Rapid threading pipeline and threading method for temporary road

文档序号:1732522 发布日期:2019-12-20 浏览:30次 中文

阅读说明:本技术 一种临时道路快速穿线管路及穿线方法 (Rapid threading pipeline and threading method for temporary road ) 是由 马凯青 宋志强 于 2019-09-16 设计创作,主要内容包括:本发明提供一种临时道路快速穿线管路及穿线方法,包括:第一槽钢、第二槽钢。第一槽钢的闭口端埋入混凝土路面内,第一槽钢的开口端设置于第二槽钢的开口端内侧;第二槽钢的闭口端与混凝土路面的表面齐平;线路设置于第一槽钢与第二槽钢围成的腔体内。本发明还提出临时道路快速穿线管路的穿线方法。本发明为活动式上下对接口,方便布线施工和后期维修,提高施工效率;根据需要铺筑的线路规格、数量调整该管路的规格、数量,布线工作更合理有效、操作方便、适用性强;设计合理,施工时不需拆除,保证施工质量、加快施工进度。(The invention provides a temporary road rapid threading pipeline and a threading method, comprising the following steps: the first channel steel and the second channel steel. The closed end of the first channel steel is embedded into the concrete pavement, and the open end of the first channel steel is arranged at the inner side of the open end of the second channel steel; the closed end of the second channel steel is flush with the surface of the concrete pavement; the circuit sets up in the cavity that first channel-section steel and second channel-section steel enclose. The invention further provides a threading method of the temporary road quick threading pipeline. The invention is a movable upper and lower butt joint, which is convenient for wiring construction and later maintenance and improves the construction efficiency; the specification and the number of the pipelines are adjusted according to the specification and the number of the lines to be paved, so that the wiring work is more reasonable and effective, the operation is convenient, and the applicability is strong; reasonable in design need not demolish during the construction, guarantees construction quality, accelerates the construction progress.)

1. A temporary road quick threading line comprising:

the closed end of the first channel steel (1) is embedded into the concrete pavement (3);

the closed end of the second channel steel (2) is flush with the surface of the concrete pavement (3), and the open end of the second channel steel (2) is arranged on the open end of the first channel steel (1); the circuit (4) is arranged in a cavity surrounded by the first channel steel (1) and the second channel steel (2).

2. A temporary road quick threading line as claimed in claim 1, wherein:

the opening end of the first channel steel (1) is arranged on the inner side of the opening end of the second channel steel (2).

3. A temporary road quick threading line as claimed in claim 2, wherein:

the second channel steel (2) is provided with a mechanism which enables the second channel steel (2) to relatively lift relative to the first channel steel (1).

4. A temporary road quick threading pipe according to any one of claims 1 to 3, characterized in that:

a wiring groove is formed in the bottom of the inner side of the first channel steel (1).

5. A temporary road quick threading pipe according to any one of claims 1 to 3, characterized in that:

the first channel steel (1) and the second channel steel (2) are angle steels.

6. A method of threading a temporary road quick threading pipe, comprising the threading pipe of any of claims 1 to 5, the steps comprising:

s1: determining the arrangement position and the number of the threading pipelines on a temporary road on which the threading pipelines need to be laid, wherein the arrangement number of the threading pipelines is determined according to the number of the lines (4);

s2: arranging a closed end of the first channel steel (1) at the arrangement position, wherein an open end of the first channel steel (1) faces upwards, and an open end of the second channel steel (2) is arranged at an open end of the first channel steel (1); the height of the assembly consisting of the first channel steel (1) and the second channel steel (2) is consistent with the thickness of the concrete pavement (3), and the closed end of the second channel steel (2) is flush with the surface of the concrete pavement (3);

s3: pouring the concrete pavement (3), and vibrating and compacting concrete around the first channel steel (1) and the second channel steel (2);

s4: within 1 hour after the initial setting of the concrete, operating a control mechanism to move the second channel steel (2) up and down relative to the first channel steel (1) so as to ensure that the second channel steel (2) can move up and down in the arrangement position after the concrete is solidified; at the moment, the first channel steel (1) and the second channel steel (2) are combined into a vertically movable open pipeline;

s5: during wiring construction, the second channel steel (2) is removed, and the line (4) is arranged at the bottom of the inner side of the first channel steel (1) or in a wiring groove;

s6: and after the wiring construction is finished, the second channel steel (2) is put back to the original position, and the later construction is continued.

Technical Field

The invention belongs to the technical field of building construction, and particularly relates to a temporary road rapid threading pipeline and a threading method.

Background

With the increasing number of projects being built, the workload of arranging the lines is correspondingly increased. During construction on site, some lines are often required to be temporarily arranged for the requirements of construction site, and some lines need to pass through temporary roads. Therefore, in order to ensure that the subsequent construction of the temporary road and the normal use in the later period of the threading pipeline are not influenced, the threading pipeline needs to be embedded in the temporary road in advance during wiring construction.

In the prior art, one of the pre-laid threading pipelines is a closed pipeline, and a plurality of cables or electric wires are threaded from head to tail in the pipeline. The operation mode easily causes the disorder and knotting of the line, and increases the construction difficulty and the potential safety hazard. The other type is a rubber wire groove plate, the specification of the product is fixed, the number of the wire passing is limited, the rubber wire groove plate must be arranged on the ground surface, and the rubber wire groove plate cannot be buried together with a line to be buried underground during later construction, so that the construction progress is influenced.

Disclosure of Invention

Aiming at the defects of the threading of the existing temporary road, the invention aims to provide a quick threading pipeline for the temporary road, wherein the upper and lower butt joints of the assembly of the threading pipeline are movable, so that the wiring construction and the later maintenance are convenient, and the construction efficiency is improved; the specification and the number of the pipelines are adjusted according to the specification and the number of the lines to be paved, so that the wiring work is more reasonable and effective; the pipeline can be buried in the ground during construction on the same line, does not need to be dismantled, and is more convenient.

In order to solve the technical problems, the invention adopts the technical scheme that:

a temporary road quick threading line comprising:

the closed end of the first channel steel is embedded into the concrete pavement;

the closed end of the second channel steel is flush with the surface of the concrete pavement, and the open end of the second channel steel is arranged on the open end of the first channel steel; the circuit is arranged in a cavity defined by the first channel steel and the second channel steel.

Further, the open end of the first channel steel is arranged on the inner side of the open end of the second channel steel.

Preferably, the second channel is provided with a mechanism for relatively lifting the second channel with respect to the first channel.

More preferably, the bottom of the inner side of each of the first channel steel and the second channel steel is provided with a wiring groove.

Preferably, the first channel steel and the second channel steel are angle steels.

A threading method of a temporary road quick threading pipeline comprises the threading pipeline, and comprises the following steps:

s1: determining the arrangement position and the number of the threading pipelines on a temporary road on which the threading pipelines need to be laid, wherein the arrangement number of the threading pipelines is determined according to the number of the lines;

s2: arranging the closed end of the first channel steel at the arrangement position, wherein the open end of the first channel steel faces upwards, and the open end of the second channel steel is arranged at the open end of the first channel steel; the height of the assembly consisting of the first channel steel and the second channel steel is consistent with the thickness of the concrete pavement, and the closed end of the second channel steel is flush with the surface of the concrete pavement;

s3: pouring the concrete pavement, and closely vibrating the concrete around the first channel steel and the second channel steel;

s4: within 1 hour after the initial setting of the concrete, operating a control mechanism to move the second channel steel up and down relative to the first channel steel, and ensuring that the second channel steel can move up and down in the arrangement position after the concrete is solidified; at the moment, the first channel steel and the second channel steel are combined into an up-down movable open pipeline;

s5: during wiring construction, the second channel steel is moved away, and the line is arranged at the bottom of the inner side of the first channel steel or in a wiring groove;

s6: and after the wiring construction is finished, the second channel steel is put back to the original position, and the later construction is continued.

Due to the adoption of the technical scheme, the temporary road quick threading pipeline can be arranged on the temporary road, then concrete pouring is carried out, then wiring construction is carried out, and finally wiring and later-stage construction are completed. The threading pipeline is a movable upper and lower butt joint, so that the wiring construction and the later maintenance are facilitated, and the construction efficiency is improved; reasonable in design, convenient operation, suitability are strong, need not demolish during the construction, guarantee construction quality, accelerate the construction progress.

Drawings

FIG. 1 is a front view of one embodiment of the present invention

FIG. 2 is a top view of an embodiment of the present invention

In the figure:

1. first channel steel 2, second channel steel 3, concrete road

4. Line

Detailed Description

The invention is further illustrated by the following examples and figures:

in one embodiment of the present invention, as shown in fig. 1 and 2, the temporary road quick threading pipe comprises: the concrete pavement comprises a first channel steel 1, a second channel steel 2, a concrete pavement 3 and a line 4. The closed end of the first channel steel 1 is embedded into the concrete pavement 3, the open end of the first channel steel 1 is arranged at the inner side of the open end of the second channel steel 2, the closed end of the second channel steel 2 is flush with the surface of the concrete pavement 3, and the circuit 4 is arranged in a cavity surrounded by the first channel steel 1 and the second channel steel 2.

Preferably, the first and second electrodes are formed of a metal,

the second channel steel 2 is provided with a mechanism for relatively lifting the second channel steel 2 relative to the first channel steel 1.

More preferably, the bottom of the inner side of each of the first channel steel 1 and the second channel steel 2 is provided with a wiring groove.

Preferably, the first channel steel 1 and the second channel steel 2 are angle steels.

A threading method of a temporary road quick threading pipeline comprises the threading pipeline, and comprises the following steps:

s1: the arrangement position and the number of the threading pipelines are determined in advance on a temporary road where the threading pipelines need to be laid. The arrangement number of the threading pipelines is determined according to the number of required lines, and preferably, the materials of the first channel steel 1 and the second channel steel 2 meet the requirements of a construction site.

S2: the closed end of the first channel steel 1 is fixed at the determined arrangement position, the open end of the first channel steel 1 faces upwards, the open end of the second channel steel 2 is buckled on the open end of the first channel steel 1 in an inverted mode, the height of an assembly formed by the first channel steel 1 and the second channel steel 2 is consistent with the thickness of a concrete pavement 3, and the closed end of the second channel steel 2 is flush with the surface of the concrete pavement 3.

S3: and (3) pouring a concrete pavement 3, and closely vibrating the concrete around the first channel steel 1 and the second channel steel 2.

S4: in 1 hour after the initial set of concrete, the operation control mechanism moves the second channel steel 2 up and down relative to the first channel steel 1, and the second channel steel 2 can move up and down in the arrangement position after the concrete is solidified. At the moment, the first channel steel 1 and the second channel steel 2 are combined into an up-down movable open pipeline.

S5: during wiring construction, the second channel steel 2 is removed, and the line 4 is arranged at the bottom of the inner side of the first channel steel 1 or in a wiring groove.

S6: and after the wiring construction is finished, the second channel steel 2 is put back to the original position, and the later construction is continued.

The temporary road quick threading pipeline provided by the invention is arranged in front of the temporary road, and the movable upper and lower butt joints are convenient for wiring construction and later maintenance, so that the construction efficiency is improved; the specification and the number of the pipelines are adjusted according to the specification and the number of the lines to be paved, so that the wiring work is more reasonable and effective; the pipeline can be buried in the ground during construction on the same line, does not need to be dismantled, and is more convenient.

The embodiments of the present invention have been described in detail, but the description is only for the preferred embodiments of the present invention and should not be construed as limiting the scope of the present invention. All equivalent changes and modifications made within the scope of the present invention shall fall within the scope of the present invention.