Treatment method for water seepage prevention of rabbet pipe connector of reinforced concrete pipe

文档序号:1000511 发布日期:2020-10-23 浏览:29次 中文

阅读说明:本技术 一种钢筋砼管企口管连接口防渗水的处理方法 (Treatment method for water seepage prevention of rabbet pipe connector of reinforced concrete pipe ) 是由 朱年华 余劲松 程平 朱清华 朱冬明 于 2020-07-22 设计创作,主要内容包括:本发明公开了一种钢筋砼管企口管连接口防渗水的处理方法,具体包括如下步骤:步骤1:钢筋砼管的基本处理,步骤2:防水粘合剂的基本涂抹,步骤3:防漏油毡布的初步安装,步骤4:双层油毡布的安装,步骤5:布料安装后的抽样测试,本发明涉及防渗水技术领域。该钢筋砼管企口管连接口防渗水的处理方法,通过步骤1和步骤2的联合设置,使得钢筋砼管企口管的表面不合格连接处被有效清理,使得后期两管之间的连接更为顺畅,同时使用水分对连接处进行湿润,使得防水粘合剂的涂抹能够更加均匀,同时采用均匀交叉涂抹,使得防水粘合剂与钢筋砼管之间具有较强的连接力,并且避免涂刷过厚,减少了局部厚薄悬殊太大导致的裂纹。(The invention discloses a method for treating water seepage prevention of a rabbet pipe connector of a reinforced concrete pipe, which specifically comprises the following steps: step 1: basic processing of reinforced concrete pipes, step 2: basic application of waterproof adhesive, step 3: preliminary installation of the leak-proof felt cloth, and step 4: mounting double-layer felt cloth, and step 5: the invention discloses a sampling test after cloth installation, and relates to the technical field of water seepage prevention. This reinforced concrete pipe rabbet mouth pipe connector prevention of seepage water processing method, through the joint setting of step 1 and step 2, make the unqualified junction in surface of reinforced concrete pipe rabbet mouth pipe effectively cleared up, make the connection between two pipes more smooth and easy in the later stage, use moisture to carry out the moist to the junction simultaneously, make the paining of waterproof adhesive can be more even, adopt even cross paining simultaneously, make waterproof adhesive and reinforced concrete pipe between have stronger engaging force, and avoid painting with a brush the excessive thickness, reduced the crackle that local thickness discrepancy greatly leads to.)

1. A method for treating the seepage prevention of a rabbet pipe connector of a reinforced concrete pipe is characterized by comprising the following steps: the method specifically comprises the following steps:

step 1: basic treatment of reinforced concrete pipes: sleeving a fixing sleeve in the middle of the reinforced concrete pipe, hoisting the reinforced concrete pipe in the middle of the reinforced concrete pipe by using a crane, wiping the surface and the joint of the rabbet pipe of the reinforced concrete pipe, removing impurities and large-particle dust, plugging and leveling honeycombs, holes and cracks at the joint by using plugging mortar, removing sharp edges and bulges, completely checking the honeycomb, holes and cracks after cleaning, and fully wetting the surface of the joint by using water before formal work;

step 2: basic application of waterproof adhesive: adding high molecular polymer powder, synthetic rubber, synthetic styrene ester, a dispersing agent, a defoaming agent and a surfactant into a reaction kettle, fully stirring, heating the mixture, keeping the temperature for 10-20 minutes when the temperature is heated to 45-55 ℃, and uniformly coating the liquid mixed waterproof adhesive on the surface of a joint by using a rag;

and step 3: preliminary installation of leak protection felt cloth: after the two rabbet pipes of the reinforced concrete pipe to be connected are coated with a waterproof adhesive, the rabbet pipes are manually aligned and clamped, then the leakproof felt cloth on one side is firstly fixed on the outer side of the joint, and the leakproof felt cloth rotates for 1.5 to 2.5 circles around the reinforced concrete pipe;

and 4, step 4: installation of double-layer felt cloth: after the first layer of leakage-proof felt cloth is installed, waiting for 10-15 minutes, uniformly coating a waterproof adhesive on the surface of the first layer of leakage-proof felt cloth, then installing waterproof felt cloth on the surface of the adhesive, and after winding is finished, detecting whether the surfaces of the two connecting pipelines are positioned on the same horizontal line;

and 5: sampling test after cloth installation: and after the complete installation, placing the reinforced concrete pipe tongue-and-groove pipe in the material bin, sampling and testing the reinforced concrete pipe before transferring, and marking and detecting products in the same batch one by one after finding unqualified products.

2. The treatment method of the seepage prevention of the rabbet pipe connecting port of the reinforced concrete pipe as claimed in claim 1, characterized in that: in the step 1, the slow-setting type plugging slurry is applied to the loose and porous basal plane for smoothing.

3. The treatment method of the seepage prevention of the rabbet pipe connecting port of the reinforced concrete pipe as claimed in claim 1, characterized in that: in the step 2, the materials can be heated after the materials are completely added.

4. The treatment method of the seepage prevention of the rabbet pipe connecting port of the reinforced concrete pipe as claimed in claim 1, characterized in that: in the step 2, a painting brush operation must be used when the waterproof adhesive is painted, and the painting directions of each layer are perpendicular to each other.

5. The treatment method of the seepage prevention of the rabbet pipe connecting port of the reinforced concrete pipe as claimed in claim 1, characterized in that: in the step 4, the number of winding turns of the anti-leakage felt cloth is equal to that in the step 3.

6. The treatment method of the seepage prevention of the rabbet pipe connecting port of the reinforced concrete pipe as claimed in claim 1, characterized in that: in the step 5, the sampling test is specifically implemented by adopting an equidistant sampling method.

7. The treatment method of the seepage prevention of the rabbet pipe connecting port of the reinforced concrete pipe as claimed in claim 1, characterized in that: in the step 3, when the asphalt felt cloth rotates around the reinforced concrete pipe, the anti-leakage asphalt felt cloth on the surface of the reinforced concrete pipe needs to be tensioned manually.

8. The treatment method of the seepage prevention of the rabbet pipe connecting port of the reinforced concrete pipe as claimed in claim 1, characterized in that: and in the step 2, heating the material in a waterproof way.

Technical Field

The invention relates to the technical field of water seepage prevention, in particular to a method for treating water seepage prevention of a rabbet pipe connecting port of a reinforced concrete pipe.

Background

Concrete pipes are pipes made of concrete or reinforced concrete in bulk and used for transporting fluids such as water, oil, gas, etc. The concrete pipe can be divided into four types, namely plain concrete pipe, common reinforced concrete pipe, self-stress reinforced concrete pipe and prestressed concrete pipe. For transporting fluids such as water, oil, gas, etc. Concrete pipes are classified into plain concrete pipes, ordinary reinforced concrete pipes, self-stressed reinforced concrete pipes, and prestressed concrete pipes. According to the different inner diameters of concrete pipes, the concrete pipes can be divided into small-diameter pipes (with the inner diameter below 400 mm), medium-diameter pipes (with the inner diameter below 400 mm) and large-diameter pipes (with the inner diameter above 1400 mm). The pressure pipe can be divided into low pressure pipe and pressure pipe according to the difference of the water pressure bearing capacity of the pipe, and the working pressure of the pressure pipe is generally 0.4, 0.6, 0.8, 1.0, 1.2 MPa and the like. Concrete pipes are classified into plain pipes, spigot-and-socket pipes, and tongue-and-groove pipes, depending on the type of pipe joint. The joint forms comprise a cement mortar smearing joint, a steel wire mesh cement mortar smearing joint, cement mortar socket joints, rubber ring socket joints and the like.

After the ordinary reinforced concrete pipe rabbet pipes are connected, water seepage of the connecting ports is often caused due to the fact that the connecting positions are not sealed in place, the later maintenance cost is extremely high, long-time low-cost stable operation of related building facilities is not facilitated, a method for performing water seepage prevention treatment on the rabbet pipes is adopted, and the water seepage prevention effect is not obvious.

Disclosure of Invention

Technical problem to be solved

Aiming at the defects of the prior art, the invention provides a method for treating water seepage of a rabbet pipe connecting port of a reinforced concrete pipe, which solves the problems that after the rabbet pipe of the common reinforced concrete pipe is connected, the connecting port is prone to water seepage due to the fact that the joint is not sealed in place, the later maintenance cost is extremely high, long-time low-cost stable operation of related building facilities is not facilitated, and the water seepage prevention effect is not obvious due to the fact that a water seepage prevention treatment method is adopted for the rabbet pipe.

(II) technical scheme

In order to achieve the purpose, the invention is realized by the following technical scheme: a method for treating the seepage prevention of a rabbet pipe connector of a reinforced concrete pipe specifically comprises the following steps:

step 1: basic treatment of reinforced concrete pipes: sleeving a fixing sleeve in the middle of the reinforced concrete pipe, hoisting the reinforced concrete pipe in the middle of the reinforced concrete pipe by using a crane, wiping the surface and the joint of the rabbet pipe of the reinforced concrete pipe, removing impurities and large-particle dust, plugging and leveling honeycombs, holes and cracks at the joint by using plugging mortar, removing sharp edges and bulges, completely checking the honeycomb, holes and cracks after cleaning, and fully wetting the surface of the joint by using water before formal work;

step 2: basic application of waterproof adhesive: adding high molecular polymer powder, synthetic rubber, synthetic styrene ester, a dispersing agent, a defoaming agent and a surfactant into a reaction kettle, fully stirring, heating the mixture, keeping the temperature for 10-20 minutes when the temperature is heated to 45-55 ℃, and uniformly coating the liquid mixed waterproof adhesive on the surface of a joint by using a rag;

and step 3: preliminary installation of leak protection felt cloth: after the two rabbet pipes of the reinforced concrete pipe to be connected are coated with a waterproof adhesive, the rabbet pipes are manually aligned and clamped, then the leakproof felt cloth on one side is firstly fixed on the outer side of the joint, and the leakproof felt cloth rotates for 1.5 to 2.5 circles around the reinforced concrete pipe;

and 4, step 4: installation of double-layer felt cloth: after the first layer of leakage-proof felt cloth is installed, waiting for 10-15 minutes, uniformly coating a waterproof adhesive on the surface of the first layer of leakage-proof felt cloth, then installing waterproof felt cloth on the surface of the adhesive, and after winding is finished, detecting whether the surfaces of the two connecting pipelines are positioned on the same horizontal line;

and 5: sampling test after cloth installation: and after the complete installation, placing the reinforced concrete pipe tongue-and-groove pipe in the material bin, sampling and testing the reinforced concrete pipe before transferring, and marking and detecting products in the same batch one by one after finding unqualified products.

Preferably, in the step 1, the delayed coagulation type plugging slurry is applied to the loose and porous base surface for smoothing.

Preferably, in the step 2, the heating can be performed only after the material is completely added.

Preferably, in the step 2, a painting brush operation must be used when the waterproof adhesive is applied, and the painting directions of each layer are perpendicular to each other.

Preferably, in the step 4, the number of winding turns of the anti-leakage felt cloth is equal to that in the step 3.

Preferably, in the step 5, the sampling test is specifically performed by using an equidistant sampling method.

Preferably, in step 3, when the asphalt felt is rotated around the reinforced concrete pipe, the anti-leakage asphalt felt on the surface of the reinforced concrete pipe needs to be manually tensioned.

Preferably, in the step 2, the material is heated in a water-proof manner.

(III) advantageous effects

The invention provides a method for treating water seepage prevention of a rabbet pipe connecting port of a reinforced concrete pipe. Compared with the prior art, the method has the following beneficial effects:

(1) the treatment method for preventing the reinforced concrete pipe rabbet pipe connecting port from leaking water comprises the following steps of 1: basic treatment of reinforced concrete pipes: sleeving a fixing sleeve in the middle of the reinforced concrete pipe, hoisting the reinforced concrete pipe in the middle of the reinforced concrete pipe by using a crane, wiping the surface and the joint of the rabbet pipe of the reinforced concrete pipe, removing impurities and large-particle dust, plugging and leveling honeycombs, holes and cracks at the joint by using plugging mortar, removing sharp edges and bulges, completely checking the honeycomb, holes and cracks after cleaning, and fully wetting the surface of the joint by using water before formal work; step 2: basic application of waterproof adhesive: adding high molecular polymer powder, synthetic rubber, synthetic styrene ester, dispersant, defoaming agent and surfactant into a reaction kettle, after fully stirring the mixture, heating the mixture to 45-55 ℃, keeping for 10-20 minutes, uniformly coating the liquid mixed waterproof adhesive on the surface of the joint by using a rag, through the combined arrangement of the step 1 and the step 2, the unqualified surface joint of the rabbet pipe of the reinforced concrete pipe is effectively cleaned, the connection between the two pipes is smoother in the later period, meanwhile, the joint is moistened by moisture, so that the waterproof adhesive can be more uniformly coated, meanwhile, the waterproof adhesive and the reinforced concrete pipe are uniformly and crossly coated, so that the waterproof adhesive has stronger connecting force, the phenomenon that the waterproof adhesive is coated too thickly is avoided, and cracks caused by large local thickness difference are reduced.

(2) The treatment method for preventing the reinforced concrete pipe rabbet pipe connecting port from leaking water comprises the following steps of 3: preliminary installation of leak protection felt cloth: after the two rabbet pipes of the reinforced concrete pipe to be connected are coated with a waterproof adhesive, the rabbet pipes are manually aligned and clamped, then the leakproof felt cloth on one side is firstly fixed on the outer side of the joint, and the leakproof felt cloth rotates for 1.5 to 2.5 circles around the reinforced concrete pipe; and 4, step 4: installation of double-layer felt cloth: after the first layer of leakproof felt cloth is installed, after waiting for 10-15 minutes, waterproof adhesive is uniformly coated on the surface of the first layer of leakproof felt cloth, waterproof felt cloth is installed on the surface of the adhesive, after winding is finished, whether the surfaces of the two connecting pipelines are positioned on the same horizontal line is detected, and through the combined arrangement of the step 3 and the step 4, the waterproof performance of the reinforced concrete pipe rabbet pipe can be further improved through the installation of the felt cloth.

(3) The treatment method for preventing the rabbet pipe connector of the reinforced concrete pipe from leaking water comprises the following steps of: sampling test after cloth installation: after the complete installation, the reinforced concrete pipe tongue-and-groove pipe is placed in the material bin, the reinforced concrete pipe is subjected to sampling test before transportation, after unqualified products are found, the products in the same batch are marked and detected one by one, and through the step 5, after the materials are completely processed, the unqualified products can be confirmed through scientific sampling inspection of the reinforced concrete pipe, so that the low efficiency caused by the one-by-one inspection of all the products is avoided, meanwhile, the operation is simple, and the implementation of workers is facilitated.

Detailed Description

The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the attached tables in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.

Referring to table 1, the embodiment of the present invention provides three technical solutions: a method for treating the seepage prevention of a rabbet pipe connector of a reinforced concrete pipe specifically comprises the following embodiments:

7页详细技术资料下载
上一篇:一种医用注射器针头装配设备
下一篇:一种增强聚乙烯缠绕复合管

网友询问留言

已有0条留言

还没有人留言评论。精彩留言会获得点赞!

精彩留言,会给你点赞!