Mounting method for newly-built reheating type double-suction-pipe coke oven coal charging car

文档序号:1793702 发布日期:2021-11-05 浏览:20次 中文

阅读说明:本技术 用于新建复热式双吸气管焦炉装煤车的安装方法 (Mounting method for newly-built reheating type double-suction-pipe coke oven coal charging car ) 是由 贾玲 于 2021-08-26 设计创作,主要内容包括:本发明公开了一种安装方法,尤其是公开了一种用于新建复热式双吸气管焦炉装煤车的安装方法,属于工程建设施工工艺技术领域。提供一种适宜在施工场地较窄,施工操作受到限制的环境下进行施工的用于新建复热式双吸气管焦炉装煤车的安装方法。述的安装方法以安装完成装煤车轨道且无干衍一端的炉端台为安装平台,通过起重设备分先后在检测合格的装煤车轨道上沿长度方向顺序的组装两台所述的装煤车完成新建复热式双吸气管焦炉装煤车的安装。(The invention discloses an installation method, in particular discloses an installation method for a newly-built reheating type double-suction-pipe coke oven coal charging car, and belongs to the technical field of engineering construction processes. The installation method is suitable for construction in the environment with narrow construction site and limited construction operation and is used for installing the newly-built reheating type double-suction-pipe coke oven coal charging car. The installation method takes a furnace end platform at the end where the coal charging car track is installed and the end without the dry-extension end as an installation platform, and two coal charging cars are sequentially assembled on the coal charging car track which is detected to be qualified along the length direction through hoisting equipment to complete the installation of the newly-built reheating type double-suction-pipe coke oven coal charging car.)

1. A mounting method for a newly-built reheating type double-air-suction-pipe coke oven coal charging car is characterized by comprising the following steps: the installation method takes a furnace end platform which is installed on the coal charging car track (1) and has no dry end as an installation platform, and two coal charging cars (2) are sequentially assembled on the coal charging car track (1) which is detected to be qualified along the length direction through hoisting equipment to complete the installation of the newly-built reheating double-suction-pipe coke oven coal charging car.

2. The installation method of the newly-built reheating type double-suction-pipe coke oven coal charging car according to claim 1, which is characterized in that: when the length of the coal charging car track (1) is not enough to arrange two coal charging cars (2) in sequence, the temporary length supplement is carried out on the coal charging car track (1) at the far end of the furnace end platform to reach the standard of arranging the two coal charging cars (2) in sequence.

3. The installation method for the newly-built reheating type double-suction-pipe coke oven coal charging car according to claim 1 or 2, which is characterized in that: the furnace end platform is arranged on one side of the elevator.

4. The installation method for the newly-built reheating type double-suction-pipe coke oven coal charging car according to claim 3, characterized in that: the hoisting equipment is a movable truck crane on site.

5. The installation method for the newly-built reheating type double-suction-pipe coke oven coal charging car according to claim 2, characterized in that: the added lengthening rail is an auxiliary rail with the same type as the working rail when the coal charging car runs.

6. The installation method of the newly-built reheating type double-suction-pipe coke oven coal charging car according to claim 5, which is characterized in that: and the auxiliary track is laid and lengthened on the basis of the newly built furnace end platform.

7. The installation method of the newly-built reheating type double-suction-pipe coke oven coal charging car according to claim 6, which is characterized in that: the coal charging car at least comprises a steel structure, a walking device, a cover uncovering and guide sleeve device, a spiral feeding device, a furnace top cleaning device, a rising pipe operating device, a dust collecting device, an air conditioning system, an air path system, a rising pipe cleaning device, a centralized lubricating system, a hydraulic system and an electrical system.

8. The installation method of the newly-built reheating type double-suction-pipe coke oven coal charging car according to claim 7, which is characterized in that: when the coal charging cars are installed, the coal charging cars are assembled one by one on the track from inside to outside, and the assembly of each coal charging car is carried out according to the following steps,

1) determination of installation reference

The central line of the coal charging car track and the central line of the coal charging port are taken as datum lines of the coal charging car, the datum lines and the coal charging port are perpendicular to each other, the vertical tolerance is 0.1/1000, and the limit deviation of each installation central line is +/-2 mm;

2) according to the installation height of the coal charging car, the maximum weight of the single piece and the overall dimension of the structure, one 150t truck crane is used for hoisting, the placing directions of the coal charging car side and the coke side are determined before hoisting, and then hoisting is carried out;

3) mounting running gear

A. The running gear is arranged on the coke side and then is hung on the rail which is checked and confirmed, the mutual position fixation is well adjusted, and sleepers and other positioning blocks are adopted for fixation when the running gear is rotated and fixed,

B. measuring and checking the inspection items according to the requirements of the inspection outline,

C. installing a walking driving part and tightening a shaft coupler;

4) mounting steel structure

The steel structure of the coal charging car consists of a steel structure main body, a cab, an electric room, a corridor, a ladder, a railing, a rain-proof plate and a buffer, and all the steel structure is transported to a construction site in bulk;

A. firstly, a steel structure main body is installed, the installation size requires that the verticality of the component is less than 1/1000,

B. the cab is installed, the electric control operating board, the main power switch cabinet and the air-conditioning cooler are installed in the cab before the cab is installed,

C. installing an electric room, installing a control cabinet, a PLC cabinet and an indoor unit of an air conditioner into the electric room before installing the electric room,

D. a walking platform, a ladder, a railing and a rain-proof plate are arranged,

E. the buffer is installed, the vertical direction of the front and back directions is adjusted by the elastic thread insert,

F. finally, mounting the remaining small parts;

5) mounting of uncovering and guiding device

Each coal charging car has four coal charging holes, so that each coal charging car needs four sets of cover uncovering and guide sleeve devices, the centers of the four sets of cover uncovering and guide sleeve devices are on the same line, and the allowable deviation is +/-3 mm.

The installation of the uncovering device should comply with the following regulations,

A. when each electromagnet is in the working position, the center of each electromagnet is coincided with the center of the corresponding coal charging port, the limit deviation is +/-20 mm,

B. the limit deviation of the upper limit of the uncovering mechanism is +/-10 mm, the limit deviation of the lower limit position is 0 to +20mm,

6) screw feeder mounting

The spiral feeding device comprises a spiral feeder, a coal hopper, a connecting rod mechanism, a coal hopper walking platform, a ladder and a railing,

the screw feeder installation should comply with the following regulations,

A. firstly, the coal hopper is arranged on the platform, then the spiral feeder is arranged,

B. the limit deviation of the center of each coal hopper and the center line of the track of the coal charging car is +/-15 mm, the limit deviation of the coal hopper and the center line of the coal charging port is +/-15 mm, the limit deviation of the distance between the center lines of two adjacent coal hoppers is +/-20 mm, the limit deviation of the elevation of the top surface of each coal hopper is +/-25 mm, the verticality of each coal hopper is not more than 2/1000,

C. the screw feeder is installed to ensure that the levelness is not more than 1/1000,

D. the center of each feed opening is superposed with the center of the corresponding coal charging opening, the deviation value is +10mm, the limit deviation of the upper limit position of the feed cover cylinder is +/-10 mm, the limit deviation of the lower limit position is 0 to +30mm,

E. the connection part of the coal hopper and the spiral feeder, the connection part of the feed opening of the spiral feeder and the guide sleeve and the connection part of the coal hopper and the steel structure are required to be tightly connected, and an adjusting base plate is required to be added for adjustment when necessary;

7) mounting of furnace roof cleaning device

The furnace top cleaning device is packaged with a dust collection trolley, a chain mechanism, a cloth bag dust collector, a silencer, a centrifugal ventilator, a bracket and a pipeline,

the furnace top cleaning device should meet the following regulations:

A. the verticality of the cloth bag dust collector is not more than 2/1000,

B. the centrifugal fan is integrally installed to ensure that the levelness is not more than 1/1000,

C. the extreme errors of the longitudinal center line, the transverse center line and the elevation of each component are +/-5 mm;

8) mounting of riser handling device

The ascending pipe operating device comprises an ammonia water conversion machine and a cover closing mechanism, and is integrally supplied after being assembled by a manufacturer, and the ultimate errors of longitudinal and transverse center lines and elevation are required to be +/-5 mm after the ascending pipe operating device is installed;

9) mounting of dust collecting devices

The dust collecting device comprises a valve and a pipeline;

10) air conditioning system, in-coke lubricating system, hydraulic system and pneumatic system installation

A. The air conditioning system, the coke-oven lubricating system, the hydraulic system and the pneumatic system mainly adopt pipeline installation, each system is preassembled and self-checked in a manufacturer, only recovery installation is carried out on site, the installation requirement is as follows,

the cleaning of hands is needed to be kept when the hydraulic and lubricating pipelines are recovered, the pipelines are not polluted,

B. the hydraulic and pneumatic piping meets the condition that the hose is not broken or extruded during the piping stroke among all mechanisms.

Technical Field

The invention relates to an installation method, in particular to an installation method for a newly-built reheating type double-suction-pipe coke oven coal charging car, and belongs to the technical field of engineering construction processes.

Background

The coal charging car of a certain model of the reheating double-suction-pipe coke oven has 2 coal charging cars, and each coal charging car has the single weight of 170 t. The construction characteristics are as follows: the construction process is many, and the equipment volume is big, and the operating point is many, characteristics such as construction site is narrow and small. The coal charging car of the newly-built coke oven cannot be installed on the coke oven body due to the influence of the construction of the coke oven body and the temporary greenhouse for construction, generally is installed on the oven end platforms at two sides of the coke oven, and generally is installed separately from one another at one side. In the construction of the furnace end platform, one side is the construction of the coke guide and the track thereof, one side is the construction of the coke pusher and the track thereof, and the other side is the construction of the coke oven body, and only one side of the material elevator is left to be constructed by using large-scale equipment. How to adapt the construction progress of the coke oven coal charging car to the construction progress of other parts under the limited construction environment and further meet the construction requirements becomes a technical problem which needs to be solved urgently by technical personnel in the field.

Disclosure of Invention

The technical problem to be solved by the invention is as follows: the installation method is suitable for construction in the environment with narrow construction site and limited construction operation and is used for installing the newly-built reheating type double-suction-pipe coke oven coal charging car.

The technical scheme adopted for solving the technical problems is as follows: the installation method is characterized in that a furnace end platform which is installed on a coal charging car track and has no end extending is used as an installation platform, and two coal charging cars are sequentially assembled on the coal charging car track which is detected to be qualified along the length direction through hoisting equipment to complete the installation of the newly-built coal charging car with the double heat absorption pipes.

Further, when the length of the coal charging car track is not enough to arrange two coal charging cars in sequence, the temporary length supplement is carried out on the coal charging car track at the far end of the furnace end platform so as to reach the standard of arranging two coal charging cars in sequence.

In a preferred mode of the above-described aspect, the furnace end table is a furnace end table on the side of the hoist.

Further, the hoisting equipment is a field movable truck crane.

The preferable mode of the scheme is that the added lengthening rail is an auxiliary rail with the same type as the working rail when the coal charging car runs.

Furthermore, the auxiliary track is paved and lengthened on the basis of the newly built furnace end platform.

The coal charging car at least comprises a steel structure, a traveling device, a cover uncovering and guide sleeve device, a spiral feeding device, a furnace top cleaning device, an ascending pipe operating device, a dust collecting device, an air conditioning system, an air path system, an ascending pipe cleaning device, a centralized lubricating system, a hydraulic system and an electric system.

Furthermore, when the coal charging cars are installed, the coal charging cars are assembled one by one on the track from inside to outside, and the assembly of each coal charging car is carried out according to the following steps,

1) determination of installation reference

The central line of the coal charging car track and the central line of the coal charging port are taken as datum lines of the coal charging car, the datum lines and the coal charging port are perpendicular to each other, the vertical tolerance is 0.1/1000, and the limit deviation of each installation central line is +/-2 mm;

2) according to the installation height of the coal charging car, the maximum weight of the single piece and the overall dimension of the structure, one 150t truck crane is used for hoisting, the placing directions of the coal charging car side and the coke side are determined before hoisting, and then hoisting is carried out;

3) mounting running gear

A. The running gear is arranged on the coke side and then is hung on the rail which is checked and confirmed, the mutual position fixation is well adjusted, and sleepers and other positioning blocks are adopted for fixation when the running gear is rotated and fixed,

B. measuring and checking the inspection items according to the requirements of the inspection outline,

C. installing a walking driving part and tightening a shaft coupler;

4) mounting steel structure

The steel structure of the coal charging car consists of a steel structure main body, a cab, an electric room, a corridor, a ladder, a railing, a rain-proof plate and a buffer, and all the steel structure is transported to a construction site in bulk;

A. firstly, a steel structure main body is installed, the installation size requires that the verticality of the component is less than 1/1000,

B. the cab is installed, the electric control operating board, the main power switch cabinet and the air-conditioning cooler are installed in the cab before the cab is installed,

C. installing an electric room, installing a control cabinet, a PLC cabinet and an indoor unit of an air conditioner into the electric room before installing the electric room,

D. a walking platform, a ladder, a railing and a rain-proof plate are arranged,

E. the buffer is installed, the vertical direction of the front and back directions is adjusted by the elastic thread insert,

F. finally, mounting the remaining small parts;

5) mounting of uncovering and guiding device

Each coal charging car has four coal charging holes, so that each coal charging car needs four sets of cover uncovering and guide sleeve devices, the centers of the four sets of cover uncovering and guide sleeve devices are on the same line, and the allowable deviation is +/-3 mm.

The installation of the uncovering device should comply with the following regulations,

A. when each electromagnet is in the working position, the center of each electromagnet is coincided with the center of the corresponding coal charging port, the limit deviation is +/-20 mm,

B. the limit deviation of the upper limit of the uncovering mechanism is +/-10 mm, the limit deviation of the lower limit position is 0 to +20mm,

6) screw feeder mounting

The spiral feeding device comprises a spiral feeder, a coal hopper, a connecting rod mechanism, a coal hopper walking platform, a ladder and a railing,

the screw feeder installation should comply with the following regulations,

A. firstly, the coal hopper is arranged on the platform, then the spiral feeder is arranged,

B. the limit deviation of the center of each coal hopper and the center line of the track of the coal charging car is +/-15 mm, the limit deviation of the coal hopper and the center line of the coal charging port is +/-15 mm, the limit deviation of the distance between the center lines of two adjacent coal hoppers is +/-20 mm, the limit deviation of the elevation of the top surface of each coal hopper is +/-25 mm, the verticality of each coal hopper is not more than 2/1000,

C. the screw feeder is installed to ensure that the levelness is not more than 1/1000,

D. the center of each feed opening is superposed with the center of the corresponding coal charging opening, the deviation value is +10mm, the limit deviation of the upper limit position of the feed cover cylinder is +/-10 mm, the limit deviation of the lower limit position is 0 to +30mm,

E. the connection part of the coal hopper and the spiral feeder, the connection part of the feed opening of the spiral feeder and the guide sleeve and the connection part of the coal hopper and the steel structure are required to be tightly connected, and an adjusting base plate is required to be added for adjustment when necessary;

7) mounting of furnace roof cleaning device

The furnace top cleaning device is packaged with a dust collection trolley, a chain mechanism, a cloth bag dust collector, a silencer, a centrifugal ventilator, a bracket and a pipeline,

the furnace top cleaning device should meet the following regulations:

A. the verticality of the cloth bag dust collector is not more than 2/1000,

B. the centrifugal fan is integrally installed to ensure that the levelness is not more than 1/1000,

C. the extreme errors of the longitudinal center line, the transverse center line and the elevation of each component are +/-5 mm;

8) mounting of riser handling device

The ascending pipe operating device comprises an ammonia water conversion machine and a cover closing mechanism, and is integrally supplied after being assembled by a manufacturer, and the ultimate errors of longitudinal and transverse center lines and elevation are required to be +/-5 mm after the ascending pipe operating device is installed;

9) mounting of dust collecting devices

The dust collecting device comprises a valve and a pipeline;

10) air conditioning system, in-coke lubricating system, hydraulic system and pneumatic system installation

A. The air conditioning system, the coke-oven lubricating system, the hydraulic system and the pneumatic system mainly adopt pipeline installation, each system is preassembled and self-checked in a manufacturer, only recovery installation is carried out on site, the installation requirement is as follows,

the cleaning of hands is needed to be kept when the hydraulic and lubricating pipelines are recovered, the pipelines are not polluted,

B. the hydraulic and pneumatic piping meets the condition that the hose is not broken or extruded during the piping stroke among all mechanisms.

The invention has the beneficial effects that: according to the construction method, the furnace end platform which is installed on the coal charging car track and has no dry end is used as an installation platform, and two coal charging cars are sequentially assembled on the coal charging car track which is detected to be qualified along the length direction through hoisting equipment to complete the installation of the newly-built reheating type double-suction-pipe coke oven coal charging car. The construction method fully utilizes one relatively idle furnace end platform in four side surfaces of the coke furnace as a foundation, then two coal charging car pairs are sequentially assembled on the coal charging car track along the length direction, and after the construction of the coke furnace is finished or when the construction is proper, the coal charging car assembled on the inner side is moved to the other side through the track, so that the construction method provided by the application can be suitable for cross simultaneous construction of the coal charging car and other processes in the environment with narrow construction site and limited construction operation, the construction period is shortened, and the construction requirement is met. The coal charging car is particularly suitable for being installed when equipment arrives at a night and a construction site is narrow.

Drawings

FIG. 1 is a schematic view of an installation structure involved in the installation method for a newly-built reheating type double-suction-pipe coke oven coal charging car of the invention;

fig. 2 is a top view of fig. 1.

Labeled as: a coal charging car track (1) and a coal charging car (2).

Detailed Description

As shown in figures 1 and 2, the invention provides a method for installing a newly-built reheating double-suction-pipe coke oven coal charging car, which is suitable for construction in an environment with a narrow construction site and limited construction operation. The installation method takes a furnace end platform which is installed on the coal charging car track (1) and has no dry end as an installation platform, and two coal charging cars (2) are sequentially assembled on the coal charging car track (1) which is detected to be qualified along the length direction through hoisting equipment to complete the installation of the newly-built reheating double-suction-pipe coke oven coal charging car. According to the construction method, the furnace end platform which is installed on the coal charging car track and has no dry end is used as an installation platform, and two coal charging cars are sequentially assembled on the coal charging car track which is detected to be qualified along the length direction through hoisting equipment to complete the installation of the newly-built reheating type double-suction-pipe coke oven coal charging car. The construction method fully utilizes one relatively idle furnace end platform in four side surfaces of the coke furnace as a foundation, then two coal charging car pairs are sequentially assembled on the coal charging car track along the length direction, and after the construction of the coke furnace is finished or when the construction is proper, the coal charging car assembled on the inner side is moved to the other side through the track, so that the construction method provided by the application can be suitable for cross simultaneous construction of the coal charging car and other processes in the environment with narrow construction site and limited construction operation, the construction period is shortened, and the construction requirement is met. The coal charging car is particularly suitable for being installed when equipment arrives at a night and a construction site is narrow.

In the above embodiment, according to the construction environment of the construction site, and the structural characteristics and characteristics of the coke oven itself, when the length of the coal charging car track (1) is not long enough to arrange two coal charging cars (2) in sequence, the temporary additional length of the coal charging car track (1) at the far end of the oven end platform is used to achieve the purpose of arranging two coal charging cars (2) in sequence. Certainly, when the length of the coal charging car track (1) is not long enough to sequentially arrange two coal charging cars (2), the coal charging cars can be arranged in a supporting mode, namely, a fixed support is erected at a supporting point of the existing track of the coke oven hung out of the coal charging car, then the coal charging car (2) is assembled by taking the fixed support as the supporting point, the assembly operation is inconvenient only by adopting the supporting point, and an operation platform needs to be erected outside the supporting point at the same time. According to the construction environment condition of the site, the furnace end platform is the furnace end platform on one side of the elevator. Correspondingly, the hoisting equipment is a field movable truck crane. Simultaneously, for the convenience of erectting, do not increase more purchasing cost, according to the actual situation that the scene has leftover bits usually, the supplementary long rail that this application increased is the auxiliary rail the same with the work track model when the coal charging car operation. Of course, the auxiliary track is laid and lengthened on the basis of the newly built furnace end platform.

Furthermore, the coal charging car at least comprises the structural characteristics of a steel structure, a traveling device, a cover uncovering and guiding device, a spiral feeding device, a furnace top cleaning device, an ascending pipe operating device, a dust collecting device, an air conditioning system, an air path system, an ascending pipe cleaning device, a centralized lubricating system, a hydraulic system and an electrical system, and the assembly of each coal charging car is carried out according to the following steps,

1) determination of installation reference

The central line of the coal charging car track and the central line of the coal charging port are taken as datum lines of the coal charging car, the datum lines and the coal charging port are perpendicular to each other, the vertical tolerance is 0.1/1000, and the limit deviation of each installation central line is +/-2 mm;

2) according to the installation height of the coal charging car, the maximum weight of the single piece and the overall dimension of the structure, one 150t truck crane is used for hoisting, the placing directions of the coal charging car side and the coke side are determined before hoisting, and then hoisting is carried out;

3) mounting running gear

A. The running gear is arranged on the coke side and then is hung on the rail which is checked and confirmed, the mutual position fixation is well adjusted, and sleepers and other positioning blocks are adopted for fixation when the running gear is rotated and fixed,

B. measuring and checking the inspection items according to the requirements of the inspection outline,

C. installing a walking driving part and tightening a shaft coupler;

4) mounting steel structure

The steel structure of the coal charging car consists of a steel structure main body, a cab, an electric room, a corridor, a ladder, a railing, a rain-proof plate and a buffer, and all the steel structure is transported to a construction site in bulk;

A. firstly, a steel structure main body is installed, the installation size requires that the verticality of the component is less than 1/1000,

B. the cab is installed, the electric control operating board, the main power switch cabinet and the air-conditioning cooler are installed in the cab before the cab is installed,

C. installing an electric room, installing a control cabinet, a PLC cabinet and an indoor unit of an air conditioner into the electric room before installing the electric room,

D. a walking platform, a ladder, a railing and a rain-proof plate are arranged,

E. the buffer is installed, the vertical direction of the front and back directions is adjusted by the elastic thread insert,

F. finally, mounting the remaining small parts;

5) mounting of uncovering and guiding device

Each coal charging car has four coal charging holes, so that each coal charging car needs four sets of cover uncovering and guide sleeve devices, the centers of the four sets of cover uncovering and guide sleeve devices are on the same line, and the allowable deviation is +/-3 mm.

The installation of the uncovering device should comply with the following regulations,

A. when each electromagnet is in the working position, the center of each electromagnet is coincided with the center of the corresponding coal charging port, the limit deviation is +/-20 mm,

B. the limit deviation of the upper limit of the uncovering mechanism is +/-10 mm, the limit deviation of the lower limit position is 0 to +20mm,

6) screw feeder mounting

The spiral feeding device comprises a spiral feeder, a coal hopper, a connecting rod mechanism, a coal hopper walking platform, a ladder and a railing,

the screw feeder installation should comply with the following regulations,

A. firstly, the coal hopper is arranged on the platform, then the spiral feeder is arranged,

B. the limit deviation of the center of each coal hopper and the center line of the track of the coal charging car is +/-15 mm, the limit deviation of the coal hopper and the center line of the coal charging port is +/-15 mm, the limit deviation of the distance between the center lines of two adjacent coal hoppers is +/-20 mm, the limit deviation of the elevation of the top surface of each coal hopper is +/-25 mm, the verticality of each coal hopper is not more than 2/1000,

C. the screw feeder is installed to ensure that the levelness is not more than 1/1000,

D. the center of each feed opening is superposed with the center of the corresponding coal charging opening, the deviation value is +10mm, the limit deviation of the upper limit position of the feed cover cylinder is +/-10 mm, the limit deviation of the lower limit position is 0 to +30mm,

E. the connection part of the coal hopper and the spiral feeder, the connection part of the feed opening of the spiral feeder and the guide sleeve and the connection part of the coal hopper and the steel structure are required to be tightly connected, and an adjusting base plate is required to be added for adjustment when necessary;

7) mounting of furnace roof cleaning device

The furnace top cleaning device is packaged with a dust collection trolley, a chain mechanism, a cloth bag dust collector, a silencer, a centrifugal ventilator, a bracket and a pipeline,

the furnace top cleaning device should meet the following regulations:

A. the verticality of the cloth bag dust collector is not more than 2/1000,

B. the centrifugal fan is integrally installed to ensure that the levelness is not more than 1/1000,

C. the extreme errors of the longitudinal center line, the transverse center line and the elevation of each component are +/-5 mm;

8) mounting of riser handling device

The ascending pipe operating device comprises an ammonia water conversion machine and a cover closing mechanism, and is integrally supplied after being assembled by a manufacturer, and the ultimate errors of longitudinal and transverse center lines and elevation are required to be +/-5 mm after the ascending pipe operating device is installed;

9) mounting of dust collecting devices

The dust collecting device comprises a valve and a pipeline;

10) air conditioning system, in-coke lubricating system, hydraulic system and pneumatic system installation

A. The air conditioning system, the coke-oven lubricating system, the hydraulic system and the pneumatic system mainly adopt pipeline installation, each system is preassembled and self-checked in a manufacturer, only recovery installation is carried out on site, the installation requirement is as follows,

the cleaning of hands is needed to be kept when the hydraulic and lubricating pipelines are recovered, the pipelines are not polluted,

B. the hydraulic and pneumatic piping meets the condition that the hose is not broken or extruded during the piping stroke among all mechanisms.

In summary, the construction method provided by the application can start from reasonable allocation personnel, saving of crane shifts and construction period, and adopts a construction sequence of synchronous installation of two coal charging cars at the 1# furnace end platform. Because 1 coal charging car is more than 15m long, two coal charging cars need to be installed at one side of the furnace end platform at the same time, the formal track length of the coal charging car on the one side of the furnace end platform is not enough, and the coal charging car needs to be lengthened. And (3) lengthening the track with the formal track model of the coal charging car, and performing lengthening point selection on a side platform beam of the material lifter of the 1# furnace end platform. The synchronous installation that carries out two coal charging cars at 1# stove end platform that this application adopted is particularly suitable for the equipment to arrive the goods evening, the coal charging car installation when the construction site is narrow.

DETAILED DESCRIPTION OF EMBODIMENT (S) OF INVENTION

1) The coal charging car of the newly-built coke oven cannot be installed on the coke oven body due to the influence of the construction of the coke oven body and the temporary greenhouse for construction, generally is installed on the oven end platforms at two sides of the coke oven, and generally is installed separately from one another at one side. In the construction of the furnace end platform, due to the construction of the coke guide and the track thereof on one side and the construction of the coke pusher and the track thereof on one side, the construction of the coke oven body on one side is realized, and only one side of the hoister is left to organize the construction by using large-scale equipment.

2) Because 1 coal charging car is more than 15m long, two coal charging cars need to be installed at one side of the furnace end platform at the same time, the formal track length of the coal charging car on the one side of the furnace end platform is not enough, and the coal charging car needs to be lengthened.

3) And (3) lengthening the track with the formal track model of the coal charging car, and performing lengthening point selection on a side platform beam of the material lifter of the 1# furnace end platform.

4) The coal charging car has the installation height of 14.28m, the maximum single piece is 11 tons, the size is large, the station cannot be close to each other, and a 150t truck crane is arranged for hoisting. During hoisting, the placing directions of the coal loader and the coke side are determined so as to avoid finding direction errors after assembly.