Construction method of peat soil foundation

文档序号:1068574 发布日期:2020-10-16 浏览:12次 中文

阅读说明:本技术 泥炭土地基的施工方法 (Construction method of peat soil foundation ) 是由 张奇 丁明鹤 秦夏强 许海岩 王洋 苗闫闫 于 2020-07-16 设计创作,主要内容包括:本发明提供了一种泥炭土地基的施工方法,该方法包括如下步骤:确定步骤,确定泥炭土地基的处理区域;起始层填筑步骤,向处理区域填筑具有第一预设粒径的块石至第一预设程度,并碾压夯实,以形成起始层;摊铺步骤,在起始层上摊铺隔离层;先锋层填筑步骤,在隔离层上填筑具有第二预设粒径的块石至第二预设程度,以形成先锋层;铺设步骤,在先锋层上铺设路基。本发明中,通过在泥炭土地基上填筑块石来对泥炭土进行挤压清除,有效地利用了泥炭土的特性,无需挖除不合格的地基进行置换,也无需在勘察阶段进行取样,本实施例能够有效提高泥炭土地基整体的稳定性和施工安全,降低了工程成本。(The invention provides a construction method of a peat soil foundation, which comprises the following steps: a determination step of determining a processing area of a peat soil foundation; an initial layer filling step, filling the processing area with rock blocks with a first preset grain diameter to a first preset degree, and rolling and tamping to form an initial layer; paving, namely paving an isolation layer on the initial layer; a pioneer layer filling step of filling rock blocks with a second preset particle size on the isolation layer to a second preset degree to form a pioneer layer; and a paving step, namely paving a roadbed on the pioneer layer. According to the invention, the peat soil is extruded and removed by filling the rock blocks on the peat soil foundation, so that the characteristics of the peat soil are effectively utilized, unqualified foundations do not need to be dug and replaced, sampling in a survey stage is also not needed, the embodiment can effectively improve the overall stability and construction safety of the peat soil foundation, and the engineering cost is reduced.)

1. A construction method of a peat soil foundation is characterized by comprising the following steps:

a determination step of determining a processing area of a peat soil foundation;

an initial layer filling step of filling the processing area with rock blocks with a first preset grain size to a first preset degree, and rolling and tamping to form an initial layer;

paving, namely paving an isolation layer on the initial layer;

a pioneer layer filling step of filling rock blocks having a second predetermined particle size to a second predetermined degree on the isolation layer to form a pioneer layer;

and a paving step, namely paving a roadbed on the pioneer layer.

2. The method of constructing a peat soil foundation according to claim 1, wherein the initial layer filling step further comprises:

a selecting substep, namely, randomly selecting a construction area with a preset area in the processing area, and cleaning the construction area; wherein the processing region comprises: a plurality of said construction areas;

filling, namely filling rock blocks with a first preset particle size into the construction area to a first preset degree, and removing peat soil extruded during filling;

a rolling substep, wherein the filled rock blocks with a first preset grain diameter are rolled and tamped;

and repeating the steps to fill the rest construction areas in the treatment area with the lump stones with the first preset grain diameter, and rolling and tamping the lump stones.

3. The peat soil foundation construction method according to claim 2, wherein, in the filling sub-step,

and pouring the rock blocks with the first preset particle size from the middle of the construction area to two sides, rolling and flattening the filled rock blocks with the first preset particle size, and repeating the steps until the filled rock blocks with the first preset particle size reach a first preset degree.

4. The method of constructing a peat soil base according to claim 2 or 3, characterised in that the first predetermined degree is 300mm above water level.

5. The peat soil foundation construction method according to claim 2, wherein, in the grinding sub-step,

leveling the filled block stone with a first preset particle size, and filling and compacting gaps of the block stone;

rolling from the middle of the filled rock block with the first preset grain size to two sides, and stopping rolling when a preset rolling degree is reached.

6. The method of constructing a peat soil base as claimed in claim 5, wherein, in the sub-step of rolling,

when the filled stone blocks with the first preset grain size are rolled, at least a preset distance is overlapped by rolling tracks every time, and the preset rolling degree is that the stone blocks with the first preset grain size slightly move or do not move.

7. The method of constructing a peat soil base as claimed in claim 1, wherein in the paving step,

the isolating layer is made of geotextile with preset strength;

the isolation layer is a plurality of, every the isolation layer is all laid along the horizontal cross section of road bed to, along adjacent two on the longitudinal direction of road bed have preset overlap joint length between the isolation layer.

8. The method of constructing a peat soil foundation according to claim 1, wherein the step of filling the pioneer layer further comprises:

a determining substep, namely measuring lofting and determining a roadbed filling central line, a side line and an ultra-wide filling side line;

drawing a filling grid line according to the roadbed filling central line, the side line and the ultra-wide filling side line;

and a rock block filling sub-step, wherein the rock blocks with the second preset particle size are paved on each grid in sequence according to the filling grid lines, and the rock blocks with the second preset particle size paved in each grid are leveled and rolled until reaching a second preset degree, and the filling of the grid is stopped.

9. The method of constructing a peat soil base according to claim 8, wherein in the substep of filling rock,

and filling longitudinally along the roadbed, paving the block stones with the second preset particle size from low to high in the transverse direction of the roadbed, flattening and rolling the paved block stones with the second preset particle size until the paving thickness reaches 300mm, and stopping filling when the compaction thickness is less than or equal to 225 mm.

10. The method of constructing a peat soil base as claimed in claim 8, wherein the step of filling the rock is followed by the step of:

and a sub-step of installation, namely installing a settlement observation plate at intervals of a preset distance along the position of the center line of the roadbed.

Technical Field

The invention relates to the technical field of roadbeds, in particular to a construction method of a peat soil foundation.

Background

The peat soil is soil which is deposited on low plain lands of certain rivers and lakes and in valley lands between mountains, has dense aquatic vegetation due to long-term water accumulation, and is formed into a peat layer by accumulating a large amount of insufficiently decomposed plant residues under the condition of oxygen deficiency. The peat soil comprises at least the following characteristics: the peat soil is different from other soft soil, and has three remarkable characteristics of high water content, high compressibility and low strength; and secondly, the peat soil soft foundation is in a fluid plastic state in a natural physical state. Based on the characteristics of peat soil, when peat soil foundations are treated, unqualified foundations are usually removed and replaced. However, when unqualified foundations are excavated, sampling in the early exploration stage is difficult, the judgment result is easily influenced, and the excavation and replacement cannot be accurately performed, so that the design and the processing in the later stage are influenced.

Disclosure of Invention

In view of the above, the invention provides a construction method of a peat soil foundation, and aims to solve the problem that in the prior art, accurate judgment cannot be performed when unqualified foundations are excavated and replaced.

The invention provides a construction method of a peat soil foundation, which comprises the following steps: a determination step of determining a processing area of a peat soil foundation; an initial layer filling step, filling the processing area with rock blocks with a first preset grain diameter to a first preset degree, and rolling and tamping to form an initial layer; paving, namely paving an isolation layer on the initial layer; a pioneer layer filling step of filling rock blocks with a second preset particle size on the isolation layer to a second preset degree to form a pioneer layer; and a paving step, namely paving a roadbed on the pioneer layer.

Further, in the above construction method of peat soil foundation, the step of filling the initial layer further comprises: a selecting substep, namely, randomly selecting a construction area with a preset area in the processing area, and cleaning the construction area; wherein the processing region includes: a plurality of construction areas; filling, namely filling rock blocks with a first preset particle size into a construction area to a first preset degree, and removing peat soil extruded during filling; a rolling substep, wherein the filled rock blocks with a first preset grain diameter are rolled and tamped; and repeating the steps to fill the rest construction areas in the treatment area with the lump stones with the first preset grain diameter, and rolling and tamping the lump stones.

Further, in the construction method of the peat soil foundation, in the sub-step of filling, the rock blocks with the first preset grain size are poured from the middle of the construction area to the two sides, the filled rock blocks with the first preset grain size are rolled and leveled, and the step is repeated until the filled rock blocks with the first preset grain size reach the first preset degree.

Further, in the construction method of the peat soil foundation, the first preset degree is 300mm above the water elevation.

Furthermore, in the construction method of the peat soil foundation, in the sub-step of rolling, the filled rock blocks with the first preset grain size are leveled, and gaps of the rock blocks are densely filled; rolling from the middle of the filled rock block with the first preset grain size to two sides, and stopping rolling when a preset rolling degree is reached.

Further, in the sub-step of rolling, when the filled rock blocks with the first preset grain size are rolled, at least a preset distance is overlapped on each rolling trace, and the preset rolling degree is that the rock blocks with the first preset grain size have small movement or no movement.

Further, in the construction method of the peat soil foundation, in the paving step, the isolation layer is geotextile with preset strength; the isolation layer is a plurality of, and every isolation layer is all laid along the horizontal cross section of road bed to, have preset overlap joint length between two adjacent isolation layers in the longitudinal direction along the road bed.

Further, in the above construction method of peat soil foundation, the step of filling the pioneer layer further comprises: a determining substep, namely measuring lofting and determining a roadbed filling central line, a side line and an ultra-wide filling side line; drawing substeps, drawing filling grid lines according to the roadbed filling central lines, the side lines and the ultra-wide filling side lines; and a rock block filling sub-step, wherein the rock blocks with the second preset particle size are paved on each grid in sequence according to filling grid lines, and the rock blocks with the second preset particle size paved in each grid are leveled and rolled until reaching a second preset degree, and the filling of the grid is stopped.

Further, in the construction method of the peat soil foundation, in the step of filling the rock blocks, the rock blocks are filled along the longitudinal direction of the roadbed, the rock blocks with the second preset grain size are paved from low to high in the transverse direction of the roadbed, and the paved rock blocks with the second preset grain size are leveled and rolled until the paving thickness reaches 300mm, and the filling is stopped when the compaction thickness is less than or equal to 225 mm.

Further, in the above construction method of peat soil foundation, the step of filling rock lumps further includes: and a sub-step of installation, namely installing a settlement observation plate at preset intervals along the center line of the roadbed.

According to the invention, the peat soil foundation treatment area is filled with the rock blocks with the first preset grain size, and is rolled and tamped to form the initial layer, the isolation layer is paved on the initial layer, and then the isolation layer is filled with the rock blocks with the second preset grain size to form the pioneer layer, so that the peat soil is squeezed and removed by filling the rock blocks on the peat soil foundation, the characteristics of the peat soil are effectively utilized, unqualified foundations do not need to be dug and replaced, sampling is not needed in a reconnaissance stage, and the problem that in the prior art, accurate judgment cannot be carried out when unqualified foundations are dug and replaced is solved.

Drawings

Various other advantages and benefits will become apparent to those of ordinary skill in the art upon reading the following detailed description of the preferred embodiments. The drawings are only for purposes of illustrating the preferred embodiments and are not to be construed as limiting the invention. Also, like reference numerals are used to refer to like parts throughout the drawings. In the drawings:

FIG. 1 is a flow chart of a method for constructing a peat soil base according to an embodiment of the present invention;

FIG. 2 is a flow chart illustrating an initial layer filling step in a method for constructing a peat soil foundation according to an embodiment of the present invention;

FIG. 3 is a flow chart of a step of filling a pioneer layer in the method for constructing a peat soil foundation according to an embodiment of the present invention;

FIG. 4 is a flow chart showing a step of filling a pioneer layer in the method for constructing a peat soil foundation according to the embodiment of the present invention;

FIG. 5 is a schematic top view illustrating a step of filling an initial layer in the method for constructing a peat soil foundation according to an embodiment of the present invention;

FIG. 6 is a schematic structural view illustrating a cleaning step in a method for constructing a peat soil base according to an embodiment of the present invention;

FIG. 7 is a schematic view of a construction area in a method for constructing a peat soil base according to an embodiment of the present invention;

FIG. 8 is a schematic structural view of a filling rock in a method for constructing a peat soil foundation according to an embodiment of the present invention;

fig. 9 is a schematic structural view illustrating a completion of filling of an initial layer in the method for constructing a peat soil foundation according to the embodiment of the present invention;

fig. 10 is a schematic structural view of a completed pioneer layer in a method for constructing a peat soil foundation according to an embodiment of the present invention;

fig. 11 is a schematic structural view of a roadbed in the construction method of the peat soil foundation according to the embodiment of the present invention.

Detailed Description

Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. While exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be embodied in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the disclosure to those skilled in the art. It should be noted that the embodiments and features of the embodiments may be combined with each other without conflict. The present invention will be described in detail below with reference to the embodiments with reference to the attached drawings.

Referring to fig. 1, fig. 1 is a flow chart illustrating a method for constructing a peat soil base according to an embodiment of the present invention. As shown in the figure, the construction method of the peat soil foundation comprises the following steps:

the determination step S1 determines a processing area of the peat soil base.

Specifically, referring to fig. 5, site lofting is performed according to a construction drawing, and a treatment area 1 where a peat soil foundation needs to be treated is determined. Then, the temporary sidewalk 2 entering the processing area 1 is paved, the temporary sidewalk 2 is disposed at one side of the processing area 1, and the transport vehicle travels on the temporary sidewalk 2 to construct the processing area 1.

An initial layer filling step S2 fills the processing area with stones having a first predetermined grain size to a first predetermined degree, and rolls and tamps to form an initial layer.

Specifically, the handling area 1 is filled with the rock blocks 4 with the first preset particle size through the transport vehicle, and the rock blocks 4 with the first preset particle size are filled and rolled from the middle to two sides gradually during filling, so that the rock blocks 4 with the first preset particle size are tightly filled, the stability of the initial layer is ensured, and the movement is avoided. In specific implementation, the first preset particle size is not more than 500mm, and a specific value can be determined according to actual conditions, which is not limited in this embodiment.

Referring to fig. 2, the start-layer filling step S2 may further include:

a selecting substep S21 of selecting a construction area with a preset area at any time in the processing area and cleaning the construction area; wherein the processing region includes: a plurality of construction areas.

Specifically, a plurality of construction areas 6 form one processing area 1, and in specific implementation, one construction area 6 with a preset area can be arbitrarily selected according to actual conditions. In specific implementation, the preset area may be determined according to actual conditions, and this embodiment does not limit this. In this embodiment, the predetermined area is 5m × 5 m. Referring specifically to fig. 7, only 4 construction areas 6 are shown, and other construction areas 6 may be selected according to actual situations.

Referring to fig. 6 and 7, a long-arm excavator is adopted to stand at the temporary sidewalk 2, the construction area 6 is cleaned, i.e., weeds, trees and the like on the original ground in the construction area 6 are removed, and then the removed weeds, trees and the like are transported out to a spoil area by an earth moving vehicle. The arrow direction at the temporary access 2 in fig. 7 indicates the vehicle traveling direction, and the arrow direction at the processing area 1 indicates the direction in which the remaining construction area is selected.

And a filling substep S22 of filling rock blocks with a first preset grain size into the construction area to a first preset degree and removing the peat soil extruded during filling.

Specifically, the rock block 4 with the first preset grain size is poured from the middle of the construction area 6 to the two sides, the filled rock block 4 with the first preset grain size is rolled and leveled, and the steps are repeated until the filled rock block 4 with the first preset grain size reaches a first preset degree.

More specifically, referring to fig. 8, the lump stones 4 having the first preset grain size are dumped to any one of the construction areas 6 using an earth moving vehicle. In the construction area 6, the soil blocks slowly topple from the middle part of the construction area 6 to the two sides of the construction area 6 during toppling, the bottom and the peripheral peat soil are squeezed to the edge along with the dead weight of the rock blocks 4 with the first preset grain diameter, and then the peat soil squeezed out of the periphery of the construction area 6 is transported to a soil abandonment site by using a earthwork vehicle. And (3) rolling and flattening the filled rock blocks 4 with the first preset particle size by using an excavator, wherein the rock blocks can settle and diffuse around, and then continuously and intensively filling the rock blocks 4 with the first preset particle size, and rolling and flattening by using the excavator. And repeating the steps of dumping the rock blocks and rolling and flattening until the height of the filled rock blocks 4 with the first preset grain diameter reaches a first preset degree. Wherein, first degree of predetermineeing is 300mm above the water elevation. The position of the ground water level 3 is shown in fig. 5.

And a rolling substep S23 of rolling and tamping the filled rock lumps with the first preset grain size.

Specifically, firstly, the filled rock blocks with a first preset grain size are leveled, and gaps of the rock blocks are densely filled. Then, rolling is performed from the middle of the filled rock block with the first preset grain size to both sides, and the rolling is stopped when a preset rolling degree is reached.

More specifically, the lump stones 4 with the first preset particle size are firstly preliminarily leveled by an excavator, and the gaps of the lump stones are densely filled with the lump stones 4 with the first preset particle size. In specific implementation, the gap is compacted by using the stone blocks with the grain diameter of 40 mm. Then, rolling is performed by a road roller with the grain size not less than 8t, and rolling is performed from the middle of the filled rock 4 with the first preset grain size to two sides gradually.

When the filled rock blocks 4 with the first preset grain size are rolled, at least a preset distance is overlapped by the rolling tracks each time, and the preset rolling degree is that the rock blocks with the first preset grain size slightly move or do not move. In specific implementation, the preset overlapping distance may be determined according to actual conditions, and this embodiment does not limit this. In the present embodiment, the predetermined distance is 300 mm. Specifically, when the roller compaction is carried out by a roller compactor with the weight not less than 8t, the wheel tracks of each roller compaction are overlapped by at least 300mm, and the roller compaction can be stopped until no obvious movement exists.