The docking facilities and interconnection method of big segment steel truss girder

文档序号:1751995 发布日期:2019-11-29 浏览:5次 中文

阅读说明:本技术 大节段钢桁梁的对接装置和对接方法 (The docking facilities and interconnection method of big segment steel truss girder ) 是由 邹冠 胡杰 张文斌 许佳平 毛玮琦 涂满明 李军堂 姚森 胡勇 崔一兵 陈涛 于 2019-07-30 设计创作,主要内容包括:本发明公开了一种大节段钢桁梁的对接装置,其用于将已架梁段和待架梁段对接;大节段钢桁梁包括上弦、下弦、竖向杆、对接杆以及大横梁;对接装置包括:第一对拉机构,其一端与待架梁段中的一大横梁连接,另一端与已架梁段中对应的大横梁连接;当第一对拉机构在对拉时,待架梁段的一大横梁向已架梁段中对应的大横梁靠近;第二对拉机构,其两端分别设在已架梁段、待架梁段的中部;当第二对拉机构在对拉时,待架梁段中的一对接杆向已架梁段中对应的对接杆靠近;起顶机构,其包括起顶器;起顶器设于待架梁段中的上弦上,且顶部固定;当起顶器向上起顶时,待架梁段下压。本发明有效调节已架梁段与待架梁段间的相对变形,实现大节段钢桁梁对接。(The invention discloses a kind of docking facilities of big segment steel truss girder, and be used to have set a roof beam in place section and section to be set a roof beam in place docking;Big segment steel truss girder include wind up, lower edge, vertical bar, to extension bar and cross bearer;Docking facilities include: first pair of drawing mechanism, and one end is connect with wait the cross bearer in section of setting a roof beam in place, and the other end is connected with cross bearer corresponding in section of having set a roof beam in place;When first pair of drawing mechanism is when to drawing, a cross bearer of section to be set a roof beam in place corresponding cross bearer into section of having set a roof beam in place is close;Second pair of drawing mechanism, both ends are respectively provided at the middle part of section of having set a roof beam in place, section to be set a roof beam in place;When second pair of drawing mechanism to draw when, it is corresponding close to extension bar into section of having set a roof beam in place wait a pair of of extension bar in section of setting a roof beam in place;Top lifting mechanism comprising lift up device;Lift up device is set to wait on winding up in section of setting a roof beam in place, and top is fixed;When the upward top lifting of lift up device, section to be set a roof beam in place is pushed.The present invention effectively adjusts the section and wait the relative deformation between section of setting a roof beam in place of having set a roof beam in place, and realizes big segment steel truss girder docking.)

1. a kind of docking facilities of big segment steel truss girder are used to dock two big segment steel truss girders, define two big Segment steel truss girder is set a roof beam in place section (A) and section to be set a roof beam in place (B);The big segment steel truss girder includes:

The several groups string beam element (1) of parallel interval setting, every group of string beam element (1) include one wind up (11), a lower edge (12), At least one winds up (11) and vertical bar (13) that lower edge (12) is connected and two are set to all vertical bars (13) with described Outside to extension bar (140);

Several cross bearers (2) wind up described in each adjacent two and are equipped at least two cross bearers (2) between (11), and two The cross bearer (2) is winded up the both ends of (11) described in being respectively arranged on two, the cross bearer (2) in section (B) to be set a roof beam in place with set a roof beam in place Cross bearer (2) in section (A) is oppositely arranged;

It is characterized in that, the docking facilities include:

First pair of drawing mechanism (3), one end are connect with the cross bearer (2) in section to be set a roof beam in place (B), the other end and section of having set a roof beam in place (A) corresponding cross bearer (2) connection in;When first pair of drawing mechanism (3) is when to drawing, the one of the section (B) to be set a roof beam in place is big Crossbeam (2) Xiang Suoshu corresponding cross bearer (2) in section (A) of having set a roof beam in place is close;

Second pair of drawing mechanism (4), both ends are respectively provided at the middle part of the set a roof beam in place section (A), section to be set a roof beam in place (B);When described When to drawing, a pair of of extension bar (140) Xiang Suoshu in the section (B) to be set a roof beam in place has set a roof beam in place corresponding in section (A) two pairs of drawing mechanisms (4) It is close to extension bar (140);

Top lifting mechanism (5) comprising lift up device (50);The lift up device (50) is set to winding up in the section (B) to be set a roof beam in place (11) on, and the top fixed setting of the lift up device (50);When the lift up device (50) upward top lifting, the section to be set a roof beam in place (B) it pushes.

2. the docking facilities of big segment steel truss girder as described in claim 1, which is characterized in that the top lifting mechanism (5) is also wrapped It includes:

One shoulder pole girder (52), one end are connect with wind up (11) in section of having set a roof beam in place (A), in the other end and section to be set a roof beam in place (B) It winds up (11) connection, the shoulder pole girder (52) is installed in the top of the lift up device (50);When the lift up device (50) pushes up upwards When playing shoulder pole girder (52), wind up (11) in the section (B) to be set a roof beam in place are moved downward.

3. the docking facilities of big segment steel truss girder as claimed in claim 2, which is characterized in that the top lifting mechanism (5) is also wrapped It includes:

Two third ear mounts (51), be installed in respectively section of having set a roof beam in place (A) wind up (11) and section to be set a roof beam in place (B) winds up (11) On, the both ends of the shoulder pole girder (52) pass through pin shaft (53) respectively and are detachably connected with two third ear mounts (51).

4. the docking facilities of big segment steel truss girder as described in claim 1, which is characterized in that first pair of drawing mechanism (3) Include:

Steel cable (32), both ends are connected with two opposite cross bearers (2) respectively;

Jack (33) is set at least one end of the steel cable (32), for shrinking the length of the steel cable (32).

5. the docking facilities of big segment steel truss girder as claimed in claim 4, which is characterized in that first pair of drawing mechanism (3) Further include:

Two first ear mounts (31), are installed in respectively in section of having set a roof beam in place (A) and section to be set a roof beam in place (B), each first ear mount (31) detachably it is connected with a steel cable (32).

6. the docking facilities of big segment steel truss girder as described in claim 1, which is characterized in that second pair of drawing mechanism (4) One end extension bar (140) is connect with section of having set a roof beam in place (A), close to this to extension bar (140) in the other end and section to be set a roof beam in place (B) Vertical bar (13) connection.

7. a kind of docking facilities of big segment steel truss girder are used to dock two big segment steel truss girders, define two big Segment steel truss girder is set a roof beam in place section (A) and section to be set a roof beam in place (B);The big segment steel truss girder includes:

The several groups string beam element (1) of parallel interval setting, every group of string beam element (1) include one wind up (11), a lower edge (12), At least one winds up (11) and vertical bar (13) that lower edge (12) is connected and two are set to all vertical bars (13) with described It is outer to extension bar (140);

Several cross bearers (2) wind up described in each adjacent two and are equipped at least two cross bearers (2) between (11), wait set a roof beam in place Cross bearer (2) in section (B) is oppositely arranged with the cross bearer (2) in section of having set a roof beam in place (A);

It is characterized in that, the docking facilities include:

First pair of drawing mechanism (3), one end for connect with the cross bearer (2) in section of having set a roof beam in place (A), the other end for to Corresponding cross bearer (2) connection in section of setting a roof beam in place (B);

Second pair of drawing mechanism (4), both ends are respectively used to be located at the middle part of the set a roof beam in place section (A), section to be set a roof beam in place (B);

Top lifting mechanism (5) comprising lift up device (50);The bottom of the lift up device (50) is used to be set to the section (B) to be set a roof beam in place In wind up on (11), top is for being fixedly installed;The lift up device (50) is used in upward top lifting, pushes described wait set a roof beam in place Section (B).

8. a kind of interconnection method of big segment steel truss girder, which is characterized in that the interconnection method passes through as described in claim 1 Docking facilities realize, the step of interconnection method includes:

Step 1: by section to be set a roof beam in place (B) all lower edges (12) in section of having set a roof beam in place (A) all lower edges (12) contraposition and it is right It connects;

Step 2: thick to align using first pair of drawing mechanism (3) to the cross bearer (2) for drawing section to be set a roof beam in place (B) with having set a roof beam in place in section (A) In section (B) to be set a roof beam in place to extension bar (140) with set a roof beam in place in section (A) to extension bar (140);

Step 3: using second pair of drawing mechanism (4) to the middle part for drawing section to be set a roof beam in place (B) with section (A) that set a roof beam in place, exactitude position is simultaneously right Reception set a roof beam in place in section (B) to extension bar (140) with set a roof beam in place in section (A) to extension bar (140);

Step 4: using lift up device (50) upward top lifting in top lifting mechanism (5), pushing winding up in the section (B) to be set a roof beam in place (11), align and dock it is described wind up (11), that is, complete the docking of big segment steel truss girder.

9. the interconnection method of big segment steel truss girder according to claim 8, which is characterized in that the specific step of the step 4 Suddenly include:

Step 401: reuse first pair of drawing mechanism (3) to the cross bearer (2) for drawing section to be set a roof beam in place (B) with having set a roof beam in place in section (A), It slightly aligns winding up in section to be set a roof beam in place (B) (11) and winds up (11) in section (A) with having set a roof beam in place;

Step 402: using lift up device (50) upward top lifting in top lifting mechanism (5), pushing winding up in the section (B) to be set a roof beam in place (11), exactitude position and (11) are winded up in section (A) with having set a roof beam in place to reception winding up in section (B) (11) of setting a roof beam in place.

10. the interconnection method of big segment steel truss girder according to claim 8, which is characterized in that first pair of drawing mechanism It (3) include the first ear mount (31) that second pair of drawing mechanism (4) includes the second ear mount, and the top lifting mechanism (5) includes third ear Seat (51);The step 1 further include:

Before docking lower edge (12), first ear mount (31), the second ear mount, third ear mount (51) are preset in and have been set a roof beam in place In section (A), section to be set a roof beam in place (B).

Technical field

The present invention relates to steel truss girder docking technique fields, and in particular to a kind of docking facilities of big segment steel truss girder and docking Method.

Background technique

With the fast development of economy and scientific and technical innovation, the bridge span in transport development is also progressively longer.Large span Bridge is mostly cable-stayed bridge, and for cable-stayed bridge, for especially combined heavily loaded cable-stayed bridge, compared to solid web girder, adopt It can reduce self weight with steel truss girder and increase rigidity to be better adapted to the load-carrying members compared with large span.

The installation of steel truss girder is by multiple segment steel truss girders mostly to realization is fetched, in the prior art, a kind of Conventional interconnection method is that temporary staging is set up below docking region, and setting is supported to the lower edge of frame steel truss girder on temporary staging, Adjustment winding up highly and to frame steel truss girder position to frame steel truss girder is suspended in midair by crane, and crane persistently suspends in midair, to butt welding After the completion, crane is removed.But when large span stayed-cable bridge uses big segment steel truss girder integral erection, due to big segment steel truss Beam has been formed from great stable structure, and therefore, front fulcrum counter-force is huge at Standing position of a crane, leads to the big segment steel truss of frame The position of beam and the banjo fixing butt jointing to frame steel truss girder is big in vertical, axially opposing deformation, in this case, according to above-mentioned normal Interconnection method is advised, big segment steel truss girder can not be directly docked by the way of punch.

Therefore, one of goal of the invention of the invention aims to solve the problem that problem of the big segment steel truss girder in docking.

Summary of the invention

In view of the deficiencies in the prior art, the purpose of the present invention is to provide a kind of big segment steel truss girders to tipping It sets and interconnection method, effectively adjusts the section and wait the relative deformation between section of setting a roof beam in place of having set a roof beam in place, realize big segment steel truss girder docking.

To achieve the above objectives, in a first aspect, the embodiment of the present invention provides a kind of docking facilities of big segment steel truss girder, For docking two big segment steel truss girders, defining two big segment steel truss girder is set a roof beam in place section and section to be set a roof beam in place;It is described Segment steel truss girder includes: greatly

The several groups string beam element of parallel interval setting, every group of string beam element include one wind up, a lower edge, at least one with It is described wind up the vertical bar being connected with lower edge and two be set to outside all vertical bars to extension bar;

Several cross bearers, wind up described in each adjacent two between be equipped at least two cross bearers, and two are described big Crossbeam be respectively arranged on two described in the both ends winded up, set wait the cross bearer in section of setting a roof beam in place is opposite with the cross bearer in section of having set a roof beam in place It sets;

The docking facilities include:

First pair of drawing mechanism, one end are connect with wait the cross bearer in section of setting a roof beam in place, and the other end is corresponding with section of having set a roof beam in place Cross bearer connection;When first pair of drawing mechanism is when to drawing, a cross bearer of the section to be set a roof beam in place is to the section of having set a roof beam in place In corresponding cross bearer it is close;

Second pair of drawing mechanism, both ends are respectively provided at the middle part of the set a roof beam in place section, section to be set a roof beam in place;It draws when described second Dui When to drawing, a pair of of extension bar wait in section of setting a roof beam in place is corresponding close to extension bar into the section of having set a roof beam in place for mechanism;

Top lifting mechanism comprising lift up device;The lift up device is set to described wait on winding up in section of setting a roof beam in place, and the top lifting The top of device is fixedly installed;When the upward top lifting of the lift up device, the section to be set a roof beam in place is pushed.

Based on the above technical solution, the top lifting mechanism further include:

One shoulder pole girder, one end are connect with winding up in section of having set a roof beam in place, and the other end is connect with wait winding up in section of setting a roof beam in place, institute State the top that shoulder pole girder is installed in the lift up device;When the lift up device jacks up the shoulder pole girder upwards, the section to be set a roof beam in place In wind up and move downward.

Based on the above technical solution, the top lifting mechanism further include:

Two third ear mounts, be installed in respectively section of having set a roof beam in place wind up and the winding up of section to be set a roof beam in place on, the shoulder pole girder Both ends pass through pin shaft respectively and are detachably connected with two third ear mounts.

Based on the above technical solution, first pair of drawing mechanism includes:

Steel cable, both ends are connected with two opposite cross bearers respectively;

Jack is set at least one end of the steel cable, for shrinking the length of the steel cable.

Based on the above technical solution, first pair of drawing mechanism further include:

Two first ear mounts are installed in the section and wait set a roof beam in place in section of having set a roof beam in place, described in each first ear mount and one respectively Steel cable is detachably connected.

Based on the above technical solution, extension bar is connect in one end of second pair of drawing mechanism and section of having set a roof beam in place, The other end is connect with wait the vertical bar in section of setting a roof beam in place close to this to extension bar.

Second aspect, the embodiment of the present invention also provide a kind of docking facilities of big segment steel truss girder, are used for big by two Segment steel truss girder is docked, and defining two big segment steel truss girder is set a roof beam in place section and section to be set a roof beam in place;The big segment steel truss girder Include:

The several groups string beam element of parallel interval setting, every group of string beam element include one wind up, a lower edge, at least one with It is described wind up the vertical bar being connected with lower edge and two be set to outside all vertical bars to extension bar;

Several cross bearers, wind up described in each adjacent two between be equipped at least two cross bearers, wait in section of setting a roof beam in place Cross bearer is oppositely arranged with the cross bearer in section of having set a roof beam in place;

The docking facilities include:

First pair of drawing mechanism, one end for connect with the cross bearer in section of having set a roof beam in place, the other end for wait set a roof beam in place Corresponding cross bearer connection in section;

Second pair of drawing mechanism, both ends are respectively used to be located at the middle part of the set a roof beam in place section, section to be set a roof beam in place;

Top lifting mechanism comprising lift up device;The bottom of the lift up device be used to be set to it is described wait winding up in section of setting a roof beam in place, Top is for being fixedly installed;The lift up device is used in upward top lifting, pushes the section to be set a roof beam in place.

The third aspect, the embodiment of the present invention also provide a kind of interconnection method of big segment steel truss girder, and the interconnection method is logical It crosses above-mentioned docking facilities such as to realize, the step of interconnection method includes:

Step 1: will align and dock with all lower edges in section of having set a roof beam in place wait all lower edges in section of setting a roof beam in place;

Step 2: using first pair of drawing mechanism to drawing Duan Yuyi to be set a roof beam in place to set a roof beam in place the cross bearer in section, slightly aligning section to be set a roof beam in place In to extension bar with set a roof beam in place in section to extension bar;

Step 3: using second pair of drawing mechanism to drawing Duan Yuyi to be set a roof beam in place to set a roof beam in place the middle part of section, exactitude position and to reception frame In beam section to extension bar with set a roof beam in place in section to extension bar;

Step 4: using the upward top lifting of lift up device in top lifting mechanism, pushing is described wait winding up in section of setting a roof beam in place, and contraposition is simultaneously It winds up described in docking, that is, completes the docking of big segment steel truss girder.

Based on the above technical solution, the specific steps of the step 4 include:

Step 401: reuse first pair of drawing mechanism to drawing Duan Yuyi to be set a roof beam in place to set a roof beam in place the cross bearer in section, thick contraposition to Winding up and winding up in section of having set a roof beam in place in section of setting a roof beam in place;

Step 402: using the upward top lifting of lift up device in top lifting mechanism, pushing is described wait winding up in section of setting a roof beam in place, accurately It aligns and sets a roof beam in place winding up and winding up in section of having set a roof beam in place in section to reception.

Based on the above technical solution, first pair of drawing mechanism includes the first ear mount, second pair of drawing mechanism Including the second ear mount, the top lifting mechanism includes third ear mount;The step 1 further include:

Before docking lower edge, first ear mount, the second ear mount, third ear mount are preset in section of having set a roof beam in place, to frame In beam section.

Compared with the prior art, the advantages of the present invention are as follows:

(1) embodiment of the present invention provides a kind of docking facilities of big segment steel truss girder, at the docking of big segment steel truss girder Reasonable layout regulating device effectively adjusts the relative deformation set a roof beam in place between section and the banjo fixing butt jointing of section to be set a roof beam in place, and realizes big section The rapid abutting joint construction of section steel truss girder, improves joint quality.

(2) regulating device used in the embodiment of the present invention, structure is simple, and can Reusability, improve utilization rate, reduce work Cheng Chengben.

(3) embodiment of the present invention provides a kind of interconnection method of big segment steel truss girder, and this method is in particular order, right The relative deformation set a roof beam in place between section and the banjo fixing butt jointing of section to be set a roof beam in place should be adjusted, realizes that the rapid abutting joint of big segment steel truss girder is applied Work improves joint quality and sets up work efficiency.

Detailed description of the invention

Fig. 1 is the docking facilities facade arrangement schematic diagram of big segment steel truss girder in the embodiment of the present invention;

Fig. 2 is the docking facilities side arrangement schematic diagram of big segment steel truss girder in the embodiment of the present invention;

Fig. 3 is that the vertical view of the docking facilities of the big segment steel truss girder of the embodiment of the present invention arranges simplified schematic diagram;

Fig. 4 is the schematic diagram of top lifting mechanism and Fig. 1 same view angle;

Fig. 5 is the schematic diagram of first pair of drawing mechanism and Fig. 1 same view angle;

In figure: 1, string beam element;11, it winds up;12, lower edge;13, vertical bar;14, brace;140, to extension bar;2, big horizontal Beam;3, first pair of drawing mechanism;31, the first ear mount;32, wrap-up;33, steel cable;34, nut;4, second pair of drawing mechanism;5, it rises Push up mechanism;50, lift up device;51, third ear mount;52, shoulder pole girder;53, pin shaft;A, it has set a roof beam in place section;B, section to be set a roof beam in place.

Specific embodiment

The present invention is described in further detail below through specific implementation examples and in conjunction with the accompanying drawings.