Engineering material conveying device

文档序号:1915038 发布日期:2021-12-03 浏览:13次 中文

阅读说明:本技术 一种工程物料传送装置 (Engineering material conveying device ) 是由 崔晓 于 2021-11-08 设计创作,主要内容包括:本发明公开了一种工程物料传送装置,包括控制箱,所述控制箱内壁左侧固定安装有电机,所述电机输出端固定连接有丝杆,且丝杆右端通过轴承与控制箱内壁转动连接,所述丝杆表面螺纹连接有螺纹套。在使用中实现了便于对工程物料进行快速传送的效果,相对于人工搬运有效提升了物料传送效率,能够对较大质量的物料进行持续传送,同时也避免了施工人员搬运物料过程中持续沾染灰尘而危害身心健康,有效防止了物料在传送过程中发生晃动,避免了物料传送过程中发生坠落的情况,相较于现有的传送带输送更加安全、稳定,达到了便于对物料传送高度进行调节的效果,便于对墙面施工中不同高度进行物料传送,使得装置使用起来更加灵活。(The invention discloses an engineering material conveying device which comprises a control box, wherein a motor is fixedly installed on the left side of the inner wall of the control box, a lead screw is fixedly connected to the output end of the motor, the right end of the lead screw is rotatably connected with the inner wall of the control box through a bearing, and a threaded sleeve is in threaded connection with the surface of the lead screw. In use has realized being convenient for carry out the effect of quick conveying to engineering material, material conveying efficiency has effectively been promoted for artifical transport, can last the conveying to the material of great quality, constructor's transport material in-process has also been avoided simultaneously and has lasted to be infected with the dust and endanger physical and mental health, the material has effectively been prevented to take place to rock in the data send process, the condition of falling takes place in having avoided the material data send process, it is safer to compare in current conveyer belt transport, it is stable, the effect of being convenient for highly adjust the material conveying has been reached, be convenient for carry out the material conveying to different heights in the wall construction, make the device use more nimble.)

1. An engineering material conveying device comprises a placing box (11) used for loading materials, and is characterized in that a limiting mechanism used for limiting the materials is installed on the placing box (11), the placing box (11) is installed at the top of a control box (1) in a sliding mode through a connecting mechanism, a driving mechanism used for driving the connecting mechanism and the placing box (11) to move along the length direction of the control box (1) is installed in the control box (1), and a lifting mechanism used for driving the control box (1) to lift is installed at the bottom of the control box (1); the driving mechanism comprises a motor (2) fixedly arranged on the inner wall of the left side of the control box (1), the output end of the motor (2) is fixedly connected with a screw rod (3), the right end of the screw rod (3) is rotationally connected with the inner wall of the control box (1) through a bearing, the surface of the screw rod (3) is in threaded connection with a threaded sleeve (4), the surface of the threaded sleeve (4) is fixedly connected with a first connecting column (5), the end part of the first connecting column (5) is fixedly connected with a sliding sleeve (6), the inner wall of the sliding sleeve (6) is connected with a sliding column (7) in a sliding way, both ends of the sliding column (7) are fixedly connected with the inner wall of the control box (1), the bottom of the threaded sleeve (4) is provided with a second connecting column (8), the bottom of the second connecting column (8) is connected with the connecting mechanism, the bottom surface of the control box (1) is provided with an extending groove (19) in a through way, and the inner wall of the extending groove (19) is in sliding connection with the surface of the second connecting column (8).

2. The engineering material conveying device according to claim 1, characterized in that the placing box (11) comprises a box body (1101), the bottom of the box body (1101) is connected with the connecting mechanism, the limiting mechanism comprises a threaded hole (1102) formed in the front side wall of the box body (1101) in a penetrating mode, a threaded column (1103) is in threaded connection with the inner wall of the threaded hole (1102), a crank (1104) is fixedly connected to the front end of the threaded column (1103), a clamping plate (1105) is rotatably connected to the rear end of the threaded column (1103), and a clamping pad (1106) is fixedly connected to the back of the clamping plate (1105).

3. The engineering material conveying device according to claim 1, characterized in that the connecting mechanism comprises a C-shaped supporting frame (9), the top of the supporting frame (9) is connected with a placing box (11), the bottom of the supporting frame is connected with a second connecting column (8), sliding blocks (10) are fixedly connected to the left side and the right side of the inner wall of the supporting frame (9), a sliding groove (12) is formed in the side surface of the control box (1), and the inner wall of the sliding groove (12) is in surface sliding connection with the sliding blocks (10).

4. The engineering material conveying device according to claim 1, wherein the lifting mechanism comprises a first supporting seat (15) hinged to the right side of the bottom surface of the control box (1), and a second supporting seat (16) arranged on the left side of the bottom surface of the control box (1), the second supporting seat (16) comprises a hinged frame (1601), the surface of the hinged frame (1601) is hinged to the bottom surface of the control box (1), the surface of the hinged frame (1601) is slidably connected with a supporting seat body (1602), the right side surface and the top surface of the supporting seat body (1602) are both in an open state, an electric push rod (1603) is hinged to the bottom surface of the inner wall of the supporting seat body (1602), and the top of the output end of the electric push rod (1603) is fixedly connected with the bottom of the hinged frame (1601).

5. The engineering material conveying device according to claim 2, wherein the bottom of the box body (1101) is provided with a roller (13), the top surface of the control box (1) is provided with a rolling groove (14), and the surface of the roller (13) is rotatably connected with the inner wall of the rolling groove (14).

6. The engineering material conveying device according to claim 5, wherein the number of the rolling grooves (14) is two, the two rolling grooves (14) are respectively arranged on the left side of the top surface of the control box (1) and the right side of the top surface of the control box (1), and the number of the rollers (13) is four.

7. A working material transfer device according to claim 4, characterized in that the number of the electric push rods (1603) is two, and the two electric push rods (1603) are respectively located on the left side of the bottom surface of the hinge frame (1601) and on the right side of the bottom surface of the hinge frame (1601).

8. The engineering material conveying device according to claim 4, wherein the first supporting seat (15) and the supporting seat body (1602) are fixedly connected with non-slip mats (17) on the bottom surfaces, and the non-slip mats (17) are provided with non-slip grooves (18) on the bottom surfaces.

9. The device for conveying construction materials according to claim 2, wherein the clamping pad (1106) is made of natural rubber.

Technical Field

The invention relates to the technical field of conveying devices, in particular to an engineering material conveying device.

Background

The building engineering refers to an engineering entity formed by the construction of various building constructions and their auxiliary facilities and the installation of lines, pipes and equipment matched with them. The house building is characterized by comprising a top cover, a beam column, a wall, a foundation and a project which can form an internal space and meet the requirements of production, living, study and public activities of people.

In-process to the wall construction, need convey a large amount of building materials to the height of using from ground to satisfy the demand to the material in the work progress. In the current material conveying process, most of materials are conveyed manually by building workers, when the mass of the materials to be conveyed is slightly larger, the materials are time-consuming and labor-consuming to convey, the efficiency is low, long-time continuous transmission is difficult to carry out, and dust attached to the building materials is easy to cause harm to the health of the conveyers; in the scene of partial wall construction, adopt conveyer belt or jib to convey the material, however the conveyer belt lacks limit structure, is difficult to effectively spacing to the material, takes place to rock easily among the material data send process or drop, causes material damage or incident to ordinary conveyer belt is difficult to highly adjusting the transmission, and the use is very inflexible, and the practicality is relatively poor.

Disclosure of Invention

In view of the defects of the prior art, the invention provides an engineering material conveying device, which solves the problems mentioned in the background technology.

In order to achieve the purpose, the invention adopts the following technical scheme:

an engineering material conveying device comprises a placing box for loading materials, and is characterized in that a limiting mechanism for limiting the materials is mounted on the placing box, the placing box is slidably mounted at the top of a control box through a connecting mechanism, a driving mechanism for driving the connecting mechanism and the placing box to move along the length direction of the control box is mounted in the control box, and a lifting mechanism for driving the control box to lift is mounted at the bottom of the control box; the driving mechanism comprises a motor fixedly arranged on the inner wall of the left side of the control box, the output end of the motor is fixedly connected with a lead screw, the right end of the lead screw is rotatably connected with the inner wall of the control box through a bearing, the surface of the lead screw is in threaded connection with a threaded sleeve, the surface of the threaded sleeve is fixedly connected with a first connecting column, the end part of the first connecting column is fixedly connected with a sliding sleeve, the inner wall of the sliding sleeve is in sliding connection with a sliding column, two ends of the sliding column are fixedly connected with the inner wall of the control box, the bottom of the threaded sleeve is provided with a second connecting column, the bottom of the second connecting column is connected with the connecting mechanism, the bottom surface of the control box is provided with an extending groove in a penetrating way, and the inner wall of the extending groove is in sliding connection with the surface of the second connecting column;

preferably, the placing box comprises a box body, the bottom of the box body is connected with the connecting mechanism, the limiting mechanism comprises a threaded hole which is formed in the front side wall of the box body in a penetrating mode, a threaded column is connected to the inner wall of the threaded hole in a threaded mode, a crank is fixedly connected to the front end of the threaded column, a clamping plate is rotatably connected to the rear end of the threaded column, and a clamping pad is fixedly connected to the back face of the clamping plate;

preferably, the connecting mechanism comprises a C-shaped support frame, the top of the support frame is connected with the placing box, the bottom of the support frame is connected with the second connecting column, the left side and the right side of the inner wall of the support frame are both fixedly connected with sliding blocks, the side surface of the control box is provided with a sliding groove, and the inner wall of the sliding groove is in sliding connection with the surface of the sliding block;

preferably, the lifting mechanism comprises a first supporting seat hinged with the right side of the bottom surface of the control box and a second supporting seat arranged on the left side of the bottom surface of the control box, the second supporting seat comprises a hinged frame, the surface of the hinged frame is hinged with the bottom surface of the control box, the surface of the hinged frame is connected with a supporting seat body in a sliding mode, the right side surface and the top surface of the supporting seat body are both in an open state, an electric push rod is hinged to the bottom surface of the inner wall of the supporting seat body, and the top of the output end of the electric push rod is fixedly connected with the bottom of the hinged frame;

preferably, the bottom of the box body is provided with a roller, the top surface of the control box is provided with a rolling groove, and the surface of the roller is rotationally connected with the inner wall of the rolling groove.

Preferably, the number of the rolling grooves is two, the two rolling grooves are respectively positioned on the left side of the top surface of the control box and the right side of the top surface of the control box, and the number of the rollers is four;

preferably, the number of the electric push rods is two, and the two groups of electric push rods are respectively positioned on the left side of the bottom surface of the hinge frame and the right side of the bottom surface of the hinge frame;

preferably, the bottom surfaces of the first supporting seat and the supporting seat body are fixedly connected with anti-slip pads, and anti-slip grooves are formed in the bottom surfaces of the anti-slip pads;

preferably, the clamping pad is made of natural rubber.

Compared with the prior art, the invention has the beneficial effects that:

1. this engineering material conveyer, motor drive lead screw through actuating mechanism rotates, thereby it removes to drive the thread bush, the thread bush drives the second spliced pole, the support frame slides with placing the box, thereby convey placing in the inside material of box body, in use has realized being convenient for carry out the effect of quick conveying to engineering material, effectively promoted material conveying efficiency for artifical transport, can last the conveying to the material of great quality, also avoided constructor transport material in-process to last to be infected with the dust and endanger physical and mental health simultaneously.

2. This engineering material conveyer is equipped with material stop gear, through rotating the crank, thereby drive the screw thread post at the inside precession of screw hole, thereby promote the clamp plate and press from both sides tight pad and remove, make press from both sides tight pad and touch the material surface, the cooperation box body carries on spacingly to the material, has prevented effectively that the material from taking place to rock in the data send process, has avoided taking place the condition of falling among the material data send process, compares in current conveyer belt or jib transport safer, stable.

3. This engineering material conveyer is equipped with elevating system, it rises to articulate the frame through electric putter drive, because the control box is articulated the setting with articulated frame and first supporting seat, thereby it rotates round first supporting seat to drive the control box, thereby change the control box conveying height, thereby reached and be convenient for carry out the effect of adjusting to the material conveying height, be convenient for carry out the material conveying to different heights in the wall construction, make the device use more nimble.

Drawings

FIG. 1 is a front view of the structure of the present invention;

FIG. 2 is a sectional plan view of the structure of the present invention;

FIG. 3 is a side view of the structure of the present invention;

FIG. 4 is a side cross-sectional view of the structure of the present invention;

FIG. 5 is a schematic view of the non-slip mat of the present invention;

FIG. 6 is a side cross-sectional view of a second support structure of the present invention.

In the figure: the automatic control device comprises a control box 1, a motor 2, a lead screw 3, a thread bushing 4, a first connecting column 5, a sliding sleeve 6, a sliding column 7, a second connecting column 8, a supporting frame 9, a sliding block 10, a placing box 11, a box 1101, a threaded hole 1102, a threaded column 1103, a crank 1104, a clamping plate 1105, a clamping pad 1106, a sliding chute 12, a roller 13, a rolling chute 14, a first supporting seat 15, a second supporting seat 16, a hinged frame 1601, a supporting seat body 1602, an electric push rod 1603, an anti-slip pad 17, an anti-slip chute 18 and an extension groove 19.

Detailed Description

The technical scheme of the embodiment of the invention is clearly and completely described below by combining the attached drawings.

Example (b): referring to fig. 1-6, an engineering material conveying device comprises a control box 1, a motor 2 is fixedly installed on the left side of the inner wall of the control box 1, a screw rod 3 is fixedly connected to the output end of the motor 2, the right end of the screw rod 3 is rotatably connected with the inner wall of the control box 1 through a bearing, a threaded sleeve 4 is in threaded connection with the surface of the screw rod 3, a first connecting column 5 is fixedly connected with the surface of the threaded sleeve 4, a sliding sleeve 6 is fixedly connected to the end part of the first connecting column 5, a sliding column 7 is in sliding connection with the inner wall of the sliding sleeve 6, both ends of the sliding column 7 are fixedly connected with the inner wall of the control box 1, a second connecting column 8 is fixedly connected to the bottom surface of the screw rod 3, an extending groove 19 is formed in the bottom surface of the control box 1 in a penetrating manner, the inner wall of the extending groove 19 is in sliding connection with the surface of the second connecting column 8, a support frame 9 is fixedly connected to the bottom of the second connecting column 8, the support frame 9 is of a C-shaped structure, and the inner wall of the support frame 9 is in sliding connection with the surface of the control box 1, the left side and the right side of the inner wall of the support frame 9 are fixedly connected with sliders 10, the side of the control box 1 is provided with a chute 12, the inner wall of the chute 12 is in sliding connection with the surface of the slider 10, the support frame 9 is more stable and prevented from shaking in the moving process by arranging the chute 12 to be matched with the slider 10, the top of the support frame 9 is fixedly connected with a placing box 11, the placing box 11 comprises a box body 1101, the bottom of the box body 1101 is fixedly connected with the top of the support frame 9, rollers 13 are arranged at the bottom of the box body 1101, the top surface of the control box 1 is provided with rolling grooves 14, the surfaces of the rollers 13 are in rotating connection with the inner walls of the rolling grooves 14, the number of the rolling grooves 14 is two, the two rolling grooves 14 are respectively positioned at the left side of the top surface of the control box 1 and at the right side of the top surface of the control box 1, the rollers 13 are four groups, and the four groups of rollers 13 are matched with the two rolling grooves 14, so that the box body 1101 is more stable in the moving process, the material conveying process is more stable, a threaded hole 1102 is formed in the front side wall of the box body 1101 in a penetrating mode, a threaded column 1103 is connected to the inner wall of the threaded hole 1102 in a threaded mode, a crank 1104 is fixedly connected to the front end of the threaded column 1103, a clamping plate 1105 is rotatably connected to the rear end of the threaded column 1103, a clamping pad 1106 is fixedly connected to the back side of the clamping plate 1105, the clamping pad 1106 is made of natural rubber, the material surface is pressed more tightly through the clamping pad 1106 made of natural rubber, the material conveying process is more stable, a first supporting seat 15 is hinged to the right side of the bottom surface of the control box 1, a second supporting seat 16 is arranged on the left side of the bottom surface of the control box 1, the second supporting seat 16 comprises a hinged frame 1601, the surface of the hinged frame 1601 is hinged to the bottom surface of the control box 1, a supporting seat body 1602 is connected to the surface of the hinged frame 1601 in a sliding mode, the right side surface and the top surface of the supporting seat body 1602 are both in an open state, anti-slip pad 17 is fixedly connected to the bottom surfaces of the first supporting seat 15 and the supporting seat body 1602, non-slip groove 18 has been seted up to slipmat 17 bottom surface, through setting up slipmat 17 and non-slip groove 18, the frictional force between device and ground has been increased, it is more stable when making the device place, supporting seat body 1602 inner wall bottom surface articulates installs electric putter 1603, and electric putter 1603 output top and articulated frame 1601 bottom fixed connection, the quantity of electric putter 1603 is two sets of, and two sets of electric putter 1603 is located articulated frame 1601 bottom surface left side and articulated frame bottom surface right side respectively, through setting up two sets of electric putter 1603, make the support to articulated frame 1601 more stable, the stability of structure has been promoted. The engineering material conveying device drives the screw rod 3 to rotate through the motor 2, so as to drive the threaded sleeve 4 to move, the threaded sleeve 4 drives the second connecting column 8, the supporting frame 9 and the placing box 11 to slide, so as to convey materials placed in the box body 1101, the effect of facilitating quick conveying of engineering materials is realized in use, the material conveying efficiency is effectively improved compared with manual conveying, materials with larger mass can be continuously conveyed, meanwhile, the situation that constructors are continuously infected with dust and harm physical and mental health in the material conveying process is avoided, the threaded column 1103 is driven to screw in the threaded hole 1102 by rotating the crank 1104, so that the clamping plate 1105 and the clamping pad 1106 are pushed to move, the surface of the materials is touched by the clamping pad 1106, the materials are limited by matching with the box body 1101, the materials are effectively prevented from shaking in the conveying process, and the falling condition in the material conveying process is avoided, compare in current conveyer belt transport safer, stable, it is ascending through electric putter 1603 drive articulated frame 1601, because control box 1 is articulated the setting with articulated frame 1601 and first supporting seat 15, thereby it rotates round first supporting seat 15 to drive control box 1, thereby change 1 conveying height of control box, thereby reached and be convenient for carry out the effect of adjusting to material conveying height, be convenient for carry out the material conveying to different heights in the wall construction, make the device use more nimble.

When in use: the material is placed in the box body 1101, the crank 1104 is rotated to drive the threaded column 1103 to screw in the threaded hole 1102, so that the clamping plate 1105 and the clamping pad 1106 are pushed to move, the clamping pad 1106 is pressed against the surface of the material, the material is limited by matching with the box body 1101, the screw rod 3 is driven to rotate by the motor 2, so that the threaded sleeve 4 is driven to move, the threaded sleeve 4 drives the first connecting column 5 to move, the first connecting column 5 drives the sliding sleeve 6 to slide along the surface of the sliding column 7, the threaded sleeve 4 drives the supporting frame 9 to slide along the surface of the control box 1, the supporting frame 9 drives the sliding block 10 to slide along the inner wall of the sliding groove 12, the supporting frame 9 drives the placing box 11 to slide, so that the material placed in the box body 1101 is conveyed, when the conveying height needs to be adjusted, the hinge frame 1601 is driven to ascend by the electric push rod 1603, and the control box 1, the hinge frame 1601 and the first supporting seat 15 are hinged, thereby driving the control box 1 to rotate around the first supporting seat 15, thereby changing the height of one end of the control box 1 and adjusting the conveying height.

To sum up, the engineering material conveying device drives the screw rod 3 to rotate through the motor 2, so as to drive the threaded sleeve 4 to move, the threaded sleeve 4 drives the second connecting column 8, the supporting frame 9 and the placing box 11 to slide, so as to convey materials placed inside the box body 1101, an effect of facilitating quick conveying of engineering materials is realized in use, the material conveying efficiency is effectively improved relative to manual conveying, materials with large mass can be continuously conveyed, meanwhile, the situation that constructors are continuously infected with dust to harm physical and mental health in the material conveying process is avoided, the threaded column 1103 is driven to screw in the threaded hole 1102 by rotating the crank 1104, the clamping plate 1105 and the clamping pad 1106 are pushed to move, the clamping pad 1106 is enabled to touch the surface of the materials, the materials are limited by matching with the box body 1101, and the materials are effectively prevented from shaking in the conveying process, avoided the condition that takes place to fall among the material transfer process, it is safer to compare in current conveyer belt or jib transport, it is stable, it rises through electric putter 1603 drive articulated frame 1601, because control box 1 is articulated the setting with articulated frame 1601 and first supporting seat 15, thereby it rotates round first supporting seat 15 to drive control box 1, thereby change 1 transfer height of control box, thereby reached and be convenient for carry out the effect of adjusting to the material transfer height, be convenient for carry out the material conveying to different heights in the wall construction, make the device use more nimble.

It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.

Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.