Construction method for assembling steel bar truss composite floor slab of reinforced concrete frame structure

文档序号:1872599 发布日期:2021-11-23 浏览:24次 中文

阅读说明:本技术 一种用于钢筋混凝土框架结构的钢筋桁架组合楼板装配的施工方法 (Construction method for assembling steel bar truss composite floor slab of reinforced concrete frame structure ) 是由 曾佳 李慧莹 李明 黄亮忠 伍俊锋 王诗铖 李向勇 张伟庭 毛鹏 孔庆娜 于 2021-09-01 设计创作,主要内容包括:本发明公开了一种用于钢筋混凝土框架结构的钢筋桁架组合楼板装配的施工方法,包括应用在钢筋混凝土框架结构中,其结构梁为现浇钢筋混凝土梁,其楼板为钢筋桁架楼承板装配的施工方法,所述施工方法包括满铺脚手架搭设、砼梁底模安装、砼梁钢筋绑扎、砼梁桁架式加强型侧模安装、安装支撑托架、钢筋桁架楼承板封边角钢安装、钢筋桁架楼承板铺设安装、楼板钢筋及附加钢筋绑扎、框架梁和楼板混凝土浇筑施工,通过本发明的施工方法可以满足在钢筋混凝土框架结构中,实现钢筋桁架楼承板的装配式施工,有效响应了国家大力推广的装配式建筑的号召,也提高现场的施工效率,缩短了施工周期,加快施工进度。(The invention discloses a construction method for assembling a steel bar truss combined floor slab for a reinforced concrete frame structure, which comprises the steps of fully laying scaffolds, installing a concrete beam bottom die, binding concrete beam steel bars, installing concrete beam truss type reinforced side dies, installing a support bracket, installing steel bar truss floor bearing plates and edge angle steels, laying and installing the steel bar truss floor bearing plates, binding floor slab steel bars and additional steel bars, and constructing frame beams and floor slab concrete, wherein the construction method comprises the steps of erecting a full-paved scaffold, installing the concrete beam bottom die, binding the concrete beam steel bars, installing the concrete beam truss type reinforced side dies, installing the support bracket, installing the edge angle steels of the steel bar truss floor bearing plates, paving and installing the steel bar truss floor bearing plates, binding the floor slab steel bars and the additional steel bars, and constructing the frame beams and the floor slab concrete, the construction period is shortened, and the construction progress is accelerated.)

1. A construction method for assembling a steel bar truss composite floor slab of a reinforced concrete frame structure is characterized by comprising the following steps of: the construction method comprises the following steps of:

step 1) fully laying scaffolds: calculating a structural support template of the reinforced concrete frame, and building a full-paved scaffold formwork according to a construction drawing;

step 2) mounting a bottom die of the concrete beam: accurately paying off a bottom die of the concrete beam, and laying and installing a bottom formwork of the concrete beam above the erected scaffold;

step 3), binding concrete beam steel bars: binding concrete beam reinforcing steel bars by adopting an in-situ method, and checking and accepting the working procedures;

step 4), mounting a truss type reinforced side form of the concrete beam: the side die is reinforced, in order to prevent the concrete beam side die from deforming to cause slurry explosion when concrete is poured later, and the requirement of bearing the end load of the floor slab transmitted by the steel bar truss floor bearing plate is considered, the method adopted by the reinforcement treatment is that a truss made of wood beams is added outside the side die to reinforce the bearing capacity of the side die so as to resist the pressure of the steel bar concrete side and bear the vertical load of the end of the floor slab;

step 5), mounting a support bracket: the support bracket is arranged above the full-paved scaffold so as to support the steel bar truss floor bearing plate upwards from the middle section below the steel bar truss floor bearing plate after the steel bar truss floor bearing plate is installed, the support bracket commonly bears the dead weight and the construction load of the concrete poured floor, and when the construction is continued upwards, the support bracket assists the steel bar truss floor bearing plate to bear the load transmitted from the upper layer of the steel bar truss floor bearing plate;

step 6), installing edge sealing angle steel of the steel bar truss floor bearing plate: edge sealing angle steel is arranged at the joint position of the steel bar truss floor bearing plate and the reinforced concrete beam, and the edge sealing angle steel is used as a connecting fixed point of the steel bar truss floor bearing plate;

step 7), laying and installing a steel bar truss floor bearing plate: laying and installing a steel bar truss floor bearing plate at a reinforced concrete beam, compacting support steel bars of the steel bar truss floor bearing plate and edge-sealing angle steel, and then welding and fixing the compacted support steel bars and the edge-sealing angle steel so as to ensure that no gap exists between the steel bar truss floor bearing plate and a reinforced concrete beam template to prevent slurry leakage;

step 8) binding of floor slab reinforcing steel bars and additional reinforcing steel bars: binding steel bars and additional steel bars on the steel bar truss floor bearing plate according to the requirements of construction drawings;

step 9), frame beam and floor concrete pouring construction: after the steel bars are concealed and accepted according to the requirements of construction drawings, pouring construction is carried out on the structural beam of the reinforced concrete frame structure, and concrete is poured on the steel bar truss floor bearing plate.

2. The construction method for assembling a steel bar truss composite floor slab for a reinforced concrete frame structure as claimed in claim 1, wherein: in step 4, the truss type reinforced side template comprises a side template and a truss type reinforced batten, the truss type reinforced batten is arranged on the outer side of the side template, the side template is a wood plate with the thickness of 15mm, the truss type reinforced batten is composed of an upper chord, a lower chord and a straight web member, the straight web member is fixed between the upper chord and the lower chord, and the side template and the truss type reinforced batten are both 100x80 battens.

3. The construction method for assembling a steel bar truss composite floor slab for a reinforced concrete frame structure as claimed in claim 1, wherein: in the step 5, the supporting bracket is arranged above the full-spread scaffold and is arranged at a plate span position of one fourth of the steel bar truss floor support plate, the supporting bracket comprises a supporting bottom frame, a supporting upright post and an adjusting bracket, the supporting upright post is arranged between the adjusting bracket and the supporting bottom frame, the bottom end of the adjusting bracket is sleeved at the top of the supporting upright post, the bottom of the supporting upright post is welded with the supporting bottom frame, a jacking batten is fixed at the top end of the adjusting bracket, and the supporting bracket bears the load transmitted from the upper layer of the steel bar truss floor support plate through the jacking batten.

4. The construction method for assembling a steel bar truss composite floor slab for a reinforced concrete frame structure as claimed in claim 3, wherein: the support chassis comprises a support main beam, support secondary beams and anti-overturning connecting rods, the support main beam is respectively arranged on two sides of the support secondary beams and welded, the anti-overturning connecting rods are arranged on one side of the support main beam and welded with the support main beam, a chassis fixing member is arranged below the anti-overturning connecting rods, the anti-overturning connecting rods are fixed above the scaffold through the chassis fixing member, and the support main beam is a through long steel pipe.

5. The construction method for assembling a steel bar truss composite floor slab for a reinforced concrete frame structure as claimed in claim 3, wherein: the support upright post comprises an upright post and a limit cap, the limit cap is connected with the top of the upright post, the limit cap is a special welding assembly, the limit cap is composed of a ring plate and a short tube, the ring plate is welded above the short tube, the thickness of the ring plate is 6mm, and the short tube is a phi 60x4 steel tube.

6. The construction method for assembling a steel bar truss composite floor slab for a reinforced concrete frame structure as claimed in claim 3, wherein: the adjusting bracket comprises an adjusting rod, a rotating mechanism and an anti-overturning limiting device, the rotating mechanism is arranged at the middle of the adjusting rod and is connected with the adjusting rod, the anti-overturning limiting device is arranged below the adjusting rod and the rotating mechanism and is connected with the bottom of the adjusting rod, the top of the adjusting rod is welded with an adjusting jacking, and the rotating mechanism adjusts the height of the adjusting rod to realize height adjustment of the adjusting jacking.

7. The construction method for assembling a steel bar truss composite floor slab for a reinforced concrete frame structure as claimed in claim 6, wherein: the rotating mechanism comprises a regulator and an adjusting switch, the adjusting switch is arranged on the outer side of the regulator and connected with the regulator, and the regulator is adjusted through the adjusting switch.

8. The construction method for assembling a steel bar truss composite floor slab for a reinforced concrete frame structure as claimed in claim 6, wherein: the overturn-preventing limiting device adopts a specially-made round nut so that the overturn-preventing limiting device is assembled and connected with the adjusting rod, the inner diameter of the overturn-preventing limiting device is M30 threads, the outer diameter of the overturn-preventing limiting device is phi 41mm, and the length of the overturn-preventing limiting device is 50 mm.

9. The construction method for assembling a steel bar truss composite floor slab for a reinforced concrete frame structure as claimed in claim 1, wherein: and 6, installing the edge sealing angle steel at the joint position of the steel bar truss floor bearing plate and the reinforced concrete beam, wherein the specification of the edge sealing angle steel is L50x 4.

10. The construction method for assembling a steel bar truss composite floor slab for a reinforced concrete frame structure as claimed in claim 1, wherein: in step 7 the steel bar truss floor support plate includes die block and steel bar truss, the die block is located steel bar truss's below and constitutes a stable support template structure with steel bar truss welding in order to bear concrete placement's dead weight and construction load, the die block adopts the galvanized steel sheet, the thickness of die block is 0.5mm, steel bar truss includes upper chord reinforcing bar and lower chord reinforcing bar, upper chord reinforcing bar and lower chord reinforcing bar are upper and lower parallel arrangement respectively, be provided with the web member reinforcing bar of continuous type between upper chord reinforcing bar and the lower chord reinforcing bar, upper chord reinforcing bar and lower chord reinforcing bar pass through the web member reinforcing bar and weld an organic whole.

Technical Field

The invention relates to the technical field of steel bar truss composite floor slab assembly, in particular to a construction method for assembling a steel bar truss composite floor slab of a reinforced concrete frame structure.

Background

At present, the floor slab in a high-rise building or a floor building system mainly has a cast-in-place concrete floor slab or a steel bar truss floor slab. Traditional floor slab work progress mainly is: in the cast-in-place reinforced concrete frame structure, a scaffold is erected, a steel bar truss floor slab is laid above the scaffold, concrete is poured above the steel bar truss floor slab, and bearing is carried out through the concrete poured on the steel bar truss floor slab and the load transmitted by an upper building.

The traditional construction process of the floor bearing plate has some problems: construction cycle is long, and the efficiency of construction is low, in addition, when steel bar truss floor board need undertake the dead weight and the construction load of pouring floor concrete, steel bar truss floor board bears the ability of load limited, and lacks the support at the middle part of steel bar truss floor board, so steel bar truss floor carrier plate can not undertake the load that the upper strata transmitted, influences the construction and the construction quality of floor, has construction potential safety hazard.

In addition, the traditional construction process does not consider the load support of the end part of the floor slab transmitted by the steel bar truss floor bearing plate, and the mortar explosion is easily caused when concrete is poured.

Therefore, the existing construction process has some defects.

Disclosure of Invention

Aiming at the problems of long construction period, low construction efficiency, limited load bearing capacity of superstructure, influence on construction and construction quality of floors, potential safety hazards of construction, no consideration of floor end load support transmitted by a steel bar truss floor bearing plate, easy slurry explosion and the like in the construction process of a steel bar truss floor slab in the prior art, the technical problem to be solved by the invention is to provide a construction method for assembling a steel bar truss composite floor slab for a steel bar truss frame structure, which can shorten the construction period, improve the construction efficiency, install a support bracket to bear the self weight and the construction load of the concrete of the cast floor slab, assist the floor slab to bear the load transmitted from the upper layer, ensure the construction progress, improve the construction safety, strengthen a side die to bear the end load of the floor slab transmitted by a steel bar truss floor bearing plate and prevent grout explosion caused during the concrete casting.

In order to solve the technical problems, the invention provides a construction method for assembling a steel bar truss composite floor slab of a reinforced concrete frame structure, which comprises the following steps of:

step 1) fully laying scaffolds: calculating a structural support template of the reinforced concrete frame, and building a full-paved scaffold formwork according to a construction drawing;

step 2) mounting a bottom die of the concrete beam: accurately paying off a bottom die of the concrete beam, and laying and installing a bottom formwork of the concrete beam above the erected scaffold;

step 3), binding concrete beam steel bars: binding concrete beam reinforcing steel bars by adopting an in-situ method, and checking and accepting the working procedures;

step 4), mounting a truss type reinforced side form of the concrete beam: the side die is reinforced, in order to prevent the concrete beam side die from deforming to cause slurry explosion when concrete is poured later, and the requirement of bearing the end load of the floor slab transmitted by the steel bar truss floor bearing plate is considered, the method adopted by the reinforcement treatment is that a truss made of wood beams is added outside the side die to reinforce the bearing capacity of the side die so as to resist the pressure of the steel bar concrete side and bear the vertical load of the end of the floor slab;

step 5), mounting a support bracket: the support bracket is arranged above the full-paved scaffold so as to support the steel bar truss floor bearing plate upwards from the middle section below the steel bar truss floor bearing plate after the steel bar truss floor bearing plate is installed, the support bracket commonly bears the dead weight and the construction load of the concrete poured floor, and when the construction is continued upwards, the support bracket assists the steel bar truss floor bearing plate to bear the load transmitted from the upper layer of the steel bar truss floor bearing plate;

step 6), installing edge sealing angle steel of the steel bar truss floor bearing plate: edge sealing angle steel is arranged at the joint position of the steel bar truss floor bearing plate and the reinforced concrete beam, and the edge sealing angle steel is used as a connecting fixed point of the steel bar truss floor bearing plate;

step 7), laying and installing a steel bar truss floor bearing plate: laying and installing a steel bar truss floor bearing plate at a reinforced concrete beam, compacting support steel bars of the steel bar truss floor bearing plate and edge-sealing angle steel, and then welding and fixing the compacted support steel bars and the edge-sealing angle steel so as to ensure that no gap exists between the steel bar truss floor bearing plate and a reinforced concrete beam template to prevent slurry leakage;

step 8) binding of floor slab reinforcing steel bars and additional reinforcing steel bars: binding steel bars and additional steel bars on the steel bar truss floor bearing plate according to the requirements of construction drawings;

step 9), frame beam and floor concrete pouring construction: after the steel bars are concealed and accepted according to the requirements of construction drawings, pouring construction is carried out on the structural beam of the reinforced concrete frame structure, and concrete is poured on the steel bar truss floor bearing plate.

Preferably, step 4 the truss-like strenghthened type side form board includes side form and truss-like reinforcement flitch, the outside of side form is located to the truss-like reinforcement flitch, the side form adopts the plank of 15mm thick, the truss-like reinforcement flitch comprises last quarter, lower chord, straight web member is fixed in between last quarter and the lower chord, the size of side form and truss-like reinforcement flitch is 100x80 flitch.

Preferably, in step 5, the support bracket is installed above the full-spread scaffold and is arranged at a plate span position of one fourth of the steel bar truss floor support plate, the support bracket comprises a support base frame, a support upright post and an adjusting bracket, the support upright post is arranged between the adjusting bracket and the support base frame, the bottom end of the adjusting bracket is sleeved at the top of the support upright post, the bottom of the support upright post is welded with the support base frame, a jacking batten is fixed at the top end of the adjusting bracket, and the support bracket bears the load transmitted from the upper layer of the steel bar truss floor support plate through the jacking batten.

Preferably, the support chassis comprises a support main beam, support secondary beams and an anti-overturning connecting rod, the support main beam is respectively arranged on two sides of the support secondary beams and welded, the anti-overturning connecting rod is arranged on one side of the support main beam and welded with the support main beam, a chassis fixing member is arranged below the anti-overturning connecting rod, the anti-overturning connecting rod is fixed above the scaffold through the chassis fixing member, and the support main beam is a through long steel pipe.

Preferably, the support column comprises an upright column and a limit cap, the limit cap is connected with the top of the upright column, the limit cap is a special welding assembly, the limit cap comprises a ring plate and a short tube, the ring plate is welded above the short tube, the thickness of the ring plate is 6mm, and the short tube is a steel tube with the specification of phi 60x 4.

Preferably, adjust the bracket including adjusting pole, slewing mechanism, the stopper of preventing toppling, slewing mechanism locates the middle part of adjusting the pole and links to each other with adjusting the pole, the stopper of preventing toppling is located the below of adjusting pole and slewing mechanism and is linked to each other with the bottom of adjusting the pole, the top welding of adjusting the pole has the regulation top to hold in the palm, slewing mechanism adjusts the altitude mixture control in order to realize the regulation top to hold in the palm to the height of adjusting the pole.

Preferably, the rotating mechanism comprises a regulator and an adjusting switch, the adjusting switch is arranged on the outer side of the regulator and connected with the regulator, and the regulator is adjusted through the adjusting switch.

Preferably, the overturn prevention limiter adopts a specially-made round nut so that the overturn prevention limiter is in assembly connection with the adjusting rod, the inner diameter of the overturn prevention limiter is M30 threads, the outer diameter of the overturn prevention limiter is phi 41mm, and the length of the overturn prevention limiter is 50 mm.

Preferably, the edge banding angle steel in step 6 is installed at the joint position of the steel bar truss floor support plate and the reinforced concrete beam, and the specification of the edge banding angle steel is L50x 4.

Preferably, in step 7 steel bar truss building carrier plate includes die block and steel bar truss, the die block is located steel bar truss's below and constitutes a stable support template structure in order to bear concrete placement's dead weight and construction load with steel bar truss welding, the die block adopts the galvanized steel sheet, the thickness of die block is 0.5mm, steel bar truss includes last chord steel bar and last chord steel bar, last chord steel bar and last chord steel bar upper and lower parallel arrangement respectively, be provided with the web member reinforcing bar of continuous type between last chord steel bar and the last chord steel bar, last chord steel bar and last chord steel bar pass through the web member reinforcing bar and weld an organic whole.

Compared with the prior art, the scheme of the invention at least comprises the following beneficial effects:

(1) the invention provides a construction method for a reinforced concrete frame structure, which is characterized in that a structural beam adopts a cast-in-place reinforced concrete beam, a floor slab adopts a construction method for assembling a reinforced truss floor bearing plate, the frame structure is a building with the cast-in-place reinforced concrete structure, and the floor slab adopts an assembly type construction process of combining the reinforced truss floor bearing plates, belongs to assembly type addition and division items, and responds to the national development planning requirements on the assembly type building.

(2) The construction method comprises the steps of building full-paved scaffolds, installing a concrete beam bottom die, binding concrete beam steel bars, installing a concrete beam truss type reinforced side die, installing a support bracket, installing edge-sealed angle steel of a steel bar truss floor bearing plate, paving and installing the steel bar truss floor bearing plate, binding floor slab steel bars and additional steel bars, and pouring the frame beam and the floor slab concrete.

(3) The construction method adopts the fully-paved scaffold, when the roof beam and roof slab structure of the layer is constructed, the load transmitted by the concrete beam and roof slab above the top can be supported, the load comprises the self weight and the construction load of the concrete beam and roof slab, the top load is uniformly diffused, the safety of the construction process is ensured, when the construction is continued upwards, the top beam and roof slab structure of the layer which does not reach the age can be assisted by the paved scaffold to bear the load transmitted above, and the bearing capacity of the roof slab concrete structure of the layer is improved.

(4) The invention adopts the truss type reinforced side template in the construction method, prevents the side template from deforming to cause slurry explosion and the like when pouring concrete, the truss type reinforced side template bears the end load of a floor slab transmitted by a reinforced bar truss floor support plate, the truss made of wood beams is added outside the side template through reinforcing the side template, thereby enhancing the bearing capacity of the side template, and the truss type reinforced side template can resist the side pressure of the concrete and bear the vertical load and end support transmitted by the end part of the reinforced bar truss floor support plate while supporting the side pressure load of the reinforced bar concrete beam.

(5) The construction method is characterized in that the support brackets are arranged in the construction method, the support brackets are symmetrically distributed and arranged at the middle section position below the steel bar truss floor bearing plate, the support brackets bear the dead weight of concrete poured on the steel bar truss floor bearing plate and the construction load, and when the construction is continued upwards, the support brackets assist the steel bar truss floor bearing plate which is not up to the age to bear the load transferred from the upper layer.

(6) The support bracket comprises a support chassis, and the support chassis adopts a plane truss, so that the transportation is convenient.

(7) The support bracket comprises the adjusting bracket, the height of the adjusting bracket can be adjusted according to engineering requirements and actual elevation requirements, and the anti-overturning limiting device is arranged on the adjusting bracket, so that the verticality of the adjusting bracket can be ensured.

(8) The steel bar truss floor support plate comprises the bottom die and the steel bar truss, the bottom die and the steel bar truss are welded to form a stable support formwork structure, the floor slab can bear the self weight of concrete and construction load, and the steel bar truss floor support plate can reduce the workload of floor slab site construction and accelerate the construction progress.

(9) According to the invention, the edge sealing angle steel is arranged below the steel bar truss floor bearing plate, and when the vertical support steel bar of the steel bar truss floor bearing plate is welded and fixed with the edge sealing angle steel, the horizontal displacement of the steel bar truss floor bearing plate can be limited, and slurry leakage can be prevented.

Drawings

In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings of the embodiments will be briefly described below.

Fig. 1 is a construction flow chart of a construction method for assembling a steel bar truss composite floor slab for a reinforced concrete frame structure according to the present invention;

fig. 2 is a schematic view of the erection of the scaffolding of the present invention;

figure 3 is a schematic view of the installation of the concrete beam bottom formwork of the present invention;

figure 4 is a schematic view of the binding of the concrete beam reinforcing bars of the present invention;

FIG. 5 is a schematic view showing the installation of the truss-type reinforced side form of the concrete beam of the present invention;

FIG. 6 is a schematic view of the mounting of the support bracket of the present invention;

FIG. 7 is a schematic view of the installation of the edge banding angle steel of the steel bar truss floor deck of the present invention;

FIG. 8 is a schematic view of the installation of the steel bar truss floor deck of the present invention;

FIG. 9 is a schematic view of the floor slab rebar and additional rebar ties of the present invention;

FIG. 10 is a schematic illustration of the construction of the frame beam and floor concrete pour of the present invention;

FIG. 11 is a schematic structural view of a truss-type reinforced side form of the concrete beam of the present invention;

FIG. 12 is a cross-sectional view taken along line A-A of FIG. 11 in accordance with the present invention;

FIG. 13 is a schematic structural view of the support bracket of the present invention;

FIG. 14 is a schematic structural view of the support chassis of the present invention;

FIG. 15 is a schematic structural view of the support column of the present invention;

FIG. 16 is an exploded schematic view of the support column of the present invention;

FIG. 17 is a schematic view of the structure of the adjustment bracket of the present invention;

FIG. 18 is a schematic view of the construction of the rotating mechanism of the present invention;

FIG. 19 is a schematic structural view of the anti-tip over stopper of the present invention;

fig. 20 is a schematic structural view of a steel bar truss floor deck of the present invention;

fig. 21 is a schematic structural view of a steel bar truss in example 1 of the present invention;

fig. 22 is a schematic structural view of a steel truss floor deck according to embodiment 2 of the present invention.

In the figure, a scaffold 1, a concrete beam bottom formwork 2, concrete beam steel bars 3, concrete beam truss reinforced side dies 4, side dies 41, truss reinforced battens 42, upper chords 421, lower chords 422, straight web members 423, support brackets 5, support underframe 51, support main beams 511, support secondary beams 512, anti-overturning connecting rods 513, underframe fasteners 514, support uprights 52, uprights 521, limit caps 522, ring plates 5221, short pipes 5222, adjusting brackets 53, adjusting rods 531, rotating mechanisms 532, adjusters 5321, adjusting switches 5322, anti-overturning limiters 533, adjusting top supports 534, top support battens 54, edge sealing angle steel 6, steel bar truss floor decks 7, bottom moulds 71, steel bar trusses 72, upper chord steel bars 721, lower chord steel bars 722, web member steel bars 723, support steel bars 73, support transverse bars 731 and support vertical steel bars 732 are arranged on a truss frame.

Detailed Description

The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.

The invention provides a construction method for assembling a steel bar truss composite floor slab of a reinforced concrete frame structure, which is mainly applied to the reinforced concrete frame structure, wherein a structural beam of the reinforced concrete frame structure is a cast-in-place reinforced concrete beam, and the floor slab of the reinforced concrete frame structure is assembled by a steel bar truss floor bearing plate 7.

As shown in fig. 1, the construction method for assembling the steel bar truss composite floor slab of the present invention includes the following steps:

step 1) fully laying the scaffold 1: calculating a structural support template of the reinforced concrete frame, and building a formwork of the full-paved scaffold 1 according to a construction drawing;

step 2) mounting a bottom die 712 of the concrete beam: accurately paying off the bottom die 712 of the concrete beam, and laying and installing a bottom template 2 of the concrete beam above the erected scaffold 1;

step 3), binding concrete beam steel bars 3: binding the concrete beam reinforcing steel bars 3 by adopting an in-situ method, and checking and accepting the working procedures;

step 4), installing a truss type reinforced side mold 4 of the concrete beam: the side die 41 is reinforced, in order to prevent the concrete beam side die 41 from deforming to cause slurry explosion when concrete is poured later and to consider the requirement of bearing the end load of the floor slab transmitted by the steel bar truss floor bearing plate 7, the method adopted by the reinforcement treatment is to add a truss made of wood beams outside the side die 41 to strengthen the bearing capacity of the side die 41 so as to resist the pressure of the steel bar concrete side and bear the vertical load of the end of the floor slab;

step 5) mounting the support bracket 5: the support bracket 5 is arranged above the full-paved scaffold 1 so as to support the steel bar truss floor bearing plate 7 from the middle section below the steel bar truss floor bearing plate 7 upwards after the steel bar truss floor bearing plate 7 is installed, the support bracket 5 commonly bears the self weight and the construction load of the poured floor concrete, and the support bracket 5 assists the steel bar truss floor bearing plate 7 to bear the load transferred from the upper layer when the upward construction is continued;

step 6) installing edge sealing angle steel 6 of the steel bar truss floor bearing plate 7: edge banding angle steel 6 is installed at the joint position of the steel bar truss floor support plate 7 and the reinforced concrete beam, and the edge banding angle steel 6 is used as a connecting fixing point of the steel bar truss floor support plate 7;

step 7) laying and installing a steel bar truss floor bearing plate 7: laying and installing a steel bar truss floor bearing plate 7 at a reinforced concrete beam, compacting support steel bars of the steel bar truss floor bearing plate 7 and edge sealing angle steel 6, and then welding and fixing to ensure that no gap exists between the steel bar truss floor bearing plate 7 and a reinforced concrete beam template so as to prevent slurry leakage;

step 8) binding of floor slab reinforcing steel bars and additional reinforcing steel bars: binding steel bars and additional steel bars on the steel bar truss floor bearing plate 7 according to the requirements of construction drawings;

step 9), frame beam and floor concrete pouring construction: after the steel bars are concealed and accepted according to the requirements of construction drawings, pouring construction is carried out on the structural beam of the reinforced concrete frame structure, and concrete is poured on the steel bar truss floor bearing plate 7.

As shown in fig. 2-10, the construction process of the present invention is a corresponding construction schematic diagram, which respectively includes the steps of setting up a full-paved scaffold 1, installing a concrete beam bottom mold, binding concrete beam steel bars 3, installing concrete beam truss type reinforced side molds 4, installing a support bracket 5, installing edge banding angle steel 6 of a steel bar truss floor support plate 7, laying and installing the steel bar truss floor support plate 7, binding floor slab steel bars and additional steel bars, and pouring frame beams and floor slab concrete.

As shown in fig. 11 to 12, in the concrete implementation, the truss-type reinforced side form 41 plate of the present invention includes a side form 41 and a truss-type reinforced batten 42, the truss-type reinforced batten 42 is provided outside the side form 41, the side die 41 is made of wood boards with the thickness of 15mm, the truss type reinforcing batten 42 is composed of an upper chord 421, a lower chord 422 and a straight web member 423, the straight web member 423 is fixed between the upper chord 421 and the lower chord 422, the sizes of the side die 41 and the truss type reinforcing batten 42 are both 100x80 battens, the invention carries out special reinforcing treatment on the side die 41, the bearing capacity of the side mould 41 can be enhanced, the side pressure of concrete can be resisted, the vertical load of the end part of the floor slab can be born, and when the side pressure load of the reinforced concrete beam is supported by the truss type reinforced side mould 41 plate, the vertical load transmitted from the end part of the steel bar truss floor bearing plate 7 can be borne, and the end part of the steel bar truss floor bearing plate 7 can be supported.

In a specific implementation, as shown in fig. 13, the support bracket 5 of the present invention is installed above the full-scale scaffold 1 and at a quarter of a span of the steel bar truss floor deck 7, in a specific implementation, two support brackets 5 are installed on the steel bar truss floor deck 7, a distance between the two support brackets 5 is 1.2m, the support brackets 5 bear a self weight and a construction load of concrete poured into the steel bar truss floor deck 7, and when continuing to perform upward construction, the steel bar truss floor deck 7 which has not reached an age is assisted to bear a load transferred from an upper layer, the support brackets 5 comprise a support chassis 51, a support upright 52 and an adjustment bracket 53, the support upright 52 is arranged between the adjustment bracket 53 and the support chassis 51, the bottom end of the adjustment bracket 53 is sleeved on the top of the support upright 52, the bottom of the support upright 52 is welded to the support chassis 51, the support chassis 51 of the present invention is a plane truss, the plane truss is adopted to facilitate the transportation of the supporting underframe 51 in the construction process, the height of the supporting underframe is adjusted according to engineering requirements and actual elevation requirements by adjusting the bracket 53, the verticality of the adjusting bracket 53 can be ensured by the overturn-preventing limiter 533, the top end of the adjusting bracket 53 is also fixed with the jacking batten 54, and the load transmitted from the upper layer of the steel bar truss floor bearing plate 7 is borne by the jacking batten 54.

As shown in fig. 14, in a specific implementation of the embodiment of the present invention, the supporting underframe 51 includes a supporting main girder 511, supporting secondary girders 512, and an anti-overturning connecting rod 513, the supporting main girder 511 is respectively disposed at two sides of the supporting secondary girders 512 and welded to the supporting secondary girders 512, the anti-overturning connecting rod 513 is disposed at one side of the supporting main girder 511 and welded to the supporting main girder 511, an underframe fixing member 514 is disposed below the anti-overturning connecting rod 513, the anti-overturning connecting rod 513 is fixed above the scaffold 1 by the underframe fixing member 514, in a specific implementation, the underframe fixing member 514 may be a self-tapping screw or a self-tapping screw, the supporting main girder 511 is a through steel pipe so as to support the main girder 511 to exert a supporting force, the cross section of the supporting main girder 511 is a square steel pipe with a specification of 60x80x4mm, the length of the supporting secondary girder 512 is 1200mm, the cross section of the supporting secondary girder 512 is an angle steel with a specification of L50x4, the length of the anti-overturning connecting rod 513 is set to 1200mm, and the section of the anti-overturning connecting rod 513 adopts angle steel with the specification of L50x 4.

As shown in fig. 15 to 16, the support upright 52 of the present invention comprises an upright 521 and a limit cap 522, the limit cap 522 is fixedly connected to the top of the upright 521, in particular, the upright 521 is made of a round steel pipe with a diameter of 50x3, the limit cap 522 is a specially made welding assembly, wherein the limit cap 522 is composed of a ring plate 5221 and a short pipe 5222, the ring plate 5221 is welded above the short pipe 5222, the thickness of the ring plate 5221 is set to be 6mm, and the short pipe 5222 is made of a steel pipe with a diameter of 60x 4.

As shown in fig. 17, the adjusting bracket 53 of the present invention includes an adjusting lever 531, a rotating mechanism 532, and an anti-overturn limiter 533, wherein the rotating mechanism 532 is disposed in the middle of the adjusting lever 531 and connected to the adjusting lever 531, the anti-overturn limiter 533 is disposed below the adjusting lever 531 and the rotating mechanism 532 and connected to the bottom of the adjusting lever 531, an adjusting top bracket 534 is welded to the top of the adjusting lever 531, the height of the adjusting lever 531 is adjusted by the rotating mechanism 532, so as to adjust the height of the adjusting top bracket 534, in particular, when the adjusting lever 531 is implemented, a screw rod with a specification of M30 is used, and the adjusting top bracket 534 is a channel steel with a specification of [14 ].

As shown in fig. 18, in a specific implementation of the embodiment of the present invention, the rotating mechanism 532 includes an adjuster 5321 and an adjusting switch 5322, the adjusting switch 5322 is disposed outside the adjuster 5321 and connected to the adjuster 5321, the adjuster 5321 is adjusted by the adjusting switch 5322, in the specific implementation, the adjuster 5321 adopts an adjusting nut, and selects an M30 nut, the adjusting switch 5322 adopts an adjusting handle, the adjusting handle adopts a round steel of phi 4, the adjuster 5321 and the adjusting switch 5322 are fixed by welding, an adjusting thread matched with the adjusting nut is disposed on an outer surface of the adjusting rod 531, and the adjusting nut is matched with the adjusting thread of the adjusting rod 531, so as to adjust the height of the adjusting rod 531.

As shown in fig. 19, the overturn-preventing stopper 533 of the present invention employs a specially-made round nut for facilitating the assembling connection of the overturn-preventing stopper 533 and the adjusting rod 531, the inner diameter of the overturn-preventing stopper 533 is set to be M30 threads, the outer diameter thereof is phi 41mm, and the length thereof is 50 mm.

According to the invention, the edge banding angle steel 6 is arranged at the joint position of the steel bar truss floor bearing plate 7 and the reinforced concrete beam, and the edge banding angle steel 6 adopts the angle steel with the specification of L50x 4.

As shown in fig. 20, in the embodiment of the present invention, in the concrete implementation, the floor slab support plate 7 of the steel bar truss includes a bottom mold 71 and a steel bar truss 72, the bottom mold 71 is disposed below the steel bar truss 72, in the concrete implementation, the bottom mold 71 and three steel bar trusses 72 are welded to form a stable support formwork structure, the support formwork structure is used to bear the self weight of the floor slab concrete and the construction load, the floor slab construction workload can be reduced by using the floor slab support plate 7 of the steel bar truss, the construction progress can be accelerated, the bottom mold 71 is made of galvanized steel plate, the thickness of the bottom mold 71 is set to be 0.5mm, and the yield strength of the bottom mold 71 is not lower than 260N/mm2The total galvanizing amount of both sides is not less than 120g/m2The steel bar truss 72 comprises an upper chord steel bar 721 and a lower chord steel bar 722, the upper chord steel bar 721 and the lower chord steel bar 722 are respectively arranged in an upper and a lower parallel mode, a continuous web member steel bar 723 is arranged between the upper chord steel bar 721 and the lower chord steel bar 722, the steel bar truss 72 is convenient to manufacture, the upper chord steel bar 721 and the lower chord steel bar 722 are welded into a whole through the web member steel bar 723, the cross section of the upper chord main steel bar and the lower chord main steel bar welded through the web member steel bar 723 is of a triangular structure, the steel bar truss 72 designed in the mode is stable in structure, and in specific implementation, the upper chord steel bar 721 and the lower chord steel bar 722 are welded into a whole through the web member steel bar 723The chord reinforcing steel bars 721 and the lower chord reinforcing steel bars 722 adopt HRB400 hot-rolled ribbed reinforcing steel bars, and the web member reinforcing steel bars 723 adopt HPB300 cold-rolled reinforcing steel bars with the same performance.

Example 1:

as shown in fig. 21, the steel bar truss floor slab 7 of the present invention includes a bottom mold 71 and a steel bar truss 72, the bottom mold 71 is welded to the steel bar truss 72, the steel bar truss 72 includes an upper chord steel bar 721 and a lower chord steel bar 722, the upper chord steel bar 721 and the lower chord steel bar 722 are also arranged in parallel, a web member steel bar 723 arranged between the upper chord steel bar 721 and the lower chord steel bar 722 is a discontinuous web member steel bar 723, and the discontinuous web member steel bar 723 is designed to save steel bar materials and reduce cost.

Example 2:

as shown in fig. 22, the steel bar truss floor deck 7 of the present invention includes support steel bars 73, the support steel bars 73 include support transverse bars 731 and support vertical bars 732, and the support transverse bars 731 and the support vertical bars 732 are welded to each other.

The above disclosure is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the scope of the present invention, therefore, the present invention is not limited by the appended claims.

27页详细技术资料下载
上一篇:一种医用注射器针头装配设备
下一篇:一种装配式建筑屋面结构及其施工方法

网友询问留言

已有0条留言

还没有人留言评论。精彩留言会获得点赞!

精彩留言,会给你点赞!