阅读说明:本技术 一种模块化装配式集中登机舱 (Modularization assembled concentrates and steps on cabin ) 是由 田韧 李葱 刘涌 孙万彪 张良 王晖 胡少华 阚博文 郑芳蒙 尹卫丰 张咪 张 于 2021-07-29 设计创作,主要内容包括:本发明公开了一种模块化装配式集中登机舱,包括托架基础和设置在托架基础顶部的主体舱体,所述托架基础设置有若干组,所述托架基础包括托架基座、立柱、横梁和楼板系统;所述主体舱体连接有至少十组连廊登机区,所述主体舱体内部设有候机厅、卫生间模组、商铺模组、机电模组A、机电模组B、标准模组和屋面系统;本发明根据现有需求进行设计,集中解决远机位登机,可满足10个机位停靠,结构主体采用托架系统,不破坏现有的道面及下部管线,登机区高度低,安装登机桥后可对接国产ARJ飞机,解决ARJ飞机集中运行保障问题,可同时满足各类飞机使用,可同时运行多架飞机,可增加机场近机位比例。(The invention discloses a modularized assembled centralized boarding cabin, which comprises a bracket foundation and a main cabin body arranged at the top of the bracket foundation, wherein the bracket foundation is provided with a plurality of groups, and the bracket foundation comprises a bracket base, stand columns, cross beams and a floor system; the main cabin body is connected with at least ten groups of corridor boarding areas, and a waiting hall, a toilet module, a shop module, an electromechanical module A, an electromechanical module B, a standard module and a roof system are arranged in the main cabin body; the invention is designed according to the existing requirements, intensively solves the problem of boarding at a far airplane station, can meet the stop of 10 airplane stations, adopts a bracket system as a structural main body, does not damage the existing road surface and lower pipelines, has low boarding area height, can be butted with a domestic ARJ airplane after a boarding bridge is installed, solves the problem of ensuring the centralized operation of ARJ airplanes, can simultaneously meet the use requirements of various airplanes, can simultaneously operate a plurality of airplanes, and can increase the proportion of near airplane stations at an airport.)

1. The utility model provides a cabin is stepped on in modularization assembled is concentrated, includes bracket basis (1) and sets up main part cabin body (2) at bracket basis (1) top, its characterized in that: the bracket foundation (1) is provided with a plurality of groups, and the bracket foundation (1) comprises a bracket base, upright posts, cross beams and a floor system;

the main cabin body (2) is connected with at least ten groups of corridor boarding areas (3), and a waiting hall, a toilet module (4), a shop module (5), an electromechanical module A (6), an electromechanical module B (7), a standard module (8) and a roof system (9) are arranged in the main cabin body (2);

the inlet end of the main body cabin body (2) is connected with an inlet escalator and a steel step module (10), and the outlet end of the main body cabin body (2) is connected with an outlet escalator and a steel step module (11);

and a boarding corridor connecting waiting hall and a boarding bridge movable end are arranged on the platform foundation of the connecting corridor boarding area (3).

2. The modular assembled centralized boarding cabin of claim 1, characterized in that: still be provided with fire pump room module and electricity distribution room module in the main part cabin body (2).

3. The modular assembled centralized boarding cabin of claim 1, characterized in that: different the bracket base is respectively provided with a fire water tank, an air conditioner external unit and a waste recycling tank.

4. The modular assembled centralized boarding cabin of claim 1, characterized in that: the two sides of the waiting hall are provided with a toilet module (4), a shop module (5) and a standard module (8).

5. The modular assembled centralized boarding cabin of claim 1, characterized in that: bathroom module (4), shop module (5) and standard module (8) set up in the cabin body module in main part cabin body (2), electromechanical module A (6) and electromechanical module B (7) are all installed at cabin body module top, roofing system (9) set up in electromechanical module A (6) and electromechanical module B (7) keep away from one side of cabin body module.

6. The modular assembled centralized boarding cabin of claim 1, characterized in that: an entrance ramp (12) and an entrance elevator (13) are arranged on one side of the entrance escalator and steel step module (10), and the entrance elevator (13) is connected with a first-layer entrance and a second-layer waiting hall.

7. The modular assembled centralized boarding cabin of claim 1, characterized in that: an exit ramp (14) and an exit elevator (15) are arranged on one side of the exit escalator and steel step module (11), and the exit elevator (15) is connected with a first-layer exit and a second-layer waiting hall.

8. The modular assembled centralized boarding cabin of claim 1, characterized in that: the evacuation steel ladder is connected to the boarding corridor, and a rain shed is arranged at one end of the boarding corridor.

Technical Field

The invention relates to the technical field of equipment for airports, in particular to a modular assembly type centralized boarding cabin.

Background

The boarding bridge is a movable lifting channel used for connecting a waiting hall and an airplane in an airport, one end of the boarding bridge is connected with a certain boarding gate of the waiting hall, the other end of the boarding bridge is connected with a cabin door of the airplane in a buckled mode, and passengers enter the airplane through the boarding bridge from the corresponding boarding gate.

The prior patent publication No. CN 212556842U discloses a modular boarding island, which realizes the boarding convenience of passengers by arranging an accessible elevator and an escalator in the boarding island. The passenger queuing channel is arranged on the second layer of the boarding island, so that the boarding convenience and safety of passengers are realized. A rain shed area is arranged at the front part of the boarding island and can be used as a passenger waiting area in rainy and snowy weather.

However, the above technical solutions have the following disadvantages: 1. only can solve the problem of boarding at a single machine position, and cannot simultaneously meet the requirement of boarding at a plurality of machine positions. 2. Each machine position needs to be provided with an elevator staircase, which causes resource waste. 3. The passenger does not set a waiting function, and the passenger must pass through the waiting function quickly and cannot stay for a long time.

In view of the above problems, a modular assembly type centralized boarding cabin is now proposed.

Disclosure of Invention

The invention aims to provide a modular assembled centralized boarding cabin to solve the problems in the prior art.

In order to achieve the purpose, the invention provides the following technical scheme:

a modular assembly type centralized boarding cabin comprises a bracket foundation and a main cabin body arranged at the top of the bracket foundation, wherein the bracket foundation is provided with a plurality of groups and comprises a bracket base, stand columns, cross beams and a floor system;

the main cabin body is connected with at least ten groups of corridor boarding areas, and a waiting hall, a toilet module, a shop module, an electromechanical module A, an electromechanical module B, a standard module and a roof system are arranged in the main cabin body;

the inlet end of the main body cabin body is connected with an inlet escalator and a steel step ladder module, and the outlet end of the main body cabin body is connected with an outlet escalator and a steel step ladder module;

and a boarding corridor is arranged on the platform foundation of the connecting corridor boarding area and is connected with a waiting hall and a boarding bridge movable end.

Preferably, a fire pump room module and a power distribution room module are further arranged in the main body cabin.

Preferably, different bracket bases are respectively provided with a fire water tank, an air conditioner external unit and a waste recycling tank.

Preferably, the two sides of the waiting hall are provided with a toilet module, a shop module and a standard module.

Preferably, bathroom module, shop module and standard module set up in the internal cabin body module in main part cabin, electromechanical module A and electromechanical module B are all installed at cabin body module top, roofing system sets up the one side of keeping away from cabin body module at electromechanical module A and electromechanical module B.

Preferably, an entrance ramp and an entrance elevator are arranged on one side of the entrance escalator and the steel step module, and the entrance elevator is connected with the first-layer entrance and the second-layer waiting hall.

Preferably, an exit ramp and an exit elevator are arranged on one side of the exit escalator and the steel step ladder module, and the exit elevator is connected with a first-layer exit and a second-layer waiting hall.

Preferably, the place of the airstairs is connected with an evacuation steel ladder, and one end of the airstairs is provided with a rain shed.

Compared with the prior art, the invention has the beneficial effects that:

1. the remote boarding positions are intensively solved, and the parking of 10 positions can be met;

2. the main structure body adopts a bracket system, so that the existing pavement and lower pipelines are not damaged;

3. the second layer is assembled by various modules, so that the building of the boarding cabin is facilitated, and the arrangement of various subsequent facilities is facilitated;

4. the height of a boarding area is low, and the boarding bridge can be connected with a domestic ARJ airplane after being installed, so that the problem of central operation guarantee of ARJ airplanes is solved, the airplane can be used by various airplanes simultaneously, a plurality of airplanes can be operated simultaneously, and the proportion of airport near positions can be increased;

5. through elevator and the ramp of being connected with the main part cabin body, solve accessible passenger and pass, the boarding bridge front portion sets up the canopy, can regard as the waiting area that falls a visitor of sleet weather.

Drawings

FIG. 1 is a schematic structural diagram of the present invention.

FIG. 2 is a schematic view of the internal cross-sectional structure of the main body cabin according to the present invention.

Fig. 3 is a schematic front view of the present invention.

Fig. 4 is a partial structural schematic diagram of the present invention.

Fig. 5 is a schematic top view of the access escalator and steel step module of the present invention.

Fig. 6 is a schematic top view of the exit escalator and steel step module of the present invention.

In the figure: 1-bracket foundation, 2-main body cabin, 3-corridor boarding area, 4-toilet module, 5-shop module, 6-electromechanical module A, 7-electromechanical module B, 8-standard module, 9-roof system, 10-entrance escalator and steel step module, 11-exit escalator and steel step module, 12-entrance ramp, 13-entrance elevator, 14-exit ramp, 15-exit elevator.

Detailed Description

The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.

Referring to fig. 1-6, in an embodiment of the present invention, a modular assembly type centralized boarding cabin includes a bracket foundation 1 and a main cabin 2 disposed at the top of the bracket foundation 1, the bracket foundation 1 is provided with a plurality of groups, and the bracket foundation 1 includes a bracket base, a column, a beam and a floor system;

the arrangement of the bracket foundation 1 does not damage the existing pavement and lower pipelines;

the main cabin body 2 is connected with at least ten groups of corridor boarding areas 3, and a waiting hall, a toilet module 4, a shop module 5, an electromechanical module A6, an electromechanical module B7, a standard module 8 and a roof system 9 are arranged in the main cabin body 2; the connecting corridor boarding area 3 intensively solves the problem of remote boarding, and can meet the stop of 10 machine positions;

the connecting corridor boarding area 3 is low in height, can be connected with a domestic ARJ airplane after a boarding bridge is installed, solves the problem of central operation guarantee of ARJ airplanes, can meet the use requirements of various airplanes at the same time, can operate a plurality of airplanes at the same time, and can increase the proportion of airport near positions;

the inlet end of the main body cabin 2 is connected with an inlet escalator and a steel step module 10, and the outlet end of the main body cabin 2 is connected with an outlet escalator and a steel step module 11;

and a boarding corridor is arranged on the platform foundation of the connecting corridor boarding area 3 and is connected with a waiting hall and a boarding bridge movable end.

Still be provided with fire pump room module and electricity distribution room module in the main part cabin body 2.

Different install fire water tank, the outer machine of air conditioner, dirty useless collection box on the bracket base respectively, set up on the bracket base, do not occupy too much space, and make full use of space.

The toilet module 4, the shop module 5 and the standard module 8 are arranged on the two sides of the waiting hall;

the toilet module 4, the shop module 5 and the standard module 8 are arranged in a cabin module in the main cabin 2, the electromechanical module A6 and the electromechanical module B7 are both arranged at the top of the cabin module, and the roof system 9 is arranged on one side of the electromechanical module A6 and the electromechanical module B7 away from the cabin module; various modules are assembled, so that the building of the cabin is facilitated, and the arrangement of various subsequent facilities is facilitated.

An entrance ramp 12 and an entrance elevator 13 are arranged on one side of the entrance escalator and steel step module 10, and the entrance elevator 13 is connected with a first-layer entrance and a second-layer waiting hall.

An exit ramp 14 and an exit elevator 15 are arranged on one side of the exit escalator and steel step module 11, and the exit elevator 15 is connected with a first-layer exit and a second-layer waiting hall.

The boarding corridor is connected with an evacuation steel ladder, one end of the boarding corridor is provided with a rain shed, and the rain shed can be used as a passenger waiting area in rainy and snowy weather.

The working principle of the invention is as follows: when the modularized assembled centralized boarding cabin is used, the passenger can enter a waiting hall from the entrance ramp 12 and the entrance escalator and steel step module 10 or enter the waiting hall through the entrance elevator 13, and the passenger can enter the connecting corridor boarding area 3 from the boarding corridor during boarding, and then boarding through the boarding bridge is facilitated.

It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof.