Integral shipping wharf plane arrangement and hoisting process of marine composite cylinder foundation fan

文档序号:338370 发布日期:2021-12-03 浏览:9次 中文

阅读说明:本技术 一种海上复合筒基础风机整体出运码头平面布置及其吊装工艺 (Integral shipping wharf plane arrangement and hoisting process of marine composite cylinder foundation fan ) 是由 薛伟 陈秀瑛 陈晴晴 周婷婷 古浩 徐亚哲 俞竹青 孙萍 辜鹏 王哲轩 张辉宇 于 2021-08-27 设计创作,主要内容包括:本发明涉及一种海上复合筒基础风机整体出运码头平面布置及其吊装工艺,包括钢材堆场、加工区、砂石料堆场、风机基础钢筒生产线、风机基础钢筋混凝土筒体生产线、基础总装区、风机部件堆场、第一风机预装区、第二风机预装区、临时堆放区以及泊位,码头平面布置实现了集约化用地和码头岸线的要求,匹配的吊装工艺与生产流程紧密贴合;复合筒基础经港池下水,进行塔筒、叶片等上部设施安装,解决了成套风机因超高、超重而无法由组装场地直接下水的难题;在两个出运泊位之间设置拖轮操作区,解决了复合筒基础卡入运输船U型槽开始安装上部设施,船舶需固定在码头前沿无法回旋再次装载的难题;本申请实现了海上复合筒基础风机一步式整体安装及出运。(The invention relates to a plane arrangement and a hoisting process of an integral shipping wharf of an offshore composite cylinder foundation fan, which comprises a steel material storage yard, a processing area, a sand and stone material storage yard, a fan foundation steel cylinder production line, a fan foundation reinforced concrete cylinder production line, a foundation assembly area, a fan part storage yard, a first fan preassembly area, a second fan preassembly area, a temporary stacking area and a berth, wherein the wharf plane arrangement meets the requirements of intensive land and wharf shoreline, and the matched hoisting process is tightly attached to the production flow; the composite cylinder foundation is drained through a harbor basin, and upper facilities such as a tower cylinder, blades and the like are installed, so that the problem that the complete set of fan cannot be directly drained from an assembly site due to superelevation and overweight is solved; a tug operation area is arranged between the two delivery berths, so that the problem that the composite cylinder foundation is clamped into a U-shaped groove of a transport ship to start installation of upper facilities, and the ship needs to be fixed at the front edge of a wharf and cannot be rotated to carry again is solved; the application realizes the one-step integral installation and shipment of the marine composite cylinder foundation fan.)

1. The utility model provides a marine compound section of thick bamboo basis fan is whole to be shipped out wharf plane and is arranged which characterized in that: the system comprises a steel material storage yard (1), a processing area (2), a sand and stone material storage yard (3), a fan foundation steel cylinder production line (4), a fan foundation reinforced concrete cylinder production line (5), a foundation assembly area (6), a fan component storage yard (7), a first fan preassembly area (81), a second fan preassembly area (82), a temporary storage area (9) and a berth, wherein the berth comprises a general berth (1001), a fan foundation launching area (1002), a first wind power special berth (1003), a tug operating area (1004) and a second wind power special berth (1005), and the first wind power special berth (1003) and the second wind power special berth (1005) are used for berthing a transport ship (1302);

establishing a two-dimensional coordinate system by taking the line of the wharf as an X axis and taking the direction vertical to the wharf as a Y axis;

arranging a general berth (1001) at the joint of an X axis and a Y axis, and sequentially arranging a fan foundation launching area (1002), a first wind power special berth (1003), a tug operating area (1004) and a second wind power special berth (1005) along the positive direction of the X axis by taking the general berth (1001) as a starting point;

sequentially laying a fan foundation steel cylinder production line (4) and a steel storage yard (1) along the positive direction of a Y axis by taking a universal berth (1001) as a starting point;

the method comprises the following steps that a fan foundation launching area (1002) is taken as a starting point, a foundation assembly area (6), a fan foundation reinforced concrete cylinder production line (5), a processing area (2) and a sand and stone material yard (3) are sequentially arranged along the positive direction of a Y axis, and the processing area (2) and the sand and stone material yard (3) are arranged in parallel to the X axis; erecting a portal frame on an axis parallel to a Y axis formed by a fan foundation launching area (1002), a foundation assembly area (6) and a fan foundation reinforced concrete cylinder production line (5), and arranging a gantry crane (1402) on the axis; a portal crane (1401) for unloading raw materials is arranged between the general berth (1001) and the fan foundation steel cylinder production line (4);

the method comprises the following steps that a gantry crane (1402), a first fan pre-installation area (81), a temporary stacking area (9) and a second fan pre-installation area (82) are sequentially arranged along the positive direction of an X axis from a gantry crane (1401) serving as a starting point, and a fixed crane (1403) is arranged between the temporary stacking area (9) and a tug operation area (1004) and used for pre-assembling and shipping a fan unit (12);

and taking the basic assembly area (6) as a starting point, and arranging a fan component storage yard (7) along the positive direction of the X axis.

2. The marine composite barrel foundation fan integral shipping dock planar arrangement of claim 1, wherein: the draught fan foundation launching area (1002) is an excavated harbor basin, so that integral hoisting launching of the draught fan composite cylinder foundation (11) and towing floating transportation of a towing ship (1301) are met;

the tug operation area (1004) is located between the first wind power special berth (1003) and the second wind power special berth (1005), and the area of the tug operation area (1004) meets the condition that the tug (1301) tows and pushes the composite cylinder foundation (11) into a U-shaped groove of the transport ship (1302).

3. The marine composite barrel foundation fan integral shipping dock planar arrangement of claim 1, wherein: and transferring parts and materials by using a module car or a flat car between a fan foundation steel cylinder production line (4), a fan foundation reinforced concrete cylinder production line (5) and a foundation assembly area (6).

4. The marine composite barrel foundation fan integral shipping dock planar arrangement of claim 1, wherein: the width of the fan foundation reinforced concrete cylinder production line (5) in the X axial direction, the width of the foundation assembly area (6) in the X axial direction and the width of the fan foundation drainage area (1002) in the X axial direction are the same.

5. The marine composite barrel foundation fan integral shipping dock planar arrangement of claim 1, wherein: a first rail is arranged between the fan foundation steel cylinder production line (4) and the universal berth (1001), the first rail is arranged in parallel with the X axis, and the portal crane (1401) is arranged on the first rail.

6. The marine composite barrel foundation fan integral shipping dock planar arrangement of claim 1, wherein: the rail of the gantry covers a processing area (2), a sand and stone material storage yard (3), a fan foundation reinforced concrete cylinder production line (5), a foundation assembly area (6) and a fan foundation drainage area (1002), and the gantry crane (1402) slides along the rail.

7. A hoisting process based on the integral shipping wharf plane arrangement of the marine composite barrel foundation fan as claimed in any one of claims 1 to 6, is characterized in that: the method specifically comprises the following steps:

step S1: the method comprises the following steps of (1) stopping a cargo ship bearing steel plates, gravels and other raw materials in a universal berth (1001), starting a portal crane (1401) to unload the steel plates and the gravels onto a transport vehicle, and conveying the transport vehicle to a steel storage yard (1) and a gravels storage yard (3) along a field road;

step S2: producing and processing the composite cylinder foundation (11);

step S3: transporting the machined and molded composite cylinder foundation (11) to a transport ship (1302), and respectively clamping the composite cylinder foundation in U-shaped grooves at two ends of the transport ship (1302);

step S4: transporting a component tower (1201), a nacelle (1202) and blades (1203) from a fan component storage yard (7) to a fan pre-installation area through a modular vehicle for pre-installation to form a fan assembly (12) component;

step S5: transporting fan assembly (12) components from a fan pre-assembly area to a temporary stacking area (9) by a modular cart;

step S6: assembling components of a fan unit (12) with a composite cylinder foundation (11) clamped in a U-shaped groove at one end of a transport ship (1302) to form a fan body;

step S7: pressurizing the composite cylinder foundation (11) to enable the fan body to float, and completing a set of pre-assembled ship of the fan body;

step S8: and moving the position of the transport ship (1302) in the special berth for wind power, and assembling the components of the fan set (12) with the composite cylinder foundation (11) clamped in the U-shaped groove at the other end of the transport ship (1302) to complete the preassembly ship of the next set of fan body.

8. The hoisting process of the offshore composite cylinder foundation fan integral shipping wharf plane arrangement according to claim 7, characterized in that:

in step S2, the specific steps of manufacturing and processing the composite tube foundation (11) include:

step S21: performing primary processing on raw materials such as steel plates, sand and stones in a processing area (2), respectively transferring to a fan foundation steel cylinder production line (4) and a fan foundation reinforced concrete cylinder production line (5) after the primary processing, and prefabricating a steel cylinder (1101) and a concrete cylinder (1102) of a composite cylinder foundation (11);

step S22: a steel cylinder body (1101) prefabricated by a fan foundation steel cylinder production line (4) is transversely moved to a foundation assembly area (6) through a module vehicle or an air bag;

step S23: starting a gantry crane (1402), and hoisting the concrete cylinder (1102) prefabricated by the fan foundation reinforced concrete cylinder production line (5) to a foundation assembly area (6);

step S24: and adjusting the gantry crane (1402), hoisting the concrete cylinder (1102) to the upper part of the steel cylinder (1101), jointing the two parts together, and then performing hook-drop welding to form the composite cylinder foundation (11).

9. The hoisting process of the offshore composite cylinder foundation fan integral shipping wharf plane arrangement as claimed in claim 8, wherein:

in step S3, the concrete step of transporting the formed composite tube foundation (11) to a transport ship (1302) includes:

step S31: starting the gantry crane (1402) again, hoisting the composite cylinder foundation (11) to a draught fan foundation launching area (1002), slowly hooking, enabling the composite cylinder foundation (11) to sink to an underwater beach surface for debugging, pressurizing the composite cylinder foundation (11) after debugging is finished, and enabling the foundation to float upwards and to be separated from the beach surface;

step S32: the tugboat (1301) drags the debugged composite cylinder foundation (11) to be transported to the position of a transport ship (1302) in a floating mode, the composite cylinder foundation (11) is clamped in U-shaped grooves at two ends of the transport ship (1302) respectively, and after the composite cylinder foundation (11) is clamped into the U-shaped grooves, the composite cylinder foundation (11) is fixed and decompressed until the composite cylinder foundation sinks to the position of a mud surface, and the composite cylinder foundation (11) is stable and does not shake when a fan unit (12) is installed.

10. The hoisting process of the offshore composite drum foundation fan integral shipping wharf plane arrangement as claimed in claim 9, wherein:

in step S6, the specific steps of forming the blower body include:

step S61: adjusting the position of the transport ship (1302) in the special wind power berth, and placing a composite cylinder foundation (11) clamped in a U-shaped groove at one end of the transport ship (1302) right below a fixed crane (1403);

step S62: starting a fixed crane (1403), vertically hoisting a tower drum (1201) arranged in a temporary stacking area (9), slowly translating the tower drum to the top of a composite drum foundation (11) after the hoisting height reaches the top height of the composite drum foundation (11), and fastening the tower drum (1201) by bolts after a bottom flange of the tower drum (1201) is butted with a top flange of the composite drum foundation (11);

step S63: continuously starting the fixed crane (1403), vertically hoisting the cabin (1202) placed in the temporary stacking area (9), continuously raising the lifting height until the top height of the tower drum (1201) is reached, translating to the top of the tower drum (1201), fastening through bolts after a bottom flange of the cabin (1202) is butted with a top flange of the tower drum (1201), yawing the cabin (1202) after fastening, and enabling the axis direction of the cabin (1202) to be parallel to the X-axis direction;

step S64: the fixed crane (1403) is continuously started, a first blade (1203) placed in the temporary stacking area (9) is horizontally lifted, the blade (1203) is inserted into a hub of the nacelle (1202), the blade is fastened through bolts, the hub of the nacelle (1202) is turned after the blade is fastened, the to-be-butted port of the hub is right opposite to the fixed crane (1403), and the blade (1203) is repeatedly installed until all the blades (1203) are installed.

Technical Field

The invention relates to a plane arrangement of an integral shipping wharf of an offshore composite cylinder foundation fan and a hoisting process of the integral shipping wharf, and belongs to the technical field of design of shipping wharfs of offshore fan equipment.

Background

Offshore wind power is also drawing considerable attention where onshore wind power has been able to compete cost-effectively with traditional power technologies. By means of the characteristics of the stability of sea wind resources and large power generation capacity, offshore wind power becomes one of important technologies for reducing carbon emission in the energy production link, has the characteristic of being highly dependent on technical drive, and has the condition of serving as a core power supply to promote the development of global low-carbon economy.

At present, offshore wind power projects built at home and abroad commonly adopt pile foundation structures and gravity type foundation structures, and have poor universality and long installation period. The composite cylindrical foundation and the one-step installation technology fill up the technical blank of one-step installation in the offshore wind power industry, so that the offshore wind power has the capacity of large-scale construction. The shipping wharf matched with the offshore composite cylindrical foundation fan is a part which cannot be lost in the offshore wind power production process flow, and the general plane arrangement, the production process flow, the hoisting process setting and the like of the shipping wharf are all required to be adapted to the special requirements of the composite cylindrical foundation and the one-step installation. The following two problems exist: 1. the composite cylindrical foundation is large in size, heavy in weight and high in height, and the traditional wharf and loading and unloading machinery cannot meet the requirement of the traditional process of hoisting and launching. 2. The fan unit has high installation height and complex process, and how to improve the efficiency and realize one-step installation and ship loading has higher requirements on wharf arrangement and installation machinery.

Disclosure of Invention

The invention provides plane arrangement and a hoisting process of an integral shipping wharf of a marine composite cylinder foundation fan, and realizes one-step integral installation and shipping of the marine composite cylinder foundation fan.

The technical scheme adopted by the invention for solving the technical problems is as follows:

the plane arrangement of the integral shipping wharf of the offshore composite cylinder foundation fan comprises a steel storage yard, a processing area, a sand and stone storage yard, a fan foundation steel cylinder production line, a fan foundation reinforced concrete cylinder production line, a foundation assembly area, a fan component storage yard, a first fan pre-installation area, a second fan pre-installation area, a temporary storage area and a berth, wherein the berth comprises a general berth, a fan foundation drainage area, a first wind power special berth, a tug operating area and a second wind power special berth, and the first wind power special berth and the second wind power special berth are used for berthing a transport ship;

establishing a two-dimensional coordinate system by taking the line of the wharf as an X axis and taking the direction vertical to the wharf as a Y axis;

arranging a general berth at the joint of an X axis and a Y axis, and sequentially arranging a fan foundation launching area, a first wind power special berth, a tug operating area and a second wind power special berth along the positive direction of the X axis by taking the general berth as a starting point;

sequentially laying a fan foundation steel cylinder production line and a steel storage yard along the positive direction of a Y axis by taking the universal berth as a starting point;

taking a fan foundation launching area as a starting point, sequentially arranging a foundation assembly area, a fan foundation reinforced concrete cylinder production line, a machining area and an aggregate storage yard along the positive direction of a Y axis, wherein the machining area and the aggregate storage yard are arranged in parallel with the X axis; erecting a portal frame on an axis parallel to a Y axis formed by a fan foundation launching area, a foundation assembly area and a fan foundation reinforced concrete cylinder production line, and arranging a gantry crane on the axis; a portal crane for unloading the raw materials is arranged between the general berth and the fan foundation steel cylinder production line;

the gantry crane, the first fan pre-installation area, the temporary stacking area and the second fan pre-installation area are sequentially arranged along the positive direction of an X axis from the beginning of the gantry crane, and the fixed crane is arranged between the temporary stacking area and the tug boat operation area and used for pre-assembling and shipping the fan unit;

taking the basic assembly area as a starting point, and arranging a fan component storage yard along the positive direction of the X axis;

as a further optimization of the invention, the draught area of the fan foundation is an excavated harbor basin, so that the integral hoisting and the water discharging of the fan composite cylinder foundation and the towing and floating transportation of the tug are met;

the tug operation area is positioned between the first special wind power berth and the second special wind power berth, and the area of the tug operation area meets the condition that the tug tows and pushes the composite cylinder foundation into a U-shaped groove of the transport ship;

as a further preferred aspect of the invention, a modular cart or a flat car is used for transporting components and materials among a fan foundation steel cylinder production line, a fan foundation reinforced concrete cylinder production line and a foundation final assembly area;

as a further preferred aspect of the invention, the width of the fan foundation reinforced concrete cylinder production line in the X-axis direction, the width of the foundation assembly area in the X-axis direction, and the width of the fan foundation drainage area in the X-axis direction are the same;

as a further preferred aspect of the invention, a first rail is arranged between the fan foundation steel cylinder production line and the general berth, the first rail is arranged in parallel with the X axis, and the portal crane is arranged on the first rail;

as a further preferred aspect of the present invention, the rail of the gantry covers a processing area, an aggregate storage yard, a fan foundation reinforced concrete cylinder production line, a foundation assembly area and a fan foundation launching area, and the gantry slides along the rail;

a hoisting process based on any offshore composite cylinder foundation fan integral shipping wharf plane arrangement specifically comprises the following steps:

step S1: the method comprises the following steps of (1) stopping a cargo ship bearing steel plates, gravels and other raw materials in a universal berth, starting a portal crane to unload the steel plates and the gravels to a transport vehicle, and conveying the transport vehicle to a steel storage yard and a gravel storage yard along a road of a field area;

step S2: carrying out production and processing on the composite cylinder foundation;

step S3: transporting the machined and molded composite cylinder foundation to a transport ship, and respectively clamping the composite cylinder foundation in U-shaped grooves at two ends of the transport ship;

step S4: transporting a component tower drum, a cabin and blades to a fan preassembling area from a fan component storage yard through a module vehicle for preassembly to form a fan unit component;

step S5: transporting the fan unit components from the fan pre-installation area to a temporary stacking area through a module vehicle;

step S6: assembling the fan unit component with a composite cylinder foundation clamped in a U-shaped groove at one end of a transport ship to form a fan body;

step S7: pressurizing the composite cylinder foundation to enable the fan body to float, and completing a set of pre-assembled ship of the fan body;

step S8: moving the position of a transport ship in the special berth for wind power, and assembling the fan unit components with a composite cylinder foundation clamped in a U-shaped groove at the other end of the transport ship to complete the preassembly ship of the next set of fan body;

as a further preferred aspect of the present invention,

in step S2, the specific steps of producing and processing the composite tube foundation include:

step S21: performing primary processing on raw materials such as steel plates, sand stones and the like in a processing area, respectively transferring the raw materials to a fan foundation steel cylinder production line and a fan foundation reinforced concrete cylinder production line after the primary processing, and prefabricating a steel cylinder body and a concrete cylinder body which form a composite cylinder foundation;

step S22: a steel cylinder barrel prefabricated by a fan foundation steel cylinder production line is transversely moved to a foundation assembly area through a module vehicle or an air bag;

step S23: starting a gantry crane, and hoisting the concrete cylinder prefabricated by the fan foundation reinforced concrete cylinder production line to a foundation assembly area;

step S24: adjusting a gantry crane, hoisting the concrete cylinder to the upper part of the steel cylinder, carrying out joint closing and butt joint on the concrete cylinder and the steel cylinder, and then carrying out hook falling welding to form a composite cylinder foundation;

as a further preferred aspect of the present invention,

in step S3, the concrete step of transporting the formed composite tube foundation to a transport ship includes:

step S31: starting the gantry crane again, hoisting the composite cylinder foundation to a draught fan foundation launching area, slowly dropping the hook, sinking the composite cylinder foundation to an underwater beach surface for debugging, pressurizing the composite cylinder foundation after debugging is finished, and separating the foundation floating from the beach surface;

step S32: the composite cylinder foundation after debugging is transported to a transport ship in a floating mode by a towing wheel and is respectively clamped in U-shaped grooves at two ends of the transport ship, and after the composite cylinder foundation is clamped in the U-shaped grooves, the composite cylinder foundation is fixed and decompressed until the composite cylinder foundation sinks to a mud surface, so that the composite cylinder foundation (11) is stable and free of shaking when a fan unit (12) is installed;

as a further preferred aspect of the present invention,

in step S6, the specific steps of forming the blower body include:

step S61: adjusting the position of the transport ship in the special wind power berth, and placing a composite cylinder foundation clamped in a U-shaped groove at one end of the transport ship under a fixed crane;

step S62: starting a fixed crane, vertically hoisting the tower barrel arranged in the temporary stacking area, slowly translating the tower barrel to the top of the composite barrel foundation after the hoisting height reaches the top of the composite barrel foundation, and fastening the tower barrel bottom flange and the top flange of the composite barrel foundation through bolts after butting;

step S63: continuously starting the fixed crane, vertically lifting the engine room arranged in the temporary stacking area, continuously lifting the lifting height until the tower barrel is lifted, horizontally moving to the top of the tower barrel, fastening the flange at the bottom of the engine room and the flange at the top of the tower barrel through bolts after butting, yawing the engine room after fastening, and enabling the axis direction of the engine room to be parallel to the X-axis direction;

step S64: and continuously starting the fixed crane, horizontally hoisting the first blade arranged in the temporary stacking area, inserting the blade into the engine room hub, fastening through the bolt, turning the engine room hub after fastening, and repeatedly installing the blades until all the blades are installed.

Through the technical scheme, compared with the prior art, the invention has the following beneficial effects:

1. the offshore composite cylinder foundation fan is integrally delivered out of the wharf plane, the arrangement and connection of each area and machinery are tightly attached to the production flow, and the requirements of intensive land utilization and wharf shoreline are met;

2. according to the marine composite cylinder foundation fan integrally delivered wharf plane arrangement, all parts of the fan body are split, processed respectively and then concentrated to the wharf for assembly, and the problem that the fan body cannot be integrally directly drained from an assembly site due to superelevation and overweight is solved;

3. the plane of the integral shipping wharf of the marine composite cylinder foundation fan provided by the invention is arranged at two sides of the tug operation area, and the first special berth for wind power and the second special berth for wind power are respectively arranged, so that the adjusting capacity of the transport ship is improved, and the problem that the ship cannot be rotated to be loaded again before being fixed at the wharf is solved.

Drawings

The invention is further illustrated with reference to the following figures and examples.

FIG. 1 is a top plan view of an offshore composite barrel foundation fan integral shipping dock layout of a preferred embodiment provided by the present invention;

FIG. 2 is a schematic structural view of a blower body according to the present invention;

FIG. 3 is a schematic diagram of a composite drum infrastructure provided by the present invention;

FIG. 4 is a schematic structural diagram of a fan assembly provided in the present invention;

fig. 5 is a side view of a first wind power-dedicated berth or a second wind power-dedicated berth provided by the invention.

In the figure: the system comprises a steel storage yard 1, a processing area 2, a sand material storage yard 3, a fan foundation steel cylinder production line 4, a fan foundation reinforced concrete cylinder production line 5, a base assembly area 6, a fan component storage yard 7, a first fan pre-installation area 81, a second fan pre-installation area 82, a temporary storage area 9, a universal berth 1001, a fan foundation launching area 1002, a first wind power special berth 1003, a tug boat operation area 1004, a second wind power special berth 1005, a composite cylinder foundation 11, a steel cylinder 1101, a concrete cylinder 1102, a fan unit 12, a tower cylinder 1201, a cabin 1202, blades 1203, a tug boat 1301, a transport boat 1302, a portal crane 1401, a gantry 1402 and a fixed crane 1403.

Detailed Description

The present invention will now be described in further detail with reference to the accompanying drawings. In the description of the present application, it is to be understood that the terms "left side", "right side", "upper part", "lower part", etc., indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of describing the present invention and simplifying the description, but do not indicate or imply that the referred device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and that "first", "second", etc., do not represent an important degree of the component parts, and thus are not to be construed as limiting the present invention. The specific dimensions used in the present example are only for illustrating the technical solution and do not limit the scope of protection of the present invention.

The composite cylindrical foundation is large in size, heavy in weight and high in height, the process of hoisting and launching the composite cylindrical foundation is difficult at present, the regional layout of the traditional wharf cannot be met, and the machinery for loading and unloading the composite cylindrical foundation cannot meet the requirement of integral hoisting and conveying easily, so that the whole installation effect is influenced.

Based on this, this application provides a marine compound section of thick bamboo basis fan is whole to be shipped out pier plane arrangement, fig. 1 shows the distribution schematic diagram of the preferred embodiment that this application provided, and whole distribution is L shape setting, and the fan body dismouting that fig. 2 shows is divided into two parts, and the first part is compound section of thick bamboo basis 11, and the second part is fan unit 12 part for the left part, explains with fig. 1 visual angle, and the left part is the production line of transportation, manufacturing compound section of thick bamboo basis, and the right side is the transportation of fan unit part along the pier part, manufacturing line. According to the arrangement mode, the fan body is detached to be manufactured and installed, the production processes of all areas are connected and pushed to the wharf direction from the rear of the land area, and the whole hoisting efficiency can be improved.

Specifically, in fig. 1, the system comprises a steel material storage yard 1, a processing area 2, a sand material storage yard 3, a fan foundation steel cylinder production line 4, a fan foundation reinforced concrete cylinder production line 5, a foundation assembly area 6, a fan component storage yard 7, a first fan pre-installation area 81, a second fan pre-installation area 82, a temporary storage area 9 and a berth, wherein the berth comprises a general berth 1001, a fan foundation drainage area 1002, a first wind power special berth 1003, a tug operating area 1004 and a second wind power special berth 1005, and the first wind power special berth and the second wind power special berth are used for berthing a transport ship 1302;

for more clear explanation, a two-dimensional coordinate system is established by taking the line of the wharf as an X axis and taking the direction vertical to the wharf as a Y axis;

arranging a general berth at the joint of an X axis and a Y axis, and sequentially arranging a fan foundation launching area, a first wind power special berth, a tug operating area and a second wind power special berth along the positive direction of the X axis by taking the general berth as a starting point; sequentially laying a fan foundation steel cylinder production line and a steel storage yard along the positive direction of a Y axis by taking the universal berth as a starting point; taking a fan foundation launching area as a starting point, sequentially arranging a foundation assembly area, a fan foundation reinforced concrete cylinder production line, a machining area and an aggregate storage yard along the positive direction of a Y axis, wherein the machining area and the aggregate storage yard are arranged in parallel with the X axis; erecting a portal frame on an axis parallel to a Y axis formed by a fan foundation launching area, a foundation assembly area and a fan foundation reinforced concrete cylinder production line, and arranging a gantry crane 1402 on the axis, wherein the gantry crane is provided with a special annular lifting appliance to ensure that the balance is stable in the process of lifting the composite cylinder foundation; a portal crane 1401 for unloading raw materials is arranged between a general berth and a fan foundation steel cylinder production line, a portal crane track is parallel to a wharf front line, the lifting capacity of the portal crane track meets the loading and unloading operation requirements of bulk and general cargo ships, and various hook head tools are required to be equipped to meet the requirements of different cargo types; the gantry crane, the first fan pre-installation area, the temporary stacking area and the second fan pre-installation area are sequentially arranged along the positive direction of an X axis from a gantry crane serving as a starting point, the two fan pre-installation areas are arranged to improve the pre-installation assembly efficiency, a fixed crane 1403 is arranged between the temporary stacking area and a tug operation area and used for pre-assembling and shipping of a fan unit, the fixed crane is provided with special tools such as a tower drum hanging seat, a cabin hanging beam, a blade clamp and the like, the hoisting capacity meets the requirements of hoisting, pre-assembling and shipping of various components of the fan unit, and the hoisting height of the fixed crane is higher than the top height of the cabin 1202 and takes a certain margin height into consideration; and taking the basic assembly area as a starting point, and arranging a fan component storage yard along the positive direction of the X axis.

The left fan foundation steel cylinder production line and the left fan foundation reinforced concrete cylinder production line are used for manufacturing a steel cylinder 1101 and a concrete cylinder 1102 respectively, the composite cylinder foundation shown in FIG. 3 is manufactured in a split mode, the production efficiency can be improved, a universal berth is arranged at the end portions of the two production lines, the size of the universal berth meets the requirements of berthing of bulk freighters and hoisting operation of unloading raw materials, and the design ship type of the universal berth is generally a bulk freighter below 3000t level; after the transportation distance of raw and other materials is improved, the production efficiency is further improved, a module car or a flat car is used for transferring components and materials between a fan foundation steel cylinder production line, a fan foundation reinforced concrete cylinder production line and a foundation final assembly area, after the production of the production line is finished, a composite cylinder foundation is conveyed, because the composite cylinder foundation is heavier, a gantry crane is adopted for hoisting, and meanwhile, the width of the fan foundation reinforced concrete cylinder production line in the X axial direction, the width of the foundation final assembly area in the X axial direction and the width of the fan foundation drainage area in the X axial direction are set to be the same, so that the gantry crane meets the hoisting requirements of three areas of the fan foundation reinforced concrete cylinder production line, the foundation final assembly area and the fan foundation drainage area. The operation of the gantry crane is that a first rail is arranged between a fan foundation steel cylinder production line and a general berth, the first rail is arranged in parallel with an X axis, the gantry crane is arranged on the first rail, the gantry crane slides along the rail, and finally the assembled composite cylinder foundation is conveyed to a transport ship in a fan foundation launching area, wherein the fan foundation launching area is an excavated type harbor basin, so that the integral hoisting launching of the fan composite cylinder foundation and the towing ship 1301 towing floating transportation are met.

The fan pre-installation area on the right side and other areas are arranged, the assembly requirements of all parts of the fan unit shown in the figure 4 are met, meanwhile, the assembly parts can be installed at the wharf side, and the problem of troublesome installation caused by high installation height and complex process of the fan unit is solved.

What needs to be specially stated here is that the area on the right side includes two berths, namely a first wind power special berth and a second wind power special berth, the two berths both stop a fan installation transport ship, and the design ship type of the wind power special berth is generally a professional barge below 20000t level; a tug operation area is arranged in the middle, the area of the tug operation area meets the requirement that the tug drags and pushes the composite cylinder foundation into a U-shaped groove of the transport ship, because if the tug operation area is not arranged in the middle of a shoreline berth, when two wind power special berths stop a fan installation transport ship, a middle clamping groove cannot fix the foundation, the method for solving the problem can only be used for driving the fan installation transport ship out of the berth to rotate and turn around to fix the foundation at the other end after a fan body is installed at one end of the fan installation transport ship, and the unbalanced load ship has higher difficulty and extremely high danger in the rotating process; the utility model provides a setting can make full use of tow boat operation area work simultaneously in the special berth of first wind-powered electricity generation and the special berth of second wind-powered electricity generation, has also guaranteed the fixed to the fan basis.

And another factor is that each fan installation transport ship is provided with two U-shaped grooves, a composite cylinder foundation can be clamped in each U-shaped groove, the fixed crane can complete the assembly of a group of fan bodies nearby, the transport ship can be moved only in the corresponding wind power special parking area, the assembly of the composite cylinder foundation at the other end can be realized, and the installation efficiency is greatly improved.

After whole pier carries out the plane arrangement, still need match the hoist and mount technology to make whole assembly process high-efficient, this application has proposed based on the hoist and mount technology of marine compound section of thick bamboo basis fan whole shipment pier plane arrangement specifically includes following step:

step S1: the cargo ship bearing the steel plates, the gravels and other raw materials is stopped in the universal berth, the portal crane is started to unload the steel plates and the gravels to the transport vehicle, and the transport vehicle is conveyed to the steel storage yard and the gravel storage yard along the road of the field area.

Step S2: the production and processing of the composite cylinder foundation comprises the following specific steps:

step S21: performing primary processing on raw materials such as steel plates, sand stones and the like in a processing area, respectively transferring the raw materials to a fan foundation steel cylinder production line and a fan foundation reinforced concrete cylinder production line after the primary processing, and prefabricating a steel cylinder body and a concrete cylinder body which form a composite cylinder foundation;

step S22: a steel cylinder barrel prefabricated by a fan foundation steel cylinder production line is transversely moved to a foundation assembly area through a module vehicle or an air bag;

step S23: starting a gantry crane, and hoisting the concrete cylinder prefabricated by the fan foundation reinforced concrete cylinder production line to a foundation assembly area;

step S24: and adjusting the gantry crane, hoisting the concrete cylinder to the position above the steel cylinder, jointing the concrete cylinder and the steel cylinder in a joint manner, and then performing hook-drop welding to form the composite cylinder foundation.

Step S3: transporting the machined and molded composite cylinder foundation to a transport ship, and respectively clamping the composite cylinder foundation in U-shaped grooves at two ends of the transport ship; as shown in fig. 5, the specific steps include:

step S31: starting the gantry crane again, hoisting the composite cylinder foundation to a draught fan foundation launching area, slowly dropping the hook, sinking the composite cylinder foundation to an underwater beach surface for debugging, pressurizing the composite cylinder foundation after debugging is finished, and separating the foundation floating from the beach surface;

step S32: the tugboat carries the composite barrel foundation after debugging to a transport ship in a towing manner, the composite barrel foundation is respectively clamped in U-shaped grooves at two ends of the transport ship and is fixed and decompressed after being clamped in the U-shaped grooves until the composite barrel foundation sinks to a mud surface, and the composite barrel foundation (11) is stable and does not shake when a fan unit (12) is installed.

Step S4: and (3) transporting the component tower 1201, the engine room and the blades 1203 to a fan pre-installation area from a fan component storage yard through a module vehicle for pre-installation to form a fan assembly component.

Step S5: and transporting the fan assembly components from the fan pre-installation area to a temporary stacking area through the module vehicle.

Step S6: assembling the fan unit component with a composite cylinder foundation clamped in a U-shaped groove at one end of a transport ship to form a fan body;

the method comprises the following specific steps: step S61: adjusting the position of the transport ship in the special wind power berth, and placing a composite cylinder foundation clamped in a U-shaped groove at one end of the transport ship under a fixed crane;

step S62: starting a fixed crane, vertically hoisting the tower barrel arranged in the temporary stacking area, slowly translating the tower barrel to the top of the composite barrel foundation after the hoisting height reaches the top of the composite barrel foundation, and fastening the tower barrel bottom flange and the top flange of the composite barrel foundation through bolts after butting;

step S63: continuously starting the fixed crane, vertically lifting the engine room arranged in the temporary stacking area, continuously lifting the lifting height until the tower barrel is lifted, horizontally moving to the top of the tower barrel, fastening the flange at the bottom of the engine room and the flange at the top of the tower barrel through bolts after butting, yawing the engine room after fastening, and enabling the axis direction of the engine room to be parallel to the X-axis direction;

step S64: and continuously starting the fixed crane, horizontally hoisting the first blade arranged in the temporary stacking area, inserting the blade into the engine room hub, fastening through the bolt, turning the engine room hub after fastening, and repeatedly installing the blades until all the blades are installed.

Step S7: pressurizing the composite cylinder foundation to enable the fan body to float, and completing a set of pre-assembled ship of the fan body;

what needs to be explained here is that the composite cylinder foundation is pressurized, namely, the air pressure is added in the steel cylinder body, the principle of the composite cylinder foundation is similar to that of a submarine, the cylinder can float after the air pressure is added in the cylinder, and the cylinder can sink after the air pressure is reduced.

Step S8: and moving the position of the transport ship in the special berth for wind power, and assembling the fan unit component and the composite cylinder foundation clamped in the U-shaped groove at the other end of the transport ship to complete the preassembly ship of the next set of fan body.

Above can know, the floor plan and hoist and mount technology of this application have foresight nature, and not only make full use of pier arranges along the line, closely links up each region, carries out the pipelining operation at manufacturing and equipment part, and speed is showing and is improving, and the self characteristic of the fan body of fully combining simultaneously is launched directly at the equipment place, and process flow is simple and convenient.

It will be understood by those skilled in the art that, unless otherwise defined, all terms (including technical and scientific terms) used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs. It will be further understood that terms, such as those defined in commonly used dictionaries, should be interpreted as having a meaning that is consistent with their meaning in the context of the prior art and will not be interpreted in an idealized or overly formal sense unless expressly so defined herein.

The meaning of "and/or" as used herein is intended to include both the individual components or both.

The term "connected" as used herein may mean either a direct connection between components or an indirect connection between components via other components.

In light of the foregoing description of the preferred embodiment of the present invention, many modifications and variations will be apparent to those skilled in the art without departing from the spirit and scope of the invention. The technical scope of the present invention is not limited to the content of the specification, and must be determined according to the scope of the claims.

15页详细技术资料下载
上一篇:一种医用注射器针头装配设备
下一篇:风电机组的数据监测装置和方法

网友询问留言

已有0条留言

还没有人留言评论。精彩留言会获得点赞!

精彩留言,会给你点赞!