Construction method for reversely hoisting horizontal prefabricated floor slab
阅读说明:本技术 一种水平预制楼板反向吊装的施工方法 (Construction method for reversely hoisting horizontal prefabricated floor slab ) 是由 宋千军 于 2019-10-20 设计创作,主要内容包括:一种水平预制楼板反向吊装的施工方法,其步骤如下:1)、地上的墙体施工至屋顶层,在墙体对应每层楼板安装处埋设有连接楼板的水平固定装置;2)、进行楼板预制,预制的所述楼板的外周设置有可与所述水平固定装置连接的连接装置;3)、楼板吊装:将预制楼板通过吊装设备将楼板吊装至屋顶需安装楼板位置处,通过固定连接件将楼板与水平固定装置连接;然后进行灌缝处理;4)、将吊装设备拆卸后再安装到已吊装好的屋顶楼板下方的墙体上,重复步骤3),依次反向向下吊装楼板直至第二层楼板完毕。本发明的施工方法,在施工上施工工序少,工艺简单,可避免使用大型吊装设备,适应于机械化作业的需求。(A construction method for reversely hoisting a horizontal precast floor slab comprises the following steps: 1) constructing the wall body on the ground to a roof layer, and embedding a horizontal fixing device for connecting floor slabs at the installation position of the wall body corresponding to each floor slab; 2) prefabricating a floor slab, wherein a connecting device which can be connected with the horizontal fixing device is arranged on the periphery of the prefabricated floor slab; 3) and hoisting the floor slab: hoisting the prefabricated floor slab to the position of the floor slab to be installed on the roof through hoisting equipment, and connecting the floor slab with a horizontal fixing device through a fixing connecting piece; then performing crack pouring treatment; 4) and detaching the hoisting equipment and then installing the hoisting equipment on a wall body below the hoisted roof floor slab, repeating the step 3), and sequentially and reversely hoisting the floor slab downwards until the second floor slab is finished. The construction method has the advantages of few construction procedures in construction, simple process, avoidance of use of large-scale hoisting equipment and suitability for the requirement of mechanized operation.)
1. A construction method for reversely hoisting a horizontal precast floor slab comprises the following steps: 1) constructing all wall bodies required by the building on the ground to the top layer of the building, and respectively embedding horizontal fixing devices connected with the floor slabs at the positions of the wall bodies corresponding to the floor slabs; 2) in the construction process of the step 1), prefabricating a floor slab, wherein a connecting device which can be connected with the horizontal fixing device is arranged on the periphery of the prefabricated floor slab; 3) and hoisting the floor slab: arranging hoisting equipment at the top end of the wall body of the floor slab to be hoisted, placing the prefabricated floor slab in a space defined by the wall body of the floor slab to be hoisted, hoisting the floor slab to the position of the floor slab to be installed on the roof through the hoisting equipment, and connecting the floor slab with the horizontal fixing device through a fixed connecting piece; then, performing crack pouring treatment on a gap between the wall body and the floor; 4) the hoisting equipment is disassembled and then installed on the wall body below the hoisted roof floor slab, the step 3) is repeated, and the next higher floor slab is hoisted; 5) and repeating the steps 3) and 4), and lifting the next layer of prefabricated floor slab downwards in sequence until the lifting of the second layer of floor slab is finished.
2. The construction method for reverse hoisting of the horizontal precast floor slab according to claim 1, wherein in the step 1), the wall body is a steel rib-fiber concrete structure wall body; the steel ribs are embedded at the stress concentration part in the fiber concrete poured wall body and the edge of the opening part of the wall body.
3. The construction method for reversely hoisting the horizontal precast floor slab according to claim 2, wherein in the step 1), a heat insulation sandwich module is embedded in the steel rib-fiber concrete wall.
4. The construction method for reversely hoisting the horizontal precast floor slab according to claim 1, wherein in the step 1), the horizontal fixing device is a counter-pulling anchoring steel rib embedded in the wall body, and two ends of the counter-pulling anchoring steel rib are respectively located at two side wall surfaces of the wall body.
5. The construction method for reverse hoisting of a horizontal precast floor slab according to claim 1, wherein in the step 3), the fixed connection member is an angle iron.
6. The construction method for horizontally hoisting a precast floor slab reversely according to claim 1, wherein in the step 2), the prefabricated connecting means of the outer periphery of the floor slab is a steel structural frame integrally connected with the embedded steel bars in the floor slab.
7. The construction method for reversely hoisting the horizontal precast floor slabs according to claim 1, wherein in the step 2), the floor slabs are precast in the space surrounded by the wall, the precast floor slabs are horizontally stacked in layers, and adjacent floor slabs are isolated by an isolation material.
8. The construction method for reversely hoisting the horizontal precast floor slab according to claim 1, wherein when the floor slab is hoisted in the step 3), a guide device for preventing the floor slab from colliding with the wall body is detachably arranged at intervals around the floor slab.
9. The method as claimed in claim 8, wherein the horizontal precast floor slab is reversely hoisted, and the four corners of the floor slab are provided with hoisting points, the guide means is provided at the hoisting points on the side close to the wall surface, and the guide means is extended from the peripheral sides of the floor slab.
10. The construction method for reverse hoisting of a horizontal precast floor slab according to claim 9, wherein the guide means is a roller.
Technical Field
The invention relates to the field of building construction, in particular to a construction method for reversely presetting and assembling a horizontal structure of a building.
Background
The main ground engineering of building construction generally consists of a load-bearing structure and a filling wall body for separation. The method is characterized in that a reinforced concrete cast-in-place mode is adopted in a bearing structure, which is the most important one, and a basic structure system is generally formed by reinforced concrete shear walls, frame columns, frame beams and floor slabs; the infilled wall is generally made of various bricks, blocks or laths and the like, and is built or installed and fixed on a bearing structure to separate the building space to form the use spaces of the buildings.
In the construction, the cast-in-place reinforced concrete building is firstly subjected to main body bearing structure construction, generally according to the floor layering construction of a building structure, pouring from the bottom to the upper layer by layer, configuring templates for each layer according to the section sizes of walls, columns, beams and plates, binding reinforcing steel bars and pouring concrete. And building the filler wall after the construction of the main body structure is finished, and finally performing decoration construction. The prefabricated reinforced concrete prefabricated building is generally characterized by that according to the same cast-in-place concept, the building structure can be divided into prefabricated components and cast-in-place portion according to the requirements, all the components are prefabricated in factory, after the components are transported to site, the components are hoisted and temporarily fixed, then the cast-in-place portion steel bar installation, formwork installation and concrete pouring are implemented, the construction also is the floor layer-by-layer construction for installing building structure, and the construction is completed from bottom to top layer by layer.
At present, large-scale mechanical equipment is needed for vertical material transportation in construction, particularly prefabricated reinforced concrete prefabricated buildings, the tonnage of a prefabricated part is heavy, and the required tower crane tonnage is extremely large and the cost is high. After research, the invention provides a building structure with all cast-in-place vertical walls and prefabricated horizontal structures, the vertical walls are directly used as hoisting supports, and whether the horizontal structures can be installed from the top layer to the bottom layer of the building can be determined, so that the use of large-scale equipment can be reduced, and the construction period can be shortened. The invention provides a construction technology for reverse prefabrication and assembly of a horizontal structure, which can solve the problems.
Disclosure of Invention
The technical problem to be solved by the invention is to provide a construction method for reversely installing a horizontal floor slab, which is installed on a wall body with certain bearing capacity, high strength and simple and convenient construction. The prefabricated floor slabs are sequentially installed from top to bottom, large-scale hoisting equipment is not needed, and the method has the advantages of convenience in construction, few construction procedures and the like.
In order to solve the technical problem, the technical scheme provided by the invention is a construction method for reversely hoisting a horizontal precast floor slab, which comprises the following steps: 1) constructing all wall bodies required by the building on the ground to the top layer of the building, and respectively embedding horizontal fixing devices connected with the floor slabs at the positions of the wall bodies corresponding to the floor slabs; 2) in the construction process of the step 1), prefabricating a floor slab, wherein a connecting device which can be connected with the horizontal fixing device is arranged on the periphery of the prefabricated floor slab; 3) and hoisting the floor slab: arranging hoisting equipment at the top end of the wall body of the floor slab to be hoisted, placing the prefabricated floor slab in a space defined by the wall body of the floor slab to be hoisted, hoisting the floor slab to the position of the floor slab to be installed on the roof through the hoisting equipment, and connecting the floor slab with the horizontal fixing device through a fixed connecting piece; then, performing crack pouring treatment on a gap between the wall body and the floor; 4) the hoisting equipment is disassembled and then installed on the wall body below the hoisted roof floor slab, the step 3) is repeated, and the next higher floor slab is hoisted; 5) and repeating the steps 3) and 4), and lifting the next layer of prefabricated floor slab downwards in sequence until the lifting of the second layer of floor slab is finished.
In the step 1), the wall body is a steel rib-fiber concrete structure wall body; the steel ribs are embedded at the stress concentration part in the fiber concrete poured wall body and the edge of the opening part of the wall body.
In the step 1), a heat-insulating sandwich module is embedded in the steel rib-fiber concrete wall.
In the step 1), the horizontal fixing device is a counter-pulling anchoring steel rib embedded in the wall body, and two ends of the counter-pulling anchoring steel rib are respectively located on wall surfaces on two sides of the wall body.
In the step 3), the fixed connecting piece is an angle steel.
In the step 2), the prefabricated connecting device at the periphery of the floor slab is a steel structure frame which is connected with the embedded steel bars in the floor slab into a whole.
In the step 2), the floor slabs are prefabricated in the space defined by the wall, the prefabricated floor slabs are horizontally stacked in layers, and adjacent floor slabs are isolated by isolating materials.
When the floor slab in the step 3) is hoisted, guiding devices for preventing the floor slab from colliding with the wall body are detachably arranged at the periphery of the floor slab at intervals.
The four corners of the floor are provided with hanging points, the guide device is arranged on the hanging points close to one side of the wall surface, and the guide device extends out of the surrounding side sides of the floor.
The guiding device is a roller.
The reverse hoisting method of the prefabricated floor slab can directly utilize the vertical wall body as a hoisting support, and the horizontal structure is installed from the top layer to the bottom layer of the building, so that the use of large-scale equipment can be reduced, and the construction period can be shortened.
Drawings
FIG. 1 is a schematic sectional view.
Fig. 2 is a schematic view of a sectional structure inside the wall body.
Fig. 3 is a schematic diagram of a hoisting section of a horizontal prefabricated floor slab on a roof.
Fig. 4 is a schematic diagram of a hoisting section of a horizontal precast floor slab of the next floor of the roof.
Fig. 5 is a schematic view of a plane for hoisting a flat prefabricated floor slab.
Fig. 6 is a schematic view of a horizontal precast floor slab reverse hoisting section.
Fig. 7, schematic view of a horizontal precast floor slab hoisting guide device.
Fig. 8 shows the connection between the horizontal precast floor slab and the vertical wall.
Detailed Description
In order that the present disclosure may be more readily and clearly understood, the present disclosure will now be described in further detail with reference to the following detailed description of specific embodiments thereof, taken in conjunction with the accompanying drawings, in which:
first, the wall of the present invention will be described by taking a steel-reinforced concrete structural wall developed by itself as an example. In the
A horizontal fixing device is embedded in the wall body at the position where each floor needs to be installed, so that the floor can be connected with the horizontal fixing device when being installed, and the floor is fixed. In this embodiment, the horizontal fixing device is a counter-pulling anchoring
And (3) prefabricating the
The concrete construction steps of horizontal precast floor slab reverse hoisting are as follows:
and (3) construction of all walls of the overground part of building: the construction of the building is that firstly, a reinforced concrete foundation is constructed according to the traditional requirements, and then the construction of the main structure on the ground is carried out after the foundation is completed. The construction of the overground main body building comprises the construction of a wall body. The construction of vertical wall body,
In the process of wall construction, the
After the wall body is constructed to the roof and all construction is finished, the
The building formed by the wall body and the floor slab can be used as a bearing wall and a partition wall because the wall body has bearing capacity. In the building, horizontal structural members are prefabricated floor slabs.
- 上一篇:一种医用注射器针头装配设备
- 下一篇:一种叠合板安装台车配合塔吊安装叠合板的施工工艺