that: the platform pedal is made by combining a bamboo foot plate capable of meeting the load requirement, a plurality of layers of templates and a metal strip-shaped pedal.

6. The high altitude big cantilever steel roof truss hang construction platform module down according to claim 1, characterized in that: the anti-hanging connecting rod is provided with a protective barrier connecting socket, the truss adjacent to the anti-hanging connecting rod is provided with a horizontal connecting rod connecting socket respectively, the anti-hanging connecting rod is inserted with a protective barrier through the protective barrier connecting socket, two ends of the horizontal connecting rod are connected with the horizontal connecting rod connecting socket of the truss in an inserting mode respectively, and the protective barrier is formed by welding square steel pipes.

7. The high altitude big cantilever steel roof truss hang construction platform module down according to claim 1, characterized in that: the lower connecting auxiliary rod is made of square steel pipes and is respectively welded with the operating platform frame and the wall connecting piece.

8. A construction method of a lower hanging construction platform module of a high-altitude large-cantilever steel roof truss is characterized by comprising the following steps of: the method comprises the following steps:

s1 hoisting preparation of lower hanging construction platform module

Pulling and placing the manufactured lower hanging construction platform module to be vertically below a position to be lifted, rechecking each node of the lower hanging construction platform module, and checking a hoisting machine, a hoisting tool and a hoisting point;

s2 hoisting debugging of hanging construction platform module

Putting down a hoisting rope of a winch, connecting the hoisting rope to the hoisting points of the lower hanging construction platform module, slowly hoisting, checking the stress condition of each hoisting point in detail after the hoisting rope is 50cm away from the ground, hoisting the lower hanging construction platform module to the mounting position, checking each stress point, adjusting the lower hanging construction platform module away from the mounting position, slowly falling to the ground, checking the conditions of a hoisting device and the lower hanging construction platform module, and finishing hoisting and debugging;

s3 formal hanging down construction platform module

a. Suspending the lower hanging construction platform module when the lower hanging construction platform module is lifted 50cm away from the ground, checking that the verticality and the levelness of the lower hanging construction platform module are correct, and then continuing to lift;

b. controlling the shaking in the hoisting process through two wind cables;

c. after the lower hanging construction platform module is lifted to the height of the metal gutter, the lower hanging construction platform module is reversely hung with a connecting rod and is placed in the metal gutter, the wind cable rope is utilized to cooperate with a hoisting device to horizontally move, the lower hanging construction platform module is parallelly moved to an installation position, the lower hanging construction platform module is slowly dropped, a square hook part of the reverse hanging connecting rod of the lower hanging construction platform module is placed in the metal gutter, a lower end stress point is placed on the outer side surface of a wall and a column, after the position is corrected, rigid connection and fixation are carried out through a fastener, and steel cable soft connection protection is carried out on the lower hanging construction platform module and an overhanging steel beam, at the moment, the hoisting device can be unhooked and reset, and the next lower hanging construction platform;

d. sequentially mounting the construction platform modules in a follow-up manner by the same method;

f. after the lower hanging construction platform modules are completely installed, checking square hook parts and high-strength bolt connection points of the reverse hanging connecting rods, and paving a platform pedal;

g. four steel wire safety ropes are hung on the steel roof truss cross beam by using the steel roof truss cross beam, and safety belts of construction personnel are hung on the safety ropes;

h. after the lower hanging construction platform module is installed in place, immediately installing the protective railings outside the lower hanging construction platform module, wherein the height is not less than 1.2m, and the distance between the middle protective railings is not more than 30 cm;

i. a split bolt suspender is arranged between the lower hanging construction platform module and the cantilever steel beam according to actual needs;

s4 dismantling and hanging down construction platform module

a. Marking out a working area mark, setting a warning line and forbidding pedestrians to enter;

b. firstly, dismantling the protective railing on the outer side of the lower hanging construction platform module, and timely hanging the protective railing to the ground through a hoisting device;

c. whether the hard and soft connecting parts of the lower hanging construction platform module and the wall body and the steel roof truss are separated from the stress point or not is comprehensively checked, and the lower hanging construction platform module is ensured to be hung away from the next mounting position one by one after no error and is timely mounted and fixed.

Technical Field

The invention belongs to the technical field of building construction, and particularly relates to a lower hanging construction platform module of a high-altitude large-cantilever steel roof truss and a construction method.

Background

At present, an engineering roof is a reinforced concrete slope roof, the overhanging length of a roof cornice is 4.2m, the overhanging height is 50.1m, the plate thickness is 0.12m, and a floor type scaffold support frame body needs to be erected to complete construction operations such as formwork support and pouring. The above construction operations have the following drawbacks: 1. the height of the floor type scaffold support frame body is over 50m, the danger coefficient is very large, construction drawings need to be designed additionally according to standard requirements and safety argumentation is carried out, safety guarantee measures are necessary to be comprehensive, and implementation difficulty is very large. 2. The top of the frame body needs to be overhung outwards, the maximum overhung length is about 6.2m, the distance between the rod pieces must be encrypted to ensure the overall stability of the frame body, a large amount of materials such as steel pipes and link pieces are inevitably input, the construction and use cost is greatly increased, and the danger coefficient is larger. 3. The roof cornice decoration and finishing process needs an independent operation platform, partial scaffold at the top of the support frame body needs to be dismantled and modified according to the requirements of a construction platform, the frame body occupies long time, and the construction cost greatly rises. 4. The floor type scaffold is erected and a construction platform is transformed, so that the labor consumption and the number of mechanical machine shifts are large, and the construction period is long.

Disclosure of Invention

The invention provides a lower hanging construction platform module of a high-altitude large-cantilever steel roof truss and a construction method thereof, which have the advantages of simple structure, convenience for quick installation and disassembly, flexible arrangement, high turnover efficiency and capability of greatly improving the personal safety and construction efficiency of constructors, and solve the technical problems in the known technology.

The technical scheme adopted by the invention for solving the technical problems in the prior art is as follows:

hang construction platform module under of steel roof truss that encorbelments greatly in high altitude, its characterized in that: including the platform footboard, connect the operation platform frame that constitutes by truss and a plurality of horizontal connecting rod, be fixed with a plurality of anti-connecting rods that hang on one side that the operation platform frame corresponds the construction wall body, operation platform frame is equipped with on anti-connecting rod one side and is equipped with the guardrail bar on one side adjacent with anti-connecting rod, is equipped with a plurality of lower connections and attaches the pole on one side that the operation platform frame bottom corresponds anti-connecting rod, the horizontal connecting rod both ends respectively with truss connection.

The invention can also adopt the following technical scheme:

preferably, the work platform frame is equipped with on the one side of anti-hanging connecting rod and with anti-hanging connecting rod adjacent one side on the rigid coupling have a guardrail bar, the horizontal connecting rod both ends respectively with truss fixed connection, the guardrail bar comprises square steel pipe welding.

Preferably, the reverse hanging connecting rod is formed by welding square steel pipes, a square hook part used for being reversely hung in a metal gutter of the high-altitude large-cantilever steel roof truss is arranged at the upper end of the reverse hanging connecting rod, two inclined supporting rods are welded in the square hook part at the upper end of the reverse hanging connecting rod, and an anti-bending inclined rod is arranged at the lower part of the reverse hanging connecting rod.

Preferably, the truss of the operation platform frame is provided with a platform pedal, and the operation platform frame is at least connected with two layers of horizontal connecting rods.

Preferably, the platform pedal is made by combining a bamboo foot plate capable of meeting the load requirement, a plurality of layers of templates and a metal strip-shaped pedal.

Preferably, the anti-hanging connecting rod is provided with a protective barrier connecting socket, the truss adjacent to the anti-hanging connecting rod is provided with a horizontal connecting rod connecting socket respectively, the anti-hanging connecting rod is inserted with a protective barrier through the protective barrier connecting socket, two ends of the horizontal connecting rod are connected with the horizontal connecting rod connecting socket of the truss in an inserting mode respectively, and the protective barrier is formed by welding square steel pipes.

Preferably, the lower connecting auxiliary rod is made of square steel pipes and is welded with the operating platform frame and the wall connecting piece respectively.

A construction method of a lower hanging construction platform module of a high-altitude large-cantilever steel roof truss is characterized by comprising the following steps of: the method comprises the following steps:

s1 hoisting preparation of lower hanging construction platform module

And pulling and placing the manufactured lower hanging construction platform module to the vertical lower part of the position to be lifted, rechecking each node of the lower hanging construction platform module, and checking a hoisting machine, a hoisting tool and a hoisting point.

S2 hoisting and debugging of lower hanging construction platform module

And putting down a hoisting rope of the winch, connecting the hoisting rope to the hoisting points of the lower hanging construction platform module, slowly hoisting, inspecting the stress condition of each hoisting point in detail after the hoisting rope is 50cm away from the ground, hoisting the lower hanging construction platform module to the mounting position, inspecting each stress point, adjusting the lower hanging construction platform module away from the mounting position, slowly falling to the ground, inspecting the conditions of the hoisting equipment and the lower hanging construction platform module, and finishing hoisting and debugging.

S3 formal hanging down construction platform module

a. Suspending the lower hanging construction platform module when the lower hanging construction platform module is lifted 50cm away from the ground, checking that the verticality and the levelness of the lower hanging construction platform module are correct, and then continuing lifting.

b. The shaking in the hoisting process is controlled by two wind cables.

c. After the lower hanging construction platform module is lifted to the height of the metal gutter, the lower hanging construction platform module reversely-hanging connecting rod is placed into the metal gutter, the wind cable rope is utilized to cooperate with the horizontal movement of the hoisting equipment, the lower hanging construction platform module is moved to the installation position in parallel, the lower hanging construction platform module slowly falls down, the reversely-hanging connecting rod square hook part of the lower hanging construction platform module is placed in the metal gutter, the lower end stress point is placed in a wall, the outer side surface of a column, the lower hanging construction platform module is fixed through a fastener after being corrected, and is protected by soft connection of a steel rope with the cantilever steel beam, at the moment, the hoisting equipment can be unhooked and reset, and the next lower hanging construction platform module is prepared to be hoisted.

d. And sequentially and subsequently mounting the construction platform modules in the same way.

f. And after the whole lower hanging construction platform modules are completely installed, checking the square hook parts and the high-strength bolt connection points of the reverse hanging connecting rods, and paving a platform pedal.

g. Four steel wire safety ropes are hung on the steel roof truss cross beam by using the steel roof truss cross beam, and safety belts of constructors are hung on the safety ropes.

h. After the lower hanging construction platform module is installed in place, the protective railings on the outer side of the lower hanging construction platform module are immediately installed, the height of each protective railing is not less than 1.2m, and the distance between the protective railings in the middle of each protective railing is not more than 30 cm.

i. According to actual needs, a split bolt suspender is arranged between the lower hanging construction platform module and the cantilever steel beam.

S4 dismantling and hanging down construction platform module

a. Marking out a working area mark, setting a warning line and forbidding pedestrians to enter.

b. The outer side protective railing of the lower hanging construction platform module is firstly detached, and the protective railing is timely hung to the ground through the hoisting equipment.

c. Whether the hard and soft connecting parts of the lower hanging construction platform module and the wall body and the steel roof truss are separated from the stress point or not is comprehensively checked, and the lower hanging construction platform module is ensured to be hung away from the next mounting position one by one after no error and is timely mounted and fixed.

The invention has the advantages and positive effects that: by adopting the technical scheme, the lower hanging construction platform formed by the lower hanging construction platform modules is adopted in the high-altitude large-cantilever reinforced concrete sloping roof construction, so that the construction can be flexibly arranged according to the size requirement of a working face, the dispatching speed is high, the turnover efficiency is high, the construction efficiency is greatly improved, the construction is not limited by the bearing capacity of soil around a building, the application range is wide, safety protection facilities can be flexibly configured according to the actual construction condition, and the personal safety of constructors is greatly improved. The lower hanging construction platform module is simple in structure, the manufacturing period can be greatly shortened, the manufacturing materials are common, and the cost is low. In addition, the damage rate of the module component of the lower hanging construction platform is low, and the module component can be recycled. The lower hanging construction platform module is fast to install and remove, and additionally, hoisting machinery does not need to be occupied in the process of erection and disassembly, so that convenience is provided for cross operation. Compared with the traditional floor type support frame body operation platform, the lower hanging construction platform module can be manufactured and constructed, and the construction cost can be greatly reduced.

Drawings

FIG. 1 is a front view of embodiment 1 of the present invention;

FIG. 2 is a right side view of FIG. 1;

FIG. 3 is a top view of FIG. 1;

FIG. 4 is a construction state diagram of embodiment 1 of the present invention;

FIG. 5 is a front view of embodiment 2 of the present invention;

FIG. 6 is a right side view of FIG. 5;

FIG. 7 is a top view of FIG. 5;

FIG. 8A is a structural view of a horizontal connecting rod in embodiment 2 of the present invention;

FIG. 8B is a side view of FIG. 8A;

FIG. 9 is a construction state diagram of embodiment 2 of the present invention.

In the figure: 1. a work platform frame; 1-1, a truss; 1-2, horizontal connecting rods; 2. a platform pedal; 3. reversely hanging a connecting rod; 3-1, a square hook part; 3-2, bending-resistant diagonal rods; 4. a guard rail; 5. a lower connecting attachment rod; 6. the protective railing is connected with the socket; 7. the horizontal connecting rod is connected with the socket; 8. cantilever steel beam; 9. and (4) forming a metal gutter.

In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail with reference to the following embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.

Example 1, referring to fig. 1-3,

the lower hanging construction platform module of the high-altitude large-cantilever steel roof truss comprises a platform pedal 2, an operation platform frame 1 consisting of trusses 1-1 and horizontal connecting rods 1-2 fixedly connected, wherein a plurality of reverse hanging connecting rods 3 are fixed on one side of the operation platform frame corresponding to a construction wall body, a protective barrier 4 is fixedly connected on one side of each operation platform frame provided with the reverse hanging connecting rods 3 and on the truss adjacent to the reverse hanging connecting rods, a plurality of lower connecting auxiliary rods 5 are arranged on one side of the operation platform frame bottom corresponding to the reverse hanging connecting rods, and two ends of each horizontal connecting rod are fixedly connected with the trusses respectively.

The anti-bending steel roof truss structure is characterized in that the reverse hanging connecting rod is formed by welding square steel pipes, a square hook portion 3-1 used for being reversely hung in a metal gutter of a high-altitude large-cantilever steel roof truss is arranged at the upper end of the reverse hanging connecting rod, two inclined supporting rods are welded in the square hook portion at the upper end of the reverse hanging connecting rod, and an anti-bending inclined rod 3-2 is arranged at the lower portion of the reverse hanging connecting rod. The reversely-hung connecting rod is reversely hung in the metal gutter 9 of the high-altitude large-cantilever steel roof truss, and the lower end of the reversely-hung connecting rod is welded with the operation platform frame.

Specifically, a platform pedal 2 is arranged on a truss 1-1 of the operating platform frame, and at least two layers of horizontal connecting rods 1-2 are fixedly connected to the operating platform frame.

Specifically, the platform pedal is made by combining a bamboo foot plate capable of meeting the load requirement, a plurality of layers of templates and a metal strip-shaped pedal.

Specifically, the guard rail 4 is formed by welding square steel pipes.

Specifically, lower connection attaches pole 5 and is made by square steel pipe, lower connection attaches the pole and is connected with operation platform frame, wall body connecting piece welded connection respectively.

Before the construction platform module is hung under the hoisting, the overhanging steel beam needs to be hoisted firstly, and before the overhanging steel beam is hoisted, the datum point is determined firstly, and the overhanging steel beam positioning line is determined. The roof steel roof truss member is hoisted by extending outwards from the middle part of the roof through a tower crane or an automobile crane, and the cantilever steel beams 8 are symmetrically installed in the south and north directions. The method comprises the steps that firstly, an overhanging short beam GL2 and an oblique beam are connected before the oblique beam is hoisted, the position of a hoisting point needs to be calculated in advance before the oblique beam is hoisted in place, then the oblique beam and a horizontal steel beam which is installed on a roof are connected through bolts, after the bolts are connected in advance, an outer frame column is in place, and after the axis position and the horizontal elevation are rechecked, the horizontal support and the lateral support are welded and connected.

Before the boundary beam is hoisted, the short beam vertically connected with the boundary beam is connected with the ground to form a T-shaped beam, hoisting is started after a hoisting point is determined, when the boundary beam is hoisted to the installation height, the angle and the position of the T-shaped beam are adjusted by a pull rope of a direction control worker at two ends of the T-shaped beam, workers at the cornice position preliminarily fix each connection part of the T-shaped beam to the installation position, welding and fastening processes are simultaneously carried out after elevation and position rechecking are qualified, and other cross-steel beams are sequentially hoisted and fixed according to the method.

Metal gutter of installation roofing (roofing gutter construction)

The size of the metal gutter 9 can meet the requirement of roof drainage flow and can be matched with the overhanging steel beam of the high-altitude large-overhanging steel roof truss structure, and the metal gutter is made and processed by manufacturers in a unified way. The metal gutter is arranged at the outer side end part of an overhanging steel beam and an edge beam of a high-altitude large-overhanging steel roof truss structure, a through long angle steel is used as a metal gutter base, the angle steel overhanging steel beam and the edge beam are connected in a welding mode, the metal gutter is connected with the angle steel through a special connecting piece, and the metal gutter is hoisted through cooperation of equipment such as manpower, a tower crane and an automobile crane, and can meet the requirements of relevant specifications during construction operation.

Manufacturing method of lower hanging construction platform module

The length, width and height of the lower hanging construction platform module can be adjusted according to the bearing capacity performance of the stressed member and the process requirements, and the safe use requirement can be met.

The lower hanging common platform module can be automatically welded and assembled according to design drawings, and the quality of a welded junction and an anti-rust measure are particularly noticed.

Referring to fig. 4 of the drawings, a schematic diagram of a display device,

a construction method of a lower hanging construction platform module of a high-altitude large-cantilever steel roof truss comprises the following steps:

s1 hoisting preparation of lower hanging construction platform module

Pulling and placing the manufactured lower hanging construction platform module to a position vertically below a position to be lifted, and rechecking each node of the lower hanging construction platform module to ensure firm connection; and the contents of hoisting machinery, a hoisting tool, a hoisting point and the like are checked, so that the hoisting safety is ensured.

S2 hoisting and debugging of lower hanging construction platform module

And putting down a hoisting rope of the winch, connecting the hoisting rope to the hoisting points of the lower hanging construction platform module, slowly hoisting, checking the stress condition of each hoisting point in detail after the hoisting rope is 50cm away from the ground, hoisting the lower hanging construction platform module to the installation position after no problem is ensured, checking each stress point, and not fixing the lower hanging construction platform module after the checking is finished. And then, the lower hanging construction platform module is adjusted away from the installation position and slowly falls to the ground, the conditions of the hoisting equipment and the lower hanging construction platform module are checked, the problem is found and corrected in time, and the hoisting and debugging are finished.

S3 formal hanging down construction platform module

a. Firstly, the lower hanging construction platform module is suspended when being lifted 50cm away from the ground, and then the lower hanging construction platform module is continuously lifted after the verticality and the levelness of the lower hanging construction platform module are checked to be correct.

b. The shaking in the hoisting process is controlled by two wind cables.

c. After the construction platform module is hung downwards to the height of the metal gutter, the reversely-hanging connecting rod 3 of the construction platform module is hung downwards and placed into the metal gutter, the construction platform module is hung downwards in a slow mode by utilizing the pull force of the wind cable rope to match with the horizontal movement of the hoisting equipment, the parallel movement of the construction platform module is hung downwards to the installation position, the square hook part of the reversely-hanging connecting rod of the construction platform module is arranged in the metal gutter, and a base plate is added at the force application point position for preventing the reversely-hanging connecting rod from damaging the metal gutter. The lower end stress point of the lower hanging construction platform module is arranged on the outer side surface of a wall and a column, rigid connection is performed through expansion bolts and the like after the position is corrected, steel rope flexible connection protection is performed on the overhanging steel beam, at the moment, the hoisting equipment can be unhooked and reset, and the next lower hanging construction platform module is prepared to be hoisted.

d. And sequentially and subsequently mounting the construction platform modules in the same way.

f. After the lower hanging construction platform modules are completely installed, square hook parts and high-strength bolt connection points of the reverse hanging connection rods are checked, professional quality inspectors and professional safety personnel check important connection points, and after the fact that the important connection points are completely installed, platform pedals 2 are laid, and the platform pedals are laid on the trusses 1-1.

g. Four steel wire safety ropes are hung on a steel roof truss cross beam by utilizing the overhanging steel beam, and safety belts of constructors are hung on the safety ropes so as to ensure the personal safety of the constructors.

h. After the lower hanging construction platform module is installed in place, the protective handrail 4 on the outer side of the lower hanging construction platform module is installed immediately, the height of the protective handrail is not smaller than 1.2m, and the distance between the protective handrails in the middle is not larger than 30 cm.

i. According to actual needs, a split bolt suspender is arranged between the lower hanging construction platform module and the cantilever steel beam, so that the bearing capacity and the safety of the lower hanging construction platform can be improved.

S4 dismantling and hanging down construction platform module

a. Marking out a working area mark, setting a warning line and forbidding pedestrians to enter.

b. The outer side protective railing of the lower hanging construction platform module is firstly detached, and the protective railing is timely hung to the ground through the hoisting equipment.

c. Whether the hard and soft connecting parts of the lower hanging construction platform module and the wall body and the steel roof truss are separated from the stress point or not is comprehensively checked, and the lower hanging construction platform module is ensured to be hung away from the next mounting position one by one after no error and is timely mounted and fixed.