阅读说明:本技术 一种高效节能绿色建筑工程施工方法 (Efficient energy-saving green construction engineering construction method ) 是由 荆松 于 2021-07-21 设计创作,主要内容包括:本发明涉及建筑施工技术领域,公开了一种高效节能绿色建筑工程施工方法,S1:对施工区域外围搭建隔音板,再根据建筑图纸进行施工测量;S2:对施工区域内建立回水渠收集废水,废水处理装置进行过滤;S3:废水处理装置内的水通过喷头对离开施工区局的施工车辆的车轮进行冲洗;S4:在施工区域内的待施工土面和未施工土面需要铺设防尘网;S5:在对基坑开挖时,需要对开挖区域进行喷洒降尘,本发明有利于减少建筑施工过程中废水污染,同时采用分类处理和分级使用规范废水使用,减少运输车辆将施工泥土带到道路上造成污染,通过灰尘检测仪进行监管,有利于减少会施工时大量灰尘飘散影响环境造成污染。(The invention relates to the technical field of building construction, and discloses a high-efficiency energy-saving green building engineering construction method, which comprises the following steps of S1: building a sound insulation board at the periphery of the construction area, and performing construction measurement according to a construction drawing; s2: establishing a return channel in the construction area to collect wastewater, and filtering by a wastewater treatment device; s3: washing the wheels of the construction vehicle away from the construction area office by water in the wastewater treatment device through a spray head; s4: laying dust screens on the soil surface to be constructed and the soil surface which is not constructed in the construction area; s5: when a foundation pit is excavated, the excavated area needs to be sprayed for dust reduction, the method is favorable for reducing the wastewater pollution in the building construction process, and the classification treatment and the graded use of the wastewater are adopted to regulate the wastewater use, so that the pollution caused by the construction soil brought to the road by a transport vehicle is reduced, and the dust detector is used for supervision, thereby being favorable for reducing the pollution caused by the influence of the scattering of a large amount of dust on the environment during construction.)

1. A construction method of high-efficiency energy-saving green building engineering is characterized in that: the construction method of the high-efficiency energy-saving green building engineering comprises the following steps:

s1: building a sound insulation board at the periphery of the construction area, and performing construction measurement according to a construction drawing;

s2: establishing a return channel in the construction area to collect wastewater, and filtering by a wastewater treatment device;

s3: washing the wheels of the construction vehicle away from the construction area office by water in the wastewater treatment device through a spray head;

s4: laying dust screens on the soil surface to be constructed and the soil surface which is not constructed in the construction area;

s5: when a foundation pit is excavated, spraying dust fall on an excavated area;

s6: the foundation pit needs to pay attention to the load and safety detection of the pit edge and the support removal;

s7: binding the areas where the reinforcing steel bars are stacked on site, marking, and paying attention to moisture resistance;

s8: in the process of building the template, the strength of the template wall-penetrating bolt of the civil air defense outer wall and the sealed partition wall needs to be ensured;

s9: concrete needs to be stirred on site, stirring needs to be carried out in a space formed by the dustproof net in the stirring process, and the foundation structure and the main structure need to be connected and poured;

s10: the safety protection of the building main body needs to adopt an overhanging frame externally hung dense mesh net;

s11: except for the construction vehicle in S3, the inspection for access to and inspection for the outside of the vehicle transportation are required for vehicles transporting harmful substances or waste emissions;

s12: s2 is used for collecting the waste water in different flow paths, and the waste water is collected in different flow paths in construction sites, mixing plants, toilets and living areas.

2. The construction method of the high-efficiency energy-saving green constructional engineering as claimed in claim 1, wherein: the method is used for detecting vehicles entering a construction area, cleaning the vehicles with a large amount of silt on wheels, and detecting the shipping specification of transportation waste and harmful waste.

3. The construction method of the high-efficiency energy-saving green constructional engineering as claimed in claim 1, wherein: the construction time of large machinery in the construction process needs to be compounded with the working time of residents.

4. The construction method of the high-efficiency energy-saving green constructional engineering as claimed in claim 1, wherein: and the space formed by the S9 dust screen is supported by the bracket to form a space for blocking dust generated by stirring.

5. The construction method of the high-efficiency energy-saving green constructional engineering as claimed in claim 1, wherein: dust detectors are arranged on the periphery of the construction area at equal intervals.

Technical Field

The invention relates to the technical field of building construction, in particular to a high-efficiency energy-saving green building engineering construction method.

Background

At present, the existing patent (with the publication number of CN112726729A) realizes water resource recycling and reduces construction cost, and meanwhile, a wall body mold is sleeved outside a wall body to quickly pour the outside of an outer wall, so that gaps remained in brickwork are eliminated, the strength of the wall body is increased, the construction efficiency is improved, and efficient, energy-saving and green construction is realized.

Therefore, the construction method of the high-efficiency energy-saving green building engineering is beneficial to reducing the wastewater pollution in the building construction process, and meanwhile, the classification treatment and the graded use standard wastewater use are adopted, so that the pollution caused by bringing construction soil to a road by a transport vehicle is reduced, and the dust detector is used for supervision, so that the pollution caused by the influence of a large amount of dust on the environment during construction is reduced.

Disclosure of Invention

The invention aims to provide an efficient energy-saving green construction engineering construction method, which solves the problems in the background technology.

In order to achieve the purpose, the invention provides the following technical scheme: a construction method of high-efficiency energy-saving green building engineering comprises the following steps:

s1: building a sound insulation board at the periphery of the construction area, and performing construction measurement according to a construction drawing;

s2: establishing a return channel in the construction area to collect wastewater, and filtering by a wastewater treatment device;

s3: washing the wheels of the construction vehicle away from the construction area office by water in the wastewater treatment device through a spray head;

s4: laying dust screens on the soil surface to be constructed and the soil surface which is not constructed in the construction area;

s5: when a foundation pit is excavated, spraying dust fall on an excavated area;

s6: the foundation pit needs to pay attention to the load and safety detection of the pit edge and the support removal;

s7: binding the areas where the reinforcing steel bars are stacked on site, marking, and paying attention to moisture resistance;

s8: in the process of building the template, the strength of the template wall-penetrating bolt of the civil air defense outer wall and the sealed partition wall needs to be ensured;

s9: concrete needs to be stirred on site, stirring needs to be carried out in a space formed by the dustproof net in the stirring process, and the foundation structure and the main structure need to be connected and poured;

s10: the safety protection of the building main body needs to adopt an overhanging frame externally hung dense mesh net;

s11: except for the construction vehicle in S3, the inspection for access to and inspection for the outside of the vehicle transportation are required for vehicles transporting harmful substances or waste emissions;

s12: s2 is used for collecting the waste water in different flow paths, and the waste water is collected in different flow paths in construction sites, mixing plants, toilets and living areas.

In a preferred embodiment of the present invention, the inspection of vehicles entering a construction area is performed, the cleaning of vehicles with a large amount of sand and sand on wheels is performed, and the inspection of shipping specifications of transport waste and hazardous waste is performed.

As a preferred embodiment of the invention, the construction time of large machinery in the construction process needs composite resident work and rest time.

In a preferred embodiment of the present invention, the space formed by the S9 dust screen is supported by a support to form a space for blocking dust generated by stirring.

Compared with the prior art, the invention has the following beneficial effects:

1. the invention carries out classification and recovery treatment on the waste water of building construction, simultaneously recycles partial waste water in a grading way, sprays dust fall on the recovered waste water or washes wheels of a transport vehicle according to different treatment grades, is beneficial to reducing the waste water pollution in the building construction process, and simultaneously reduces the pollution caused by the transport vehicle bringing construction soil to a road by adopting classification treatment and grading use standard waste water.

2. According to the invention, the dust screen is laid on the non-construction soil surface to reduce the raised dust, the dust-proof space is arranged in the concrete mixing area, the water is sprayed to the construction area to reduce the dust, and the dust is monitored by the dust detector, so that the environment pollution caused by the influence of a large amount of dust in construction on the environment can be reduced.

Detailed Description

In order to make the technical means, the creation characteristics, the achievement purposes and the effects of the invention easy to understand, the invention is further described with the specific embodiments.

In the description of the present invention, the specific meanings of the above-mentioned terms in the present invention will be understood to be specific to those skilled in the art.

The invention provides a technical scheme that: a construction method of high-efficiency energy-saving green building engineering comprises the following steps:

s1: building a sound insulation board at the periphery of the construction area, and performing construction measurement according to a construction drawing;

s2: establishing a return channel in the construction area to collect wastewater, and filtering by a wastewater treatment device;

s3: washing the wheels of the construction vehicle away from the construction area office by water in the wastewater treatment device through a spray head;

s4: laying dust screens on the soil surface to be constructed and the soil surface which is not constructed in the construction area;

s5: when a foundation pit is excavated, spraying dust fall on an excavated area;

s6: the foundation pit needs to pay attention to the load and safety detection of the pit edge and the support removal;

s7: binding the areas where the reinforcing steel bars are stacked on site, marking, and paying attention to moisture resistance;

s8: in the process of building the template, the strength of the template wall-penetrating bolt of the civil air defense outer wall and the sealed partition wall needs to be ensured;

s9: concrete needs to be stirred on site, stirring needs to be carried out in a space formed by the dustproof net in the stirring process, and the foundation structure and the main structure need to be connected and poured;

s10: the safety protection of the building main body needs to adopt an overhanging frame externally hung dense mesh net;

s11: except for the construction vehicle in S3, the inspection for access to and inspection for the outside of the vehicle transportation are required for vehicles transporting harmful substances or waste emissions;

s12: s2 is used for collecting the waste water in different flow paths, and the waste water is collected in different flow paths in construction sites, mixing plants, toilets and living areas.

In this embodiment, the vehicle that gets into the construction area is inspected, and the vehicle that the wheel has a large amount of silt is cleared up, inspects the shipment specification of transportation discarded object and harmful waste.

In this embodiment, the construction time of the large machine in the construction process needs to be combined with the working time of residents.

In this embodiment, the space formed by the S9 dust screen is supported by the bracket to form a space for blocking dust generated by stirring.

In this embodiment, dust detectors are installed at equal intervals around the construction area.

Detailed description of the preferred embodiment 1

S1: building a sound insulation board at the periphery of the construction area, and performing construction measurement according to a construction drawing;

s2: establishing a return channel in the construction area to collect wastewater, and filtering by a wastewater treatment device;

s3: washing the wheels of the construction vehicle away from the construction area office by water in the wastewater treatment device through a spray head;

s4: laying dust screens on the soil surface to be constructed and the soil surface which is not constructed in the construction area;

s5: when a foundation pit is excavated, spraying dust fall on an excavated area;

s6: the foundation pit needs to pay attention to the load and safety detection of the pit edge and the support removal;

s7: binding the areas where the reinforcing steel bars are stacked on site, marking, and paying attention to moisture resistance;

s8: in the process of building the template, the strength of the template wall-penetrating bolt of the civil air defense outer wall and the sealed partition wall needs to be ensured;

s9: concrete needs to be stirred on site, stirring needs to be carried out in a space formed by the dustproof net in the stirring process, and the foundation structure and the main structure need to be connected and poured;

s10: the safety protection of the building main body needs to adopt an overhanging frame externally hung dense mesh net;

s11: except for the construction vehicle in S3, the inspection for access to and inspection for the outside of the vehicle transportation are required for vehicles transporting harmful substances or waste emissions;

s12: s2 is used for collecting the waste water in different flow paths, and the waste water is collected in different flow paths in construction sites, mixing plants, toilets and living areas.

When the vehicle got into the construction area, need inspect the vehicle shipment goods, whether the automobile body of observing the shipment vehicle simultaneously is complete, avoids the goods to lose, when construction vehicle left the construction area, clears up construction vehicle's wheel through rivers, and need inspect the goods of loading in the haulage vehicle, inspects the specification of loading object, avoids loading the thing transportation in-process to drop.

Specific example 2

S1: building a sound insulation board at the periphery of the construction area, and performing construction measurement according to a construction drawing;

s2: establishing a return channel in the construction area to collect wastewater, and filtering by a wastewater treatment device;

s3: washing the wheels of the construction vehicle away from the construction area office by water in the wastewater treatment device through a spray head;

s4: laying dust screens on the soil surface to be constructed and the soil surface which is not constructed in the construction area;

s5: when a foundation pit is excavated, spraying dust fall on an excavated area;

s6: the foundation pit needs to pay attention to the load and safety detection of the pit edge and the support removal;

s7: binding the areas where the reinforcing steel bars are stacked on site, marking, and paying attention to moisture resistance;

s8: in the process of building the template, the strength of the template wall-penetrating bolt of the civil air defense outer wall and the sealed partition wall needs to be ensured;

s9: concrete needs to be stirred on site, stirring needs to be carried out in a space formed by the dustproof net in the stirring process, and the foundation structure and the main structure need to be connected and poured;

s10: the safety protection of the building main body needs to adopt an overhanging frame externally hung dense mesh net;

s11: except for the construction vehicle in S3, the inspection for access to and inspection for the outside of the vehicle transportation are required for vehicles transporting harmful substances or waste emissions;

s12: s2 is used for collecting the waste water in different flow paths, and the waste water is collected in different flow paths in construction sites, mixing plants, toilets and living areas.

The waste water treatment method has the advantages that the waste water is collected in a shunting mode through different return water channels aiming at waste water not used, a construction site, a stirring station, a toilet and a living area are collected in a shunting mode, waste water generated by different regional differences is treated in a grading mode, and waste water after grading treatment can be used for secondary utilization of water according to different construction requirements.

Specific example 3

S1: building a sound insulation board at the periphery of the construction area, and performing construction measurement according to a construction drawing;

s2: establishing a return channel in the construction area to collect wastewater, and filtering by a wastewater treatment device;

s3: washing the wheels of the construction vehicle away from the construction area office by water in the wastewater treatment device through a spray head;

s4: laying dust screens on the soil surface to be constructed and the soil surface which is not constructed in the construction area;

s5: when a foundation pit is excavated, spraying dust fall on an excavated area;

s6: the foundation pit needs to pay attention to the load and safety detection of the pit edge and the support removal;

s7: binding the areas where the reinforcing steel bars are stacked on site, marking, and paying attention to moisture resistance;

s8: in the process of building the template, the strength of the template wall-penetrating bolt of the civil air defense outer wall and the sealed partition wall needs to be ensured;

s9: concrete needs to be stirred on site, stirring needs to be carried out in a space formed by the dustproof net in the stirring process, and the foundation structure and the main structure need to be connected and poured;

s10: the safety protection of the building main body needs to adopt an overhanging frame externally hung dense mesh net;

s11: except for the construction vehicle in S3, the inspection for access to and inspection for the outside of the vehicle transportation are required for vehicles transporting harmful substances or waste emissions;

s12: s2 is used for collecting the waste water in different flow paths, and the waste water is collected in different flow paths in construction sites, mixing plants, toilets and living areas.

In the construction area, the dust screen is laid to the soil face of not being under construction to prop up the formation space with the dust screen through the support, make the dust fly away when concrete mixing or screening sand, and supervise the dust condition in the region through the dust detector, when single position dust detector appears reporting an emergency, can look for the dust according to the wind direction and take place the direction and in time handle.

Specific example 4

Before the construction, the acoustic celotex board is erect to the construction region outer wall to according to resident work and rest control large-scale mechanical operating time, avoid large-scale mechanical operating time and resident rest time coincidence through time management, avoid the noise formation that the construction brought to disturb the people.

When the construction method of the high-efficiency energy-saving green building engineering is used, it needs to be explained that the construction method of the high-efficiency energy-saving green building engineering is provided, all parts are universal standard parts or parts known by technicians in the field, and the structure and the principle of the construction method are known by the technicians through technical manuals or conventional experimental methods.

While there have been shown and described what are at present considered the fundamental principles and essential features of the invention and its advantages, it will be apparent to those skilled in the art that the invention is not limited to the details of the foregoing exemplary embodiments, but is capable of other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein.

Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

7页详细技术资料下载
上一篇:一种医用注射器针头装配设备
下一篇:一种装配式控制点竖向投测洞口固定装置

网友询问留言

已有0条留言

还没有人留言评论。精彩留言会获得点赞!

精彩留言,会给你点赞!