Three-dimensional maintenance operation platform of full-length gantry type power-concentrated motor train unit

文档序号:1607264 发布日期:2020-01-10 浏览:29次 中文

阅读说明:本技术 一种通长龙门架式动力集中动车组立体检修作业平台 (Three-dimensional maintenance operation platform of full-length gantry type power-concentrated motor train unit ) 是由 周明星 杨辉 郑青松 邱绍峰 李经伟 林飞 李加祺 何武山 冯帅 刘宗泽 于 2019-09-19 设计创作,主要内容包括:本发明公开了一种通长龙门架式动力集中动车组立体检修作业平台,其特征在于:用于对既有客整所进行改造,包括接触网腕臂(2)、龙门架(3)、防护网(4)、腕臂安装支柱(5)、防雨棚(7)、三层作业平台(8)、二层作业平台(9);其构造设计,对出入所线,牵出线带地沟整备股道进行电化挂网,用于完成160公里动力集中型动车组动力车D1修程中的机车一级整备、客车日常检修等。可以有效的缩短人工作业难度、作业时间。同时新增安全联锁监控系统,保证检修人员登顶作业安全。(The invention discloses a through-long portal frame type power centralized motor train unit three-dimensional overhaul operation platform which is characterized in that: the device is used for transforming the existing passenger station and comprises a contact net cantilever (2), a portal frame (3), a protective net (4), a cantilever mounting pillar (5), a rain-proof shed (7), a three-layer operation platform (8) and a two-layer operation platform (9); the structure design is that electrified net hanging is carried out on the incoming and outgoing lines with trench preparation station tracks, and the electrified net hanging device is used for finishing locomotive primary preparation, daily passenger car maintenance and the like in the maintenance process of the power D1 of the 160 kilometer power concentrated motor train unit power car. The manual operation difficulty and the operation time can be effectively shortened. Meanwhile, a safety interlocking monitoring system is added, and the safety of the overhaul personnel in the top climbing operation is guaranteed.)

1. The utility model provides a three-dimensional operation platform that overhauls of EMUs is concentrated to logical long portal frame formula power which characterized in that: the device is used for transforming the existing passenger station and comprises a contact net cantilever (2), a portal frame (3), a protective net (4), a cantilever mounting pillar (5), a rain-proof shed (7), a three-layer operation platform (8) and a two-layer operation platform (9);

the portal frames (3) are arranged above the preparation tracks of the multi-strip ditches of the existing passenger preparation facilities in a spanning mode, and the portal frames (3) are sequentially arranged at intervals along the longitudinal direction of the tracks; the portal frame (3) comprises portal frame columns (31) on two sides and a middle operation frame (32);

the protective net (4) and the cantilever mounting strut (5) are arranged below the operation frame (32) and above the middle of an adjacent preparation station track in the portal frame;

the contact net cantilevers (2) are arranged on the two transverse sides of the cantilever mounting support (5) and are positioned above the power-concentrated motor train unit (1);

the inner sides of the two portal frame columns (31) are sequentially provided with the rain-proof shed (7), the three-layer operation platform (8) and the two-layer operation platform (9) from top to bottom; the two-layer operation platform (9) is arranged on the side surfaces of a head train and a tail train of the power-concentrated motor train unit, and the three-layer operation platform (8) is arranged on the side surface of the middle part of the power-concentrated motor train unit.

2. The full-length gantry type power-concentrated motor train unit three-dimensional overhauling operation platform as recited in claim 1, which is characterized in that:

the first column of the two portal frame columns (31) is arranged between a preparation track with a trench of the existing passenger coach and a parking line track without the trench of the existing passenger coach.

3. The full-length gantry type power-concentrated motor train unit three-dimensional overhauling operation platform as recited in claim 2, wherein:

the first upright post is provided with the contact net cantilever (2) towards the outer side of the portal frame and located above the power-concentrated motor train unit of the parking line track.

4. The full-length gantry type power-concentrated motor train unit three-dimensional overhauling operation platform as recited in claim 1, which is characterized in that:

and the second column of the two portal frame columns (31) is arranged between a preparation track with a trench in the portal frame of the existing customer service center and a preparation track with a trench outside the portal frame of the existing customer service center.

5. The full-length gantry type power-concentrated motor train unit three-dimensional overhauling operation platform as recited in claim 4, wherein:

the second upright post is provided with a contact net cantilever (2) towards the outer side of the portal frame and positioned above a power-concentrated motor train unit of a preparation station track with a trench outside the portal frame of the existing passenger service station;

or the contact net cantilever (2) is not arranged on the second upright column towards the outer side of the portal frame.

6. The full-length gantry type power-concentrated motor train unit three-dimensional overhauling operation platform as recited in claim 3, wherein:

and an installation interface of the contact net cantilever (2) is preset on the portal frame upright post (31).

7. The full-length gantry type power-concentrated motor train unit three-dimensional overhauling operation platform as recited in claim 1, which is characterized in that:

the contact net cantilever (2) is hung in a simple chain type, and the hanging type is contact hanging.

8. The full-length gantry type power-concentrated motor train unit three-dimensional overhauling operation platform as recited in claim 1, which is characterized in that:

and the mounting interface of the contact net cantilever (2) is preset on the cantilever mounting strut (5).

9. The full-length gantry type power-concentrated motor train unit three-dimensional overhauling operation platform as recited in claim 1, which is characterized in that:

a ladder stand is arranged between the second-layer operation platform (9) and the ground, and a ladder stand with a safety door is arranged between the third-layer operation platform (8) and the second-layer operation platform (9).

10. The full-length gantry type power-concentrated motor train unit three-dimensional overhauling operation platform as recited in claim 1, which is characterized in that:

and a loading platform (10) is arranged at the outer side of the two-layer operation platform (9) and between the outer sides of the two-layer operation platform and the plurality of portal frames (3) in the longitudinal direction and is used for storing tools.

Technical Field

The invention belongs to the field of reconstruction of existing passenger trains and maintenance of power-concentrated motor train units, and particularly relates to a through-long portal frame type three-dimensional maintenance operation platform for a power-concentrated motor train unit.

Background

At present, railway passenger trains are mainly divided into motor train units (power decentralized type) and general-speed passenger trains. In order to meet different market demands, in the serial development of the Chinese standard motor train unit with 'Fuxing' number, the standard motor train unit forms a standard serial product with the speed grade of CR400/300/200, wherein the standard motor train unit with the CR200 grade gradually replaces a common passenger bus.

The power-concentrated motor train unit is used as a series of 'renaming' motor train units and plays an important role in upgrading and upgrading speed-increasing passenger cars, promoting structural reform of the railway passenger transport supply side and improving transport organization efficiency. Compared with the traditional locomotive and vehicle general speed train, the power-concentrated motor train unit adopts an operation mode without decoding, reduces the operation time of decoding, changing ends and the like, and adopts a locomotive vehicle fixed grouping and integrated maintenance mode.

At present, the detection operation surface of the power concentrated motor train unit has no contact net facilities for the whole passenger and the existing preparation line, and cannot meet the traveling requirements of the power concentrated motor train unit and the difficulty of vehicle maintenance operation.

In addition, the structural parameters of the power-concentrated motor train unit are quite different from those of the traditional motor train unit. If a newly built motor car is specially used for overhauling the motor car, the engineering investment is large, land acquisition is difficult, and the construction period is long. If the engineering machine is dragged to the maintenance of the passenger train maintenance station, the maintenance facilities of the passenger train maintenance station cannot adapt to the requirements of power-concentrated motor train unit maintenance, top-climbing maintenance and parking.

Disclosure of Invention

Aiming at least one of the defects or improvement requirements in the prior art, the invention provides a full-length portal frame type three-dimensional overhaul operation platform for a power-concentrated motor train unit, which aims to meet the requirement of the power-concentrated motor train unit on top overhaul operation and save the space of an overhaul channel between a station track and a station track according to the adaptability improvement requirement, and provides the full-length portal frame type three-dimensional overhaul operation platform for the power-concentrated motor train unit, which is used for electrochemically screening the station track with a trench for access and exit lines and is used for finishing locomotive primary overhaul, passenger train daily overhaul and the like in the repair process of a power-concentrated motor train unit D1 with 160 kilometers of power. The manual operation difficulty and the operation time can be effectively shortened. Meanwhile, a safety interlocking monitoring system is added, and the safety of the overhaul personnel in the top climbing operation is guaranteed.

In order to achieve the purpose, according to one aspect of the invention, the invention provides a full-length portal frame type power-concentrated motor train unit three-dimensional overhaul operation platform which is used for transforming an existing passenger train unit and comprises a contact network cantilever, a portal frame, a protective net, a cantilever mounting pillar, a rain-proof shed, a three-layer operation platform and a two-layer operation platform;

the portal frames are arranged above the preparation tracks of the multi-strip ditches of the existing passenger preparation facilities in a spanning mode, and the portal frames are sequentially arranged at intervals along the longitudinal direction of the tracks; the portal frame comprises portal frame upright columns on two sides and an operation frame in the middle;

the protective net and the cantilever mounting strut are arranged below the operation frame and above the middle of an adjacent preparation station track in the portal frame;

the contact net cantilevers are arranged on the two transverse sides of the cantilever mounting support and are positioned above the power-concentrated motor train unit;

the inner sides of the two portal frame stand columns are sequentially provided with the rain-proof shed, the three-layer operation platform and the two-layer operation platform from top to bottom; the two-layer operation platform is arranged on the side surfaces of a head train and a tail train of the power-concentrated motor train unit, and the three-layer operation platform is arranged on the side surface of the middle part of the power-concentrated motor train unit.

Preferably, a first column of the two gantry columns is arranged between a preparation track with a trench of the existing passenger coach and a storage line track without the trench of the existing passenger coach.

Preferably, the first upright post is provided with the contact net cantilever towards the outer side of the portal frame and located above the power-concentrated motor train unit of the parking line track.

Preferably, the second column of the two gantry columns is arranged between the preparation track with the trench in the gantry of the existing customer service center and the preparation track with the trench outside the gantry of the existing customer service center.

Preferably, the overhead line system cantilever is arranged on the second upright column towards the outer side of the portal frame and is positioned above the power-concentrated motor train unit with the preparation station track with the trench outside the portal frame of the existing passenger preparation station;

or the second upright column is not provided with the contact net cantilever towards the outer side of the portal frame.

Preferably, the installation interface of the contact net cantilever is preset on the portal frame upright post.

Preferably, the contact net cantilever is suspended in a simple chain type, and the suspension type is contact suspension.

Preferably, the mounting interface of the contact net cantilever is preset on the cantilever mounting pillar.

Preferably, a ladder stand is arranged between the second-layer operation platform and the ground, and a ladder stand with a safety door is arranged between the third-layer operation platform and the second-layer operation platform.

Preferably, the outer side of the two-layer operation platform is provided with a loading platform arranged between the plurality of portal frames in the longitudinal direction for storing tools.

The above-described preferred features may be combined with each other as long as they do not conflict with each other.

Generally, compared with the prior art, the above technical solution conceived by the present invention has the following beneficial effects:

1. the through-length portal frame type power centralized motor train unit three-dimensional overhaul operating platform provided by the invention is used for carrying out electrified net hanging on the in-out line, the out-drawn line and the trench-equipped station track, and is used for finishing locomotive primary servicing, passenger train daily overhaul and the like in the power D1 repair process of a 160-kilometer power centralized motor train unit power vehicle. The manual operation difficulty and the operation time can be effectively shortened. Meanwhile, a safety interlocking monitoring system is added, and the safety of the overhaul personnel in the top climbing operation is guaranteed.

2. The through-length portal frame type power centralized motor train unit three-dimensional overhaul operating platform comprises a ground one-layer operating platform, a head-tail two-layer operating platform and a through type three-layer operating platform, covers the longest 20 marshalling lengths of the motor train unit at present, can easily perform operations such as inspection on the bottom of a locomotive, oil filling, water filling, sand filling and the like, performs omnibearing three-dimensional cleaning and inspection on doors and windows of the locomotive, the interior of the locomotive and roof equipment, meets the requirement of power centralized motor train unit top-climbing overhaul operation, and greatly improves overhaul efficiency and safety.

3. The through-length portal frame type power centralized motor train unit three-dimensional overhauling operation platform has the advantages that the main body adopts a portal type steel structure, the structure is stable, and safety and reliability are realized. The top is equipped with the weather enclosure, avoids the outdoor operation of staff, can deal with bad weather such as sleet, has improved operation platform's practicality, travelling comfort.

4. The through-length portal frame type power centralized motor train unit three-dimensional overhaul operating platform is compact in overall layout structure and small in occupied space, the overhaul channel is arranged by utilizing the upper suspension mode between 6 channels and 7 channels, the space of the overhaul channel between the station tracks is saved, the existing hardened ground can be used for walking the overhaul vehicle, and the overhaul channel and large part transportation overhaul operation requirements are met.

Drawings

FIG. 1 is a schematic composition diagram of a full-length gantry type power-concentrated motor train unit three-dimensional overhaul operating platform according to an embodiment of the invention;

FIG. 2 is a schematic cross-sectional view of a full-length gantry-type power-concentrated motor train unit three-dimensional overhaul operating platform according to an embodiment of the invention;

FIG. 3 is a schematic partial overhead view of a full-length gantry-type power-concentrated motor train unit three-dimensional maintenance operation platform according to an embodiment of the invention;

FIG. 4 is a portal frame schematic view of a full-length portal frame type power-concentrated motor train unit three-dimensional overhaul operating platform according to an embodiment of the invention;

FIG. 5 is a schematic diagram of a protective net of the through-long gantry type power-concentrated motor train unit three-dimensional overhaul operating platform according to the embodiment of the invention;

FIG. 6 is a schematic view of a contact network cantilever of a through-long gantry type power-concentrated motor train unit three-dimensional overhaul operating platform according to an embodiment of the invention;

FIG. 7 is a schematic view of a cantilever mounting upright post of a full-length gantry type power-concentrated motor train unit three-dimensional overhaul operating platform according to an embodiment of the invention;

fig. 8 is a schematic diagram of a two-layer operation platform and a three-layer operation platform of the full-length gantry type power-concentrated motor train unit three-dimensional overhaul operation platform in the embodiment of the invention.

Fig. 9 is a schematic view of a rain-proof shed of a full-length gantry type power-concentrated motor train unit three-dimensional overhaul operating platform in the embodiment of the invention.

Detailed Description

In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention. In addition, the technical features involved in the embodiments of the present invention described below may be combined with each other as long as they do not conflict with each other. The present invention will be described in further detail with reference to specific embodiments.

As a preferred embodiment of the present invention, as shown in fig. 1 to 9, the present invention provides a through-long gantry type power-concentrated motor train unit three-dimensional overhaul operation platform for transforming an existing passenger train station, which mainly comprises a contact network cantilever 2, a gantry 3, a protection net 4, a cantilever mounting pillar 5, a rain-proof shed 7, a three-layer operation platform 8, and a two-layer operation platform 9.

As shown in fig. 2, the portal frames 3 span over prepared tracks (e.g. 6 tracks and 7 tracks) of a plurality of strip trenches of an existing passenger company, and the portal frames 3 are sequentially arranged at intervals along the longitudinal direction of the tracks.

As shown in fig. 2-3, the gantry 3 includes gantry columns 31 on both sides and a working frame 32 in the middle. The protective net 4 and the cantilever mounting pillar 5 are arranged below the operation frame 32 and above the middle of an adjacent preparation station track in the portal frame. The contact net cantilevers 2 are arranged on the two transverse sides of the cantilever mounting support 5 and located above the power-concentrated motor train unit 1. The inner sides of the two portal frame upright columns 31 are sequentially provided with the rain-proof shed 7, the three-layer operation platform 8 and the two-layer operation platform 9 from top to bottom, and the left side and the right side of each portal frame upright column are symmetrically distributed in a set; the two-layer operation platform 9 is arranged on the side surfaces of a head train and a tail train of the power-concentrated motor train unit, and the three-layer operation platform 8 is arranged on the side surface of the middle part of the power-concentrated motor train unit.

As shown in fig. 2, a first column of the two gantry columns 31 is disposed between a preparation track with a trench of the existing passenger company and a storage line track (e.g., 8 tracks) without a trench of the existing passenger company. The first upright post is provided with the contact net cantilever 2 towards the outer side of the portal frame and is positioned above the power concentrated motor train unit of the parking line track. The second column of the two gantry columns 31 is arranged between the preparation track with the trench in the gantry of the existing customer service center and the preparation track with the trench (such as 5 tracks) outside the gantry of the existing customer service center. The second upright post is provided with a contact net cantilever 2 towards the outer side of the portal frame and positioned above a power-concentrated motor train unit of a preparation station track with a trench outside the portal frame of the existing passenger station; or the contact net cantilever 2 is not arranged on the second upright column towards the outer side of the portal frame.

The specific structure is described below.

1) Portal frame

As shown in FIG. 4, the integrated operation platform main body adopts a gantry type steel structure, and is stable in structure, safe and reliable. The working frame 32 has left and right upright posts, which are cast on the existing hardened ground by using concrete through a pre-embedding technology. The protective net 4 of the working platform is hung under the main beam of the working frame 32, as shown in fig. 5, and is provided with a mounting interface of a contact net cantilever structure. The inner sides of the two upright posts of the operation frame are provided with operation platforms which are used for the maintainers to check relevant components such as the pantograph, the air conditioner filter screen and the like by climbing the top in the daily servicing operation process. And the outer side of the left upright post of the operation frame is provided with a mounting interface for 8 contact net cantilever structures. The setting position and the setting scheme fully meet the overall process arrangement requirement of the railway locomotive servicing and overhaul.

2) Contact net cantilever

As shown in fig. 6, the catenary cantilever 2 is used for supplying power to the power centralized motor train unit. In one embodiment, the number of the contact network cantilevers 2 is three, the contact network cantilevers are connected and installed on the cantilever installation column 5 and the portal frame 3 through bolts, and power is supplied to three power centralized motor train units on 6 lanes, 7 lanes and 8 lanes respectively. The contact net cantilever structure adopts simple chain type suspension, the suspension type is contact suspension, and the wire combination is JTMM95+ CTA 120.

3) Cantilever mounting upright post

As shown in fig. 7, the cantilever mounting column 5 is mounted on the gantry 3 through a bolt, and meanwhile, a bolt mounting interface is arranged on the cantilever mounting column 5 for connecting and mounting the contact net cantilever 2.

4) Two-layer operation platform

As shown in FIG. 8, the length of the two-layer working platform 9 is 72m, the platform surface elevation of the platform is 1.8m, and steel grating plates are paved on the platform surface. The two-layer operation platform 9 is installed on the portal frame 3 through bolt connection and is located at the head and tail positions of the power centralized motor train unit, both sides of the operation platform are provided for overhauling the head car and the tail car, and related overhauling personnel clean, inspect doors and windows of the locomotive and carry out the internal operation of the locomotive through the two-layer operation platform. As shown in fig. 3, a loading platform 10 is arranged outside the two-layer working platform 9 and between the plurality of portal frames 3 in the longitudinal direction for storing tools, and the loading platform 10 is connected to the portal frames 3 through bolts.

5) Three-layer operation platform

As shown in fig. 8, the three-layer operation platform 8 on both sides is 531m long, the top platform is 4.0m high, a steel grating is laid on the platform, and the three-layer operation platform 8 is installed on the portal frame 3 through bolt connection. As shown in fig. 2 and 5, a full-length safety protection net is arranged on the non-working surface side of the top of the vehicle body, the safety protection net is installed on a connecting beam 41 of a portal frame working frame, and the height of the protection net 4 is 1.1 m; the two ends and the middle of the three-layer operation platform are provided with an up-down crawling ladder for the operator. The three-layer operation platform is used for detecting, cleaning, checking and overhauling the roof equipment by related overhauling personnel. A ladder stand is arranged between the second-layer operation platform 9 and the ground, and an operator can climb the second-layer platform from the ground to operate according to working requirements. A ladder with a safety door is arranged between the three-layer operation platform 8 and the two-layer operation platform 9, and a safety interlocking monitoring system is additionally arranged to ensure the safety of the top climbing operation of maintainers.

6) Rainproof shed

As shown in fig. 9, the weather enclosure 7 is installed on the portal frame 3 through bolted connection, is located directly over the three-layer operation platform, and is mainly used for shielding rain and snow for the three-layer operation platform, so that the outdoor operation of workers is avoided, and the comfort of the operation platform is improved.

The through-length portal frame type power centralized motor train unit three-dimensional overhaul operating platform provided by the invention is used for carrying out electrified net hanging on the in-out line, the out-drawn line and the trench-equipped station track, and is used for finishing locomotive primary servicing, passenger train daily overhaul and the like in the power D1 repair process of a 160-kilometer power centralized motor train unit power vehicle. The manual operation difficulty and the operation time can be effectively shortened. Meanwhile, a safety interlocking monitoring system is added, and the safety of the overhaul personnel in the top climbing operation is guaranteed.

The through-length portal frame type power centralized motor train unit three-dimensional overhaul operating platform comprises a ground one-layer operating platform, a head-tail two-layer operating platform and a through type three-layer operating platform, covers the longest 20 marshalling lengths of the motor train unit at present, can easily perform operations such as inspection on the bottom of a locomotive, oil filling, water filling, sand filling and the like, performs omnibearing three-dimensional cleaning and inspection on doors and windows of the locomotive, the interior of the locomotive and roof equipment, meets the requirement of power centralized motor train unit top-climbing overhaul operation, and greatly improves overhaul efficiency and safety.

The through-length portal frame type power centralized motor train unit three-dimensional overhauling operation platform has the advantages that the main body adopts a portal type steel structure, the structure is stable, and safety and reliability are realized. The top is equipped with the weather enclosure, avoids the outdoor operation of staff, can deal with bad weather such as sleet, has improved operation platform's practicality, travelling comfort.

The through-length portal frame type power centralized motor train unit three-dimensional overhaul operating platform is compact in overall layout structure and small in occupied space, the overhaul channel is arranged by utilizing the upper suspension mode between 6 channels and 7 channels, the space of the overhaul channel between the station tracks is saved, the existing hardened ground can be used for walking the overhaul vehicle, and the overhaul channel and large part transportation overhaul operation requirements are met.

It will be understood by those skilled in the art that the foregoing is only a preferred embodiment of the present invention, and is not intended to limit the invention, and that any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the scope of the present invention.