阅读说明:本技术 一种护墙板与阴角角柜的施工工艺 (Construction process of wall panel and internal corner cabinet ) 是由 李志国 冯云忠 于 2020-05-09 设计创作,主要内容包括:本发明公开了一种护墙板施工工艺,在安装前通过测量工具将房屋的尺寸进行精确的测量,测量后根据得到的尺寸设计护墙板安装效果图和施工图纸,使用水平仪根据施工图纸在保证垂直度和平行度的情况下在墙面上安装基板;在基板安装完毕后,根据护墙板施工图纸对应的护墙板位置通过螺栓将基板扣件安装在基板对应位置上,将基板扣件暴露在外一侧涂上有色颜料,在有色颜料未干透之前。该护墙板与阴角角柜的施工工艺,通过设置的卡接片和扣件套,通过在安装过程中将扣件套直接固定在基板主体上,在通过在扣件套上涂上有色颜料,即可达到底座、支柱和卡接片在护墙板主体上的定位,能够达到不具备较高的工艺要求即可进行安装。(The invention discloses a construction process of a panel, which is characterized in that the dimension of a house is accurately measured by a measuring tool before installation, an installation effect drawing and a construction drawing of the panel are designed according to the obtained dimension after measurement, and a base plate is installed on a wall surface by using a level gauge according to the construction drawing under the condition of ensuring the verticality and the parallelism; after the base plate is installed, the base plate fastener is installed on the corresponding position of the base plate through the bolt according to the position of the wall panel corresponding to the construction drawing of the wall panel, the base plate fastener is exposed on the outer side, and the color pigment is coated before the color pigment is dried completely. This dado and reentrant corner cabinet's construction process, through the joint piece and the fastener cover that set up, through with fastener cover snap-on in the installation on the base plate main part, coating colored pigment through sheatheeing in the fastener, can reach the location of base, pillar and joint piece in the dado main part, can reach and do not possess higher technological requirement and can install.)

1. A construction process of a wall panel is characterized by comprising the following steps:

s1 and mounting substrate

The method comprises the following steps of accurately measuring the size of a house through a measuring tool before installation, designing a mounting effect drawing and a construction drawing of a wall panel according to the obtained size after measurement, and installing a substrate on a wall surface by using a level gauge according to the construction drawing under the condition of ensuring the verticality and the parallelism;

s2 mounting fastener

After the base plate is installed, installing the base plate fastener on the corresponding position of the base plate through a bolt according to the position of the wall panel corresponding to the construction drawing of the wall panel, exposing the base plate fastener on the outer side, coating a colored pigment, attaching the wall panel correspondingly to the wall panel before the colored pigment is dried completely so that the colored pigment leaves a mark on the wall panel, and installing the wall panel fastener on the installation surface of the wall panel according to the mark;

s3, mounting of wall panel

After the fasteners are installed, the wall panel is aligned with the substrate installation fasteners through the wall panel installation fasteners and pressed down, and then the installation of the wall panel and the substrate can be achieved.

2. The wall panel construction process according to claim 1, wherein the substrate fastener in the step S2 comprises a fastener sleeve (6), a clamping sliding block (4), a clamping groove (9) and a fixing block (8), the fastener sleeve (6) is close to the bottom fixedly connected with fixing block (8), the clamping groove (9) is formed in the inner wall of the fastener sleeve (6) close to the bottom, the clamping sliding block (4) is fixedly connected to the left side of the clamping groove (9) and close to the inner wall of the fastener sleeve (6), and an arc-shaped notch is formed in the clamping sliding block (5) close to the left side.

3. A panel construction process according to claim 1, wherein the panel fastener in step S2 comprises a base (5), a pillar (4) and a clip (2), the right side of the base (5) is fixedly connected to the left end of the pillar (4), and the right end of the pillar (4) is fixedly connected to the clip (2).

4. A panel construction process according to claim 1, wherein in step S3, the panel and the substrate are installed by fasteners such that the base (5), the pillar (4) and the clip (2) are sleeved into the fastener sleeve (6), and the clip (2) is clipped with the clip groove (9) and the clip slider (7).

5. A panel construction process according to claim 3, wherein four bases (5), four pillars (4) and four clamping pieces (2) are arranged and distributed at four corners of the panel main body (3).

6. A panel construction process according to claim 4, characterised in that the base (5) is fitted into the fastener sleeve (6) and the diameter of the inner wall of the fastener sleeve (6) is equal to the diameter of the base (5).

7. The inside corner cabinet construction process is characterized by comprising the following steps:

s1, measuring size and selecting corner cabinet

Before the corner cabinet is installed, measuring the size of an internal corner of the house after the wall panel is installed, and after the measurement is finished, selecting a corresponding corner cabinet according to the measured size of the internal corner;

s2 installation of corner cabinet fastener

Installing a corner cabinet fastener on one surface of a corresponding internal corner of a corner cabinet, after the corner cabinet fastener is installed, coating a colored pigment on the exposed side of the corner cabinet fastener, attaching the corner cabinet to the corner cabinet correspondingly before the colored pigment is dried completely so that the colored pigment leaves a mark on the wall panel, forming an installation hole on the wall panel according to the mark, and fixing the installation fastener in the installation hole;

s3 corner cabinet installation

The corner cabinet fastener corresponds to the mounting fastener and is pressed down, so that the corner cabinet is mounted through the fastener and the wall panel, and seamless connection is performed.

8. The inside corner cabinet construction process according to claim 7, wherein the corner cabinet fasteners and the wall panel fasteners in step S2 are of uniform specification and are provided with bases (5), pillars (4) and clamping pieces (2).

9. The inside corner cabinet construction process according to claim 7, wherein the installation fasteners in step S2 include fastener sleeves (6), clamping sliders (7), clamping grooves (9) and fixing holes (10), the clamping grooves (9) are formed in the inner walls of the fastener sleeves (6) near the bottom, the clamping sliders (7) are fixedly connected to the left sides of the clamping grooves (9) and near the inner walls of the fastener sleeves (6), the clamping sliders (7) are provided with arc notches near the left sides, and the fixing holes (10) are formed in the inner walls of the fastener sleeves (6) near the right sides of the clamping grooves (9).

10. The inside corner cabinet construction process according to claim 7, wherein in step S3, the corner cabinet fasteners and the mounting fasteners are installed in the same way as the retaining wall panel fasteners and the base panel fasteners, and all the fasteners are installed by sleeving the base (5), the pillar (4) and the clamping sheet (2) into the fastener sleeve (6), and the clamping sheet (2) is clamped with the clamping groove (9) and the clamping slider (7).

Technical Field

The invention relates to the technical field of construction of wall panels and internal corner cabinets, in particular to a construction process of the wall panels and the internal corner cabinets.

Background

The wall panel is a new material for decorating wall bodies developed in recent years, generally adopts wood and the like as a base material, and has the advantages of attractive appearance, light weight, fire resistance, moth resistance, simple and convenient construction, low manufacturing cost, safe use, obvious decoration effect, convenient maintenance and the like, thereby being popular with people.

The corner cabinet is also called a corner cabinet, can be placed at the corner of the household layout, reasonably utilizes the space, and can play the role of attractive storage.

The existing wall panel needs to be accurately measured through a measuring scale in the installation process, the fastener is installed in a refined mode, the wall panel can be installed, the installation process is time-consuming, labor-consuming, high in installation requirement personnel operation is needed, the installation process is not suitable for the society which is rapidly developed at present, gaps are reserved after installation in the installation process of the corner cabinet at the internal corner, and the corner cabinet is unstable, and therefore the construction process of the wall panel and the internal corner cabinet needs to be invented urgently.

Disclosure of Invention

Technical problem to be solved

Aiming at the defects of the prior art, the invention provides a construction process of a wall panel and an internal corner cabinet, which has the advantages of time and labor saving, lower installation requirements, no gap and stability after the corner cabinet is installed and the like, and solves the problems that the installation process is time-consuming and labor-consuming, and the operation of personnel with higher installation requirements and the gap and instability after the installation are required.

(II) technical scheme

In order to realize the purposes of time saving, labor saving, lower installation requirement and no gap and stability after the corner cabinet is installed, the invention provides the following technical scheme: a construction process of a wall panel comprises the following steps:

s1 and mounting substrate

The method comprises the steps of carrying out accurate measurement on the size of a house through a measuring tool before installation, designing a mounting effect graph and a construction drawing of the panel according to the obtained size after measurement, and installing a base plate on a wall surface by using a level gauge according to the construction drawing under the condition of ensuring perpendicularity and parallelism.

S2 mounting fastener

After the base plate installation finishes, install the base plate fastener on the base plate corresponds the position through the bolt according to the dado position that dado construction drawing corresponds, expose the base plate fastener and scribble colored pigment on one side outside, before colored pigment does not dry out, paste that corresponds the dado and make colored pigment leave the mark on the dado, install the dado fastener at the dado installation face according to the mark.

S3, mounting of wall panel

After the fasteners are installed, the wall panel is aligned with the substrate installation fasteners through the wall panel installation fasteners and pressed down, and then the installation of the wall panel and the substrate can be achieved.

Preferably, the base plate fastener in step S2 includes fastener cover, joint slider, joint groove and fixed block, the fastener cover is close to bottom fixed connection fixed block, the fastener cover inner wall is close to the bottom and has seted up the joint groove, fastener cover inner wall is close to joint groove left side fixed connection joint slider, the joint slider is close to the left side and has seted up the arc breach.

Preferably, in the step S2, the panel fastener includes a base, a pillar and a clip, the right side of the base is fixedly connected to the left end of the pillar, and the right end of the pillar is fixedly connected to the clip.

Preferably, in step S3, the baseboard and the baseboard are mounted by fasteners such that the base, the pillar and the clip are sleeved in the fastener sleeves, and the clip is clipped with the clip groove and the clip slider.

Preferably, base, pillar and joint piece are provided with four, distribute in dado main part four corners.

Preferably, the base is sleeved in the fastener sleeve, and the diameter of the inner wall of the fastener sleeve is equal to that of the base.

The invention provides a construction process of an internal corner cabinet, which aims to solve another technical problem and comprises the following steps:

s1, measuring size and selecting corner cabinet

Before the corner cabinet is installed, the size of the internal corner of the house after the wall panel is installed is measured, and after the measurement is finished, the corresponding corner cabinet is selected according to the measured size of the internal corner.

S2 installation of corner cabinet fastener

The corner cabinet fastener is installed on one side of the internal corner of the corner cabinet corresponding to the installation, after the corner cabinet fastener is installed, the corner cabinet fastener is exposed on one side of the external side and coated with colored pigment, before the colored pigment is dried completely, the corner cabinet is attached to the wall panel so that the colored pigment can leave a mark on the wall panel, the installation hole is formed in the wall panel according to the mark, and the installation fastener is fixed in the installation hole.

S3 corner cabinet installation

The corner cabinet fastener corresponds to the mounting fastener and is pressed down, so that the corner cabinet is mounted through the fastener and the wall panel, and seamless connection is performed.

Preferably, the corner cabinet fasteners and the wall panel fasteners in step S2 are of a uniform specification and are provided with a base, a pillar and a clamping piece.

Preferably, installation fastener includes fastener cover, joint slider, joint groove and fixed orifices in step S2, the joint groove has been seted up near the bottom to the fastener cover inner wall, fastener cover inner wall is close to joint groove left side fixed connection joint slider, the joint slider has been seted up near the left side arc breach, fastener cover inner wall has been seted up near joint groove right side fixed orifices.

Preferably, in the step S3, the installation modes of the corner cabinet fastener and the installation fastener are the same as the installation modes of the retaining wall fastener and the base plate fastener, the base, the pillar and the clamping piece are all sleeved in the fastener sleeve, and the clamping piece is clamped with the clamping groove and the clamping slider.

(III) advantageous effects

Compared with the prior art, the invention provides a construction process of a wall panel and an internal corner cabinet, which has the following beneficial effects:

1. this construction process of dado and reentrant corner angle cabinet through joint piece and the fastener cover that sets up, through with fastener cover snap-on in the installation on the base plate main part, sheathe in through the fastener and scribble colored pigment, can reach the location of base, pillar and joint piece in the dado main part, can reach and do not possess higher technological requirement and can install.

2. According to the construction process of the wall panel and the internal corner cabinet, the clamping slide block and the clamping groove are arranged, when the wall panel and the corner cabinet are installed, the base, the pillar and the clamping sheet are sleeved into the fastener sleeve, and meanwhile, the clamping sheet is clamped with the clamping groove and the clamping slide block, so that the purpose of quick installation can be achieved, and time and labor are saved effectively.

3. This construction process of dado and reentrant corner cabinet through the fixed block that sets up, can be after the dado installation, provides the holding power through the fixed block, the effectual stability of having guaranteed the dado installation, simultaneously through in base, pillar and joint piece cup joint fastener cover, joint piece and joint groove and joint slider joint can the effectual seamless installation of assurance corner cabinet and dado simultaneously.

Drawings

FIG. 1 is a schematic view of the construction process of the panel of the present invention;

FIG. 2 is a schematic view of the construction process of the inside corner cabinet of the present invention;

FIG. 3 is a schematic view of the structure of the panel body, panel fastener, substrate fastener and substrate body of the present invention;

FIG. 4 is an enlarged view of the structure at A in FIG. 3 according to the present invention;

FIG. 5 is a schematic view of the mounting clip of the present invention.

In the figure: 1 base plate main part, 2 joint pieces, 3 dado main parts, 4 pillars, 5 bases, 6 fastener covers, 7 joint sliders, 8 fixed blocks, 9 joint grooves, 10 fixed orifices.

Detailed Description

The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.

11页详细技术资料下载
上一篇:一种医用注射器针头装配设备
下一篇:塑料发泡双面金属连接导热防潮减震垫

网友询问留言

已有0条留言

还没有人留言评论。精彩留言会获得点赞!

精彩留言,会给你点赞!